Hampshire County Council Item 14
Executive Member Education - 13 May 2004 Major Projects Status Report
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 E-mail: [email protected]
1. Summary
1.1 This report presents an update of the major projects for which appraisals have been approved by the Executive Members for Policy and Resources and Education which are now being progressed through to completion.
1.2 Where necessary, further details of specific action being taken on particular projects will be provided when endorsement or approval is required.
1.3 Appendix 1 shows those capital projects for which an allocation has been made in the Education Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.
2. Schemes Recently Completed
2.1 Since the December 2003 meeting of the Executive Member - Education, schemes at the following schools have been completed and the new accommodation handed over to the County Education Officer. All of these schemes remain financially on target:
SCHOOL COMPLETION DATE
Balksbury Infant and Junior December 2003
Buriton Primary February 2004
Crestwood Community School January 2004
Elvetham Heath Primary February 2004
Henry Beaufort School December 2003
Netley Abbey Junior December 2003
Sharps Copse Primary February 2004
3. Additional Works and Funding Added Post Contract
3.1 The following schemes have had further funding added to the contract for specific additional works.
3.2 Balksbury Infant and Junior Schools
Additional funding of £294,021, excluding fees, has been added to this contract. Of this amount £261,150 was for an extension to the Infant School. Policy and Resources 2003/04 NDS Condition funding has been added to the contract for cladding works to both schools. Work was completed on 4 December 2003.
3.3 Buriton Primary School
A contribution of £27,530, excluding fees, has been made to this contract from the Policy and Resources 2003/04 Capital Repairs budget. This enabled structural repairs to the reception class roof and remedial works to two classrooms. Work was completed on 23 February 2004.
3.4 Calthorpe Park Secondary School
An additional £57,000, excluding fees, has been added to this contract from the Education 2003/04 contingency for the installation of a sub-station at this school. A further £12,000, excluding fees, has been added from the Policy and Resources 2003/04 External Landscaping budget and £3,002, excluding fees, from the Policy and Resources 2003/04 Capital Repairs budget for additional builders work.
3.5 Fernhill Secondary School
A contribution of £20,000, excluding fees, has come from the Policy and Resources 2003/04 External Landscaping budget for enhanced landscaping associated with the new sports hall scheme at this site.
3.6 Sharps Copse Primary School
Additional funding of £18,000, excluding fees, has been added to the contract on this site to provide a new Early Years Centre. £10,000 has come from Policy and Resources 2003/04 External Landscaping budget and £8,000 from the Policy and Resources 2003/04 NDS Condition fund for external lighting and glazing. Work was completed on 2 February 2004.
It is proposed that an additional phase of work be undertaken at this school to provide a Children's Centre. The estimated cost of the scheme is £241,000, excluding fees. Funding for the scheme is subject to confirmation from the County Education Officer following discussion with the Executive Member - Education and details can be found in the Capital Programme Update report elsewhere on this agenda.
Work will comprise the internal refurbishment of one wing of the existing infant school building to provide a Children's Centre. This will include the conversion of two former classrooms to training rooms with a kitchen and servery between. Creation of a multi-use space, toy library, interview / consultation rooms and children's toilets. Extension of the reception area and adult toilets and a link to the main hall and nursery block.
It is intended that this contract be negotiated with Brazier Construction who have previously completed two major programmes of work at this site comprising the amalgamation of the schools and the new Early Years Centre. This course of action was agreed by the Executive Member - Policy and Resources at the April 2004 meeting. It is anticipated that work will commence on site during July 2004 and be completed during October 2004, with external works completing during November 2004.
4. Current Position
4.1 This section gives the summarised position of the major projects, which have already been approved by the Executive Members for Policy and Resources and Education. Those schemes with works on site are reported as being financially on target unless otherwise indicated elsewhere in this report.
4.2 Alderman Quilley and Hounsdown Schools
Due to delays in the NOF funding approval process and the time taken to ensure that the best price is achieved, a revised programme has been agreed for the proposed sports hall schemes at both of these schools. Work will now commence during April 2004 and be completed during October / November 2004.
4.3 Fernhill Secondary School
The scheme at this school to construct a new sports hall was due to complete during February 2004, however, due to changes in the roof specification and issues with acoustic works, to meet new regulations introduced during the design and procurement of the scheme, work will now be completed during March 2004.
4.4 Swanmore Secondary School
The proposed scheme for a flood-lit multi use games area (MUGA) at this school has been delayed awaiting approvals from Winchester City Council who are providing the funding for this scheme. It is anticipated that Winchester City Council will soon be able to commit to their funding and work can commence on site during April / May 2004 with completion during June / July 2004.
4.5 Whitewater Primary School
A change to the Headteacher at this school has resulted in a re-evaluation of the scheme and a slight delay in the proposed programme of work to provide a new school hall at this Primary School. Work will now commence during July with completion anticipated during January 2005.
4.6 Yateley Secondary School
The scheme at this school to construct a new dance studio was due to complete during March 2004. Due to delays associated with the contractor's performance the work is now due to complete during May 2004.
5. NDS Modernisation 2004/05 - School Specialist Accommodation Programme
5.1 At the February 2004 meeting of the Executive Member - Education approval was given to the 2004/05 programme for expenditure of the New Deal for Schools (NDS) Modernisation funding. Included in this programme was funding for the refurbishment of specialist accommodation in secondary schools.
5.2 The work will comprise the refurbishment and upgrade of the existing science laboratory, food technology and textile laboratory accommodation at five schools. Four of the schools will be grouped together in two separate packages. The first package comprises work at Cove and Fernhill Schools and has an estimated value of £594,923, excluding fees. The second package comprises work at Noadswood and Richard Aldworth Schools and has an estimated value of £249,763, excluding fees. The final scheme will be undertaken at Bridgemary School at an estimated cost of £341,723, excluding fees.
5.3 At the February 2004 meeting of the Executive Member - Policy and Resources it was agreed that the two packages would be negotiated with preferred contractors who successfully tendered and completed part of the 2003/04 programme. The third scheme at Bridgemary will be competitively tendered.
5.4 It is anticipated that work at all schools will commence on site during July 2004 and be completed during September 2004.
6. Costello Technology College - Fire Damage Reinstatement
6.1 The purpose of this section of the report is to advise Members of a package of fire reinstatement works that have been implemented following a fire that broke out on the evening of 5 December 2003 at Costello Technology College. The fire destroyed the single storey technology building and attached two storey maths building.
6.2 The Chief Executive's department has authorised the Director of Property, Business and Regulatory Services to undertake a package of fire reinstatement work and that the cost be a charge against the County Council`s Fire Reinstatement budget.
6.3 The work to date has comprised the removal of asbestos from the remains of both buildings, followed by the demolition of the buildings and clearance of the site. Temporary buildings have been placed on site to accommodate pupils until permanent accommodation is constructed in the future.
6.4 The value of the work already undertaken to date is £489,000, excluding fees.
Recommendations
1. That the position of the major projects being undertaken by the Director of Property, Business and Regulatory Services be noted.
2. That the action being taken following a fire a Costello Technology College be endorsed.
3. That the Executive Member - Education approves the action being taken at various secondary schools under the NDS Modernisation 2004/05 School Specialist Accommodation Programme, in particular the scheme at Bridgemary Secondary School at a value of £365,000, excluding fees.
4. That the Executive Member - Education approves the proposal to undertake a scheme at Sharps Copse Primary School to provide a Children's Centre, subject to the agreement of funding arrangements detailed in the County Education Officer's Capital Programme Update report elsewhere on the agenda.
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS
Tender schedules
MAJOR PROJECT STATUS REPORT
School |
Current Status |
Start |
Complete |
Funding/ * Contract Sum £ |
Source of Funding £ |
Alderman Quilley Secondary School, Eastleigh - NOF Sports Hall |
Tender Analysis |
Apr 04 |
Oct 04 |
1,272,000 |
New Opportunities Fund 1,230,000 School - Devolved Capital 42,000 1,272,000 |
Amery Hill Secondary School, Alton - extension to provide basic need accommodation, refurbishment works and synthetic turf pitch |
On site |
Jan 04 |
Nov 04 |
* 2,937,388 |
Education Capital 03/04 1,599,388 Eggars Trust 688,000 School - Devolved Capital 242,000 P&R Capital Repairs 03/04 408,000 2,937,388 |
Balksbury Infant and Junior Schools, Andover - extensions for basic need, Key Stage 2, IT & Staff accommodation |
Complete |
Feb 03 |
Dec 03 |
* 788,060 add 294,021 1,082,081 |
Education Capital 02/03 504,994 Education Capital 03/04 156,600 NDS Modernisation 03/04 149,000 Staff Workplaces 03/04 26,000 SAI 03/04 10,300 Temp classroom hire budget 10,000 Junior School 124,218 Infant School 79,326 P&R NDS Condition 03/04 21,643 1,082,081 |
Bay House Secondary School, Gosport - extension to provide sixth form accommodation |
On site |
Jan 04 |
Aug 04 |
* 651,500 |
Education Capital 03/04 591,500 School 60,000 651,500 |
Brookfield Community School, Sarisbury Green - Performing Arts Block |
On Site |
Oct 03 |
Sept 04 |
* 1,410,961 |
Education Capital 03/04 930,000 School 480,961 1,410,961 |
Brune Park Community School, Gosport - Extension to provide a new dance studio and dining hall |
Design |
June 04 |
Feb 05 |
1,101,000 |
Education Capital 03/04 849,000 School - Devolved Capital 80,000 Public Service Agreement Funding 172,000 1,101,000 |
Buriton Primary School, Petersfield - extension to provide Key Stage 2 accommodation and removal of temporary building |
Complete |
Mar 03 |
Feb 04 |
* 485,576 add 27,530 513,106 |
Education Capital 02/03 216,000 Key Stage 2 02/03 183,000 School 86,576 P&R Capital Repairs 03/04 27,530 513,106 |
Calthorpe Park Secondary School, Fleet - extension to provide 113 basic need places |
On site |
May 03 |
Mar 04 |
*1,201,500 add 72,002 1,273,502 |
Education Capital 02/03 1,192,000 101,067 F&E Budget 30,000 School 33,000 P&R NDS Condition 03/04 3,500 P&R External Works 03/04 12,000 P&R Capital Repairs 03/04 3,002 1,273,502 |
Chalk Ridge Primary School, Basingstoke - extension to provide two new classrooms and a new library |
Tender Analysis |
Mar 04 |
Aug 04 |
447,000 |
Basingstoke Reorg Fund 379,500 School 67,500 447,000 |
Cherrywood Community Primary School, Farnborough - new Community Primary School |
On Site |
Aug 03 |
June 04 |
*1,217,221 |
Education Capital 02/03 1,145,669 School 71,552 1,217,221 |
Crestwood Community School, Eastleigh - Synthetic Turf Pitch |
Complete |
Sept 03 |
Jan 04 |
* 338,127 |
Schools Balance Loan Scheme 338,127 |
Eggars School, Alton - IT block, Sports Hall and internal refurbishment |
Design |
May 04 |
May 05 |
1,669,000 |
Education Capital 03/04 743,000 NDS Modernisation 03/04 65,000 School 173,000 Eggars Trust Fund 688,000 1,669,000 |
Elvetham Heath Primary School, Fleet - new Primary School |
Complete |
Aug 02 |
Feb 04 |
* 2,118,773 |
Education Capital 02/03 2,118,773 |
Elvetham Heath Primary School, Fleet - 2FE Extension |
On site |
Feb 04 |
Sept 04 |
* 1,123,492 |
Education Capital 03/04 1,123,492 |
Fernhill Secondary School, Farnborough - new Sports Hall |
On Site |
Aug 03 |
Mar 04 |
* 1,298,405 add 20,000 1,318,405 |
New Opportunities Fund 1,016,509 Education Capital 03/04 196,896 P&R External Works 03/04 45,000 Rushmoor BC 18,000 School - Devolved Capital 42,000 1,318,405 |
Fordingbridge Infant School, Fordingbridge - 2 classroom extension, music room, library and IT area. |
Contract Formation |
Mar 04 |
Sep 04 |
566,000 |
NDS Modernisation 03/04 524,000 School - Devolved Capital 42,000 566,000 |
Frogmore Community College, Yateley - Two classroom, Music Room, Library and IT area extension |
Design |
May 04 |
Dec 04 |
648,000 |
Education Capital 03/04 648,000 |
Grateley Primary School - new school hall |
Design |
May 04 |
Oct 04 |
419,000 |
Education Capital 03/04 374,000 School 45,000 419,000 |
Hamble Community Sports College - new gymnasium and refurbishment/ remodelling - Gymnasium |
On Site |
Aug 03 |
Mar 04 Jul 04 |
* 1,990,000 |
Education Capital 03/04 604,000 Less funding for other works -155,000 Sport England 691,000 School 330,000 Dynamo Gymnastics 57,000 Eastleigh Borough Council 44,000 Hampshire Playing Fields Ass. 11,000 Dynamo Fundraising 29,000 P&R Lottery partnership 18,000 P&R Capital Repairs 03/04 280,000 P&R Fire Precautions 03/04 11,000 P&R Fire Alarm budget 03/04 70,000 1,990,000 |
Hamble Community Sports College - new Youth Building and refurbishment of Newbold building |
Negotiation |
Apr 04 |
Aug 04 |
752,000 |
Education Capital 03/04 155,000 NDS Modernisation 03/04 195,000 P&R Capital Repairs 03/04 200,000 HCC Youth Service 67,000 South Central Connections 45,000 Eastleigh Borough Council 45,000 Community Strategy Group 45,000 752,000 |
Hatch Warren Infant and Junior Schools, Basingstoke - two classroom extension at Infant and four classroom extension at Junior Schoo |
Design |
Feb 04 |
Sept 04 |
* 1,998,287 |
Education Capital 03/04 1,818,287 School - Infant 92,000 School - Junior 93,000 1,998,287 |
Henry Beaufort School, Winchester - IT Suite, CDT accommodation, kitchen and nursery |
Complete |
Jun 03 |
Dec 03 |
* 659,000 |
SEED Challenge 03/04 89,000 Cap Prog Specialist Sch. St 86,000 Devolved Cap/Private funding 133,000 P&R Landscape budget 03/04 26,000 P&R Capital Repairs 03/04 194,000 Winchester City/LHPC 71,000 Hampshire Caterers 30,000 c/f from previous scheme 30,000 659,000 |
Hilting bury Infant School, Chandlers Ford - two classroom extension and remove temps |
Design |
Apr 04 |
Nov 04 |
744,000 |
NDS Modernisation 03/04 329,000 P&R NDS Condition 03/04 380,000 P&R Major Repairs 03/04 15,000 744,000 |
Hilting bury Junior School, Chandlers Ford - four classroom extension |
On site |
Feb 04 |
Aug 04 |
* 434,132 |
Education Capital 03/04 327,000 School - Devolved Capital 38,132 Schools Access Initiative 43,000 P&R Landlords Budget 03/04 26,000 434,132 |
Hounsdown Secondary School, Totton - NOF Sports Hall |
Tender Analysis |
Apr 04 |
Nov 04 |
1,259,000 |
New Opportunities Fund 1,193,000 School - Devolved Capital 66,000 1,259,000 |
Hythe Primary School, Hythe - extension to provide Hall, Kitchen, Music Room, Therapy Room and remodelling of existing kitchen and hall. |
On site |
Nov 03 |
Aug 04 |
* 761,669 |
NDS Modernisation 03/04 505,000 Schools Access Initiative 174,000 School - Devolved Capital 55,369 P&R External decs. 03/04 27,300 761,669 |
Kings' Secondary School, Winchester - six classroom teaching block |
Tender |
Mar 04 |
Sep 04 |
720,000 |
School 720,000 |
Lee-on-the-Solent Infant and Junior Schools - Infant - Nursery and Music Room extension - Junior - Extensions to reception, admin area, teaching and library areas. |
Tender |
Mar 04 |
Sept 04 |
551,455 |
Education Capital 03/04 455,869 SEED Challenge 03/04 30,000 School - Devolved Capital 52,586 P&R NDS Condition 03/04 13,000 551,455 |
Liphook Infant School - classroom extension |
Design |
Apr 04 |
Aug 04 |
264,000 |
Education Capital 04/05 190,000 School 74,000 264,000 |
Long Sutton Primary School, Basingstoke - Classroom Extensions and Internal Alterations |
Design |
Apr 04 |
Oct 04 |
438,000 |
NDS Modernisation 03/04 345,000 School -Devolved Capital 93,000 438,000 |
Manor Fields Infant and Junior Schools - Classroom/Playgroup Extensions and Internal Alterations and Refurbishment |
On Site |
Oct 03 |
Sept 04 |
*1,948,000 |
Education Capital 03/04 1,948,000 |
Marchwood Junior School, Southampton - Extensions and removal of temporary buildings |
On Site |
Jul 03 |
Mar 04 |
* 740,370 |
Education Capital 03/04 674,340 School 30,000 P&R NDS Condition 03/04 10,780 P&R External Works 03/04 10,250 740,370 |
Netley Abbey Junior School - two classroom extension and internal alterations |
Complete |
May 03 |
Dec 03 |
*319,229 |
Education Capital 02/03 173,229 School 146,000 319,229 |
Park Primary School, Aldershot - new Early Years Centre |
Negotiation |
Mar 04 |
Dec 04 |
671,695 |
NDS Modernisation 03/04 335,652 NEDA 03/04 273,043 Children's Centre Programme 63,000 671,695 |
Perins Community School, Alresford - dance studio, fitness suite and PE classroom |
Design |
May 04 |
Jan 05 |
1,389,000 |
Education Capital 04/05 733,000 Specialist College Status 86,000 School 270,000 P&R Capital funding 300,000 1,389,000 |
Petersfield Secondary School - new performing arts centre |
On site |
Jan 04 |
Aug 04 |
* 892,284 |
School 707,284 P&R NDS Condition 03/04 20,000 SEED Challenge 03/04 165,000 892,284 |
Priestlands Secondary School, Lymington - multi-purpose sports hall, fitness suite/changing facilities and synthetic turf pitch |
On site |
Mar 04 |
Dec 04 |
* 2,164,206 |
P&R (Capital Receipt) 328,000 NFDC 504,206 Lymington Town Council 187,000 Sport England 1,145,000 2,164,206 |
Priestlands Secondary School, Lymington -music/drama facility and dining extension |
Design |
Jun 04 |
Jan 05 |
1,163,000 |
Education Capital 03/04 756,000 Education contingency - TBA 76,000 School 331,000 1,163,000 |
Shakespeare Junior School, Eastleigh - three classroom and PE store extension |
On Site |
Nov 03 |
Apr 04 |
* 293,661 |
Education Capital 03/04 222,661 School - Devolved Capital 71,000 293,661 |
Sharps Copse Primary School, Havant - new Early Years Centre |
Complete |
Sep 03 |
Feb 04 |
* 437,000 add 18,000 455,000 |
Education Capital 03/04 45,000 New Opportunities Fund 392,000 P&R NDS Condition 03/04 8,000 P&R External Works 03/04 10,000 455,000 |
Steep CE(C) Primary School, Petersfield - new hall, library and internal alterations |
Tender Analysis |
Apr 04 |
Sep 04 |
557,534 |
NDS Modernisation 03/04 438,793 School 116,741 P&R Capital Repairs 03/04 2,000 557,534 |
Swanmore Secondary School - new multi use games area |
Design |
Apr/May 04 |
Jun/Jul 04 |
258,300 |
Winchester City Council 258,300 |
Swanmore Secondary School -new multi use hall |
Design |
Jun 04 |
Jan 05 |
598,000 |
Winchester City Council 598,000 |
Test Valley Secondary School, Stockbridge - NOF sports hall - language block and alterations |
On site On site |
Feb 04 Mar 04 |
Sep 04 Sep 04 |
* 2,113,625 |
Education Capital 03/04 640,000 New Opportunities Fund 1,418,625 Schools Devolved Capital 42,000 P&R Capital Repairs 03/04 3,000 P&R External Works 03/04 10,000 2,113,625 |
Tower Hill Primary School, Farnborough -two classroom extension |
Tender Analysis |
Apr 04 |
Sep 04 |
482,000 |
Education Capital 03/04 442,000 School 40,000 482,000 |
Westgate School, Winchester - administration and classroom extensions and science upgrade |
Design |
Apr 04 |
Dec 04 |
1,016,000 |
Education Capital 04/05 216,000 NDS Modernisation 03/04 139,000 Specialist School Status 86,000 School 352,000 P&R Capital Repairs 03/04 223,000 1,106,000 |
Whitewater Primary School, Hook - new hall |
Design |
Jul 04 |
Jan 05 |
411,000 |
Education Capital 04/05 351,000 School 37,000 Local Business Contribution 21,000 Ecclesiastical Trust 2,000 411,000 |
Wicor Primary School, Fareham - four classroom extension, library, music/drama room and internal |
Tender Analysis |
Mar / Apr 04 |
Sept 04 |
820,000 |
NDS Modernisation 03/04 537,000 SEED Challenge 03/04 37,000 William Price Trust 127,000 School - Devolved Capital 119,000 820,000 |
Wildern Secondary School, Hedge End - sports development and learner pool |
On site |
Feb 04 |
Dec 04 |
* 1,986,194 |
Eastleigh Borough Council 1,593,130 School 136,207 Town / Parish Councils 80,000 P&R Capital Repairs 03/04 165,857 Education funding 11,000 1,986,194 |
Winchester Early Years Centre - Lanterns - new Early Years Centre |
Design |
Jul 04 |
Jul 05 |
2,040,000 |
Education Capital 03/04 616,000 Capital receipts 1,276,000 Friends of Medecroft 95,000 Medecroft - Devolved capital 53,000 2,040,000 |
Wyvern Technology College, Fair Oak - sports hall refurbishment and extension |
On site |
Feb 04 |
Nov 04 |
* 1,782,737 |
Education Capital 03/04 205,094 Education planning budget 40,100 NDS Modernisation 03/04 50,000 Sport England 441,127 Eastleigh BC 267,100 P&R Revenue Maint. 03/04 133,000 P&R NDS Condition 03/04 202,000 P&R Capital Repairs 03/04 26,900 Parish Councils 44,500 Education FFE 26,700 School (various budgets) 346,216 1,782,737 |
Yateley Secondary School, Camberley - new dance studio |
On Site |
Jul 03 |
Mar 04 |
* 420,848 |
SEED Challenge 03/04 52,174 Specialist School Status 86,207 School 154,000 P&R M'ment P'ship 03/04 15,750 P&R Capital Repairs 03/04 112,717 420,848 |
SPECIALIST SCHOOLS ACCOMMODATION PROGRAMME | |||||
Package 1 - - Cove Secondary - Fernhill Secondary |
Design |
Jul 04 |
Sep 04 |
594,923 |
NDS Modernisation 04/05 480,749 Schools 110,174 P&R Capital Repairs 04/05 4,000 594,923 |
Package 2 - - Noadswood Secondary - Richard Aldworth Secondary |
Design |
Jul 04 |
Sep 04 |
249,763 |
NDS Modernisation 04/05 201,763 Schools 48,000 249,763
|
Bridgemary Community School |
Design |
Jul 04 |
Sep 04 |
341,723 |
NDS Modernisation 04/05 265,636 School 76,087 341,723 |
Other Schemes in the Education Capital Programme
The following schemes are included in the Education 2004/05 Capital Programme and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member Education or Policy and Resources:
School Allocation
(excluding fees)
£'000
PRIMARY
Droxford Junior |
729 |
Liphook Infant |
190 |
Whiteley / Sarisbury Primary |
1,240 |
2,159 |
SECONDARY
Crookhorn Community |
223 |
Perins Community |
732 |
955 |
NDS MODERNISATION
Alton Infant |
800 |
Bursledon Infant |
826 |
Cherbourg Primary EBD Unit |
217 |
Crescent Primary |
571 |
Lakeside School |
1,565 |
Netley Marsh Primary |
659 |
Nightingale Early Years Centre |
522 |
Nightingale Primary |
261 |
Saint Lawrence Primary |
684 |
Sundridge EBD |
652 |
The Bridge Centre |
830 |
The Westgate School |
218 |
Whitewater Primary |
351 |
8,156 | |
TOTAL |
11,270 |