Archived decisions
Hampshire County Council Executive Member - Spatial Strategy 13 July 2004 Project Appraisal: Regeneration of Older Urban Areas - Shore Road, Warsash Report of the Director of Environment |
Item 2 |
Contact: Simon Cramp, ext 6723 email: [email protected]
1. Summary
1.1 The following decision is sought:
That the attached Project Appraisal to carry out environmental improvements at Shore Road, Warsash, as part of the Regeneration of Older Urban Areas programme, at an estimated cost of £359,100, be approved, subject to planning permission for the rebuilding of stone walls to the boundary of the River Hamble Harbour Master's office.
2. Reason
2.1 This decision supports Aim 2 of the Corporate Strategy (Stewardship of the Environment) by developing the distinctiveness and quality of the Warsash Conservation Area.
2.2 The County Council's Regeneration of Older Urban Areas programme is managed to implement landmark projects to raise the quality of life for all who live, work and visit urban areas. All projects are designed to demonstrate the benefits of making the best use of land and property; high quality design; long life solutions and materials; and appropriateness to the local sense of place.
3. Other Options Considered and Rejected
3.1 Alternative design approaches have been considered. The current scheme is considered to enhance the character of the area, and represents the most appropriate technical solution and the most sensitive to conservation of the cultural asset.
4. Conflicts of Interest Declared by the Decision Maker or Other Executive Member Consulted - None.
5. Dispensation granted by the Standards Committee - Not applicable.
6. Reason(s) for the Matter being dealt with if Urgent - Not applicable.
Approved by: Date:
Councillor J K Glen
HAMPSHIRE COUNTY COUNCIL EXECUTIVE MEMBER - SPATIAL STRATEGY |
PROJECT APPRAISAL |
_____________________________________________
13 JULY 2004
_____________________________________________
__________________________________________________________________
PROJECT: |
REGENERATION OF OLDER URBAN AREAS - SHORE ROAD, WARSASH |
__________________________________________________________________
COMMENCEMENT DATE: |
JANUARY 2005 |
COMPLETION DATE: |
APRIL 2005 |
PLANNED YEAR OF START IN ACCORDANCE WITH CAPITAL PROGRAMME: 2004/05 |
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
1. |
FINANCE (Client Department, Director of Property, Business and Regulatory Services [Estates Practice] and County Treasurer) |
__________________________________________________________________
Current |
Capital | ||||
Estimate |
Programme | ||||
(at 2004 |
(at 2004 | ||||
prices) |
prices) | ||||
Capital Expenditure |
£'000 |
£'000 | |||
Land to be purchased |
nil |
nil | |||
Construction |
292 |
292 | |||
Fees |
68 |
68 | |||
360 |
360 | ||||
Less developers/ |
|||||
other contributions |
|||||
360 |
360 | ||||
Financial provision for total scheme |
Total Cost | ||||
1. |
From Committees own resources |
||||
(a) Capital programme (as above) |
360 | ||||
(b) Other |
|||||
360 | |||||
2. |
From other resources |
||||
(a) |
|||||
(b) |
|||||
(c) |
|||||
TOTAL |
360 | ||||
Value of land for this project in HCC ownership £ |
|||||
Variations from capital programme |
|||||
Revenue implications |
£'000 |
% variation | |||
to Committee's | |||||
budget | |||||
Net current expenditure |
3.0 |
0.003 | |||
Capital charges |
nil |
nil | |||
TOTAL net expenditure |
3.0 |
0.003 | |||
__________________________________________________________________
__________________________________________________________________
2. |
STATEMENT OF NEED/JUSTIFICATION FOR PROJECT (Client Department) |
__________________________________________________________________
The lower end of Shore Road and the waterfront at Warsash are recognised as having significant townscape, nature conservation and historic interest. The area is protected by many national and international designations, including Conservation Area status. A location plan is attached. The public Hard and adjacent car park are amongst the busiest destinations for visitors to the River Hamble and are important facilities for local residents and the business community. However, the external spaces lack the features usually associated with areas of this quality and there are fundamental problems relating to traffic management. The public footpath along the river is an integral part of the Solent Way which crosses the County Council's nature reserve at Bunny Meadows, and connects with the ferry crossing point. The project provides an extension to previous improvement work funded by the Regeneration of Older Urban Areas (ROUA) programme. It is also part of the emerging Transport and Access Strategy for the river and developing partnership working with the Crown Estate. |
__________________________________________________________________
3. |
ROAD IMPROVEMENT PROPOSAL (Client Department) |
__________________________________________________________________
National/County Network and Policies | |
This project will contribute to environmental improvements and enhance traffic management, including more effective use of car parking facilities, in the Warsash area. The improvements also continue the previous investment of the ROUA programme in this area. | |
Details of Scheme and Design Standards | |
The proposals seek to develop previous phases of work by meeting the following objectives: (i) safeguard and enhance the unique local character; (ii) make a more attractive and safer place for pedestrians; (iii) create a sense of arrival at the entrances into the Conservation Area; (iv) give higher priority to pedestrians and slow traffic down to appropriate speeds; and (v) improve the appearance of the waterfront car park. The proposals will achieve this by extending and joining up previous phases. Work will include: (i) replacing concrete kerbs to the full extent of the improvements with new stone kerbs and sett channels; (ii) resurfacing tarmac pavements, including the access to the Harbour Master's Office, with natural coloured high quality resin bound material; (iii) resurfacing the carriageway, and Shore Road car park, with natural coloured high quality surfacing and stone setts to emphasise the traffic management provisions and the special character of the area; (iv) installing new street lighting units in Lower Shore Road ; and (v) constructing new stone walls adjacent to the Harbour Master's Office and Lobster Quay, and within Shore Road car park. A detailed plan of the proposals will be displayed at the meeting. | |
Environmental Impact | |
The scheme will make high quality improvements to the streetscape within the Conservation Area. All construction materials will be selected for their quality and long-life, providing better value for money for long term maintenance costs. | |
Land Requirements | |
No land acquisition required. All works to be confined within the highway boundary or within areas where the owners have formally given their consent. | |
Statutory Procedures | |
Planning permission is required for the rebuilding of stone walls to the boundary of the River Hamble Harbour Master's Office. Planning permission for all other elements off-highway has been granted. | |
Public Consultation | |
A public exhibition was undertaken on 23 April 2004. A total of 111 visitors were recorded, but it is estimated that approximately 150 people viewed the proposals at the exhibition. Overall a significant number of responses expressed no comment either in favour or against the proposals, however objections were received to the scheme and the one-way system in particular. A total of 70 questionnaires were returned. Respondents were asked to answer three questions: 1. Do you agree that this is a suitable final phase of environmental improvements for Shore Road and Passage Lane? 2. A 20 mph speed limit is being considered for Lower Shore Road. Do you think this should be extended further? 3. Do you think the facilities for pedestrians are adequate? Of the 39 negative responses to question 1, 15 object to the scheme outright and 24 record a range of reasons. Of the 15, 9 cite the reversal of the one-way system as the principal reason for their objection. Of the remaining 24 `no' responses, where there is no outright objection to the scheme, 14 do so because of the reversal of the one-way system and 7 due to a range of minor issues. It should be noted that 12 of those comments that indicate a `yes' for question 1 are qualified by the identification of the need for minor changes to the proposals and 1 for the reversal of the one-way system. The not completed and `undecided' responses to question 1 also include a total of 3 commenting on the need for reversal of the one-way system. A full report on the consultation is attached as an appendix. The objection to the current one-way system, as reflected in the questionnaires, has also previously resulted in a 177 signatory petition, together with completed survey forms, calling for reversal of the one-way system. The petition was presented to Fareham Borough Council on 29 January 2004. The petition was considered by Fareham Borough Council's Executive on 22 March 2004. The Executive's decision was to press for implementation of the recommendations of the safety audit and to ask the County Council to reconsider the one-way system. This decision was formally conveyed to the County Council by letter dated 11 May 2004. A review of the features of the new and previous one-way systems has been undertaken and the outcomes are included in the attached appendix. | |
Local Member's View | |
The local Member, Councillor Estlin, supports the proposals. | |
Equalities | |
The needs of disabled people have been taken into account in the preparation of the detailed design. Facilities and surfacing, consistent with the character of the area, have been selected with disabled people in mind. | |
Maintenance Implications | |
The completed scheme will be incorporated into the maintenance programme of the Highway Authority and individual landowners as appropriate. | |
Crime and Disorder Act 1998 | |
Improvement to the public realm, including new lighting and surfacing, will enhance the sense of safety and security for all those using the area. | |
Sustainability | |
The scheme will improve the setting of important Listed Buildings and the Conservation Area generally. The project demonstrates the advantages of investment in the principles of appropriateness, high quality and long life, and supports the County Council's corporate Urban Living Strategy. |
____________________________________________________________________
4. |
ROAD IMPROVEMENT - ALTERNATIVES CONSIDERED (Client Department) |
____________________________________________________________________
Alternative design approaches have been considered. The current scheme is considered to enhance the character of the area, and represents the most appropriate technical solution and the most sensitive to conservation of the cultural asset. |
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
Project File |
Environment Department Room 112 |
8806/SC
APPENDIX
SHORE ROAD, WARSASH - REGENERATION OF OLDER URBAN AREAS PROGRAMME
REPORT OF PUBLIC CONSULTATION
1. Consultation
1.1 A public exhibition of the proposals was held at the Harbour Master's Office, Warsash between 10:00 am and 9:00 pm on 23 April 2004. The exhibition was manned for the duration. The exhibition was also available for viewing between 9:00 am and 12:00 noon on 24 April 2004. The exhibition was promoted through public notices, Fareham Borough Council's community notice boards, advertisements in the Southern Echo and Portsmouth News and the Warsash Residents Association. Formal questionnaires were available during the consultation and comments on the proposals were requested by 10 May 2004.
1.2 A visitor's book was kept open during the exhibition and 111 names were recorded. However, it is estimated that around 150 people viewed the proposals at the exhibition and, given the relatively limited number of properties directly affected by the proposals, this is considered to represent a good level of attendance. The population of Warsash village is approximately 6,740 (Office of National Statistics).
2. Results of Consultation
2.1 Following the consultation exercise Hampshire County Council received 70 written responses containing a large number of detailed comments.
2.2 The main objections related to:
(i) traffic management - reinstatement of the previous clockwise direction one-way system;
(ii) pedestrian safety - provision of safe crossing and footway facilities in Lower Shore Road and at its junction with Passage Lane;
(iii) excessive vibration on Listed Buildings - vehicles passing too close to properties;
(iv) inappropriate and unnecessary use of granite setts in the carriageway; and
(v) proposed access changes to Shore Road Car Park.
2.3 Fareham Borough Council has been part of the discussions on the development of the scheme throughout the process. The Borough Council was fully involved in the planning and implementation of the previous phase of improvements, including the reversal of the one-way system. Following receipt of a 177 person petition in January 2004 objecting to the one-way, the Borough Council's Executive has written to the County Council formally requesting that the reversal of the one-way system be reconsidered. With this exception, the Borough Council supports the current proposals. The County Councillor is fully supportive of the proposals.
2.4 The following table summarises the comments received to the questions at the exhibition:
Question 1 |
Yes |
|
No |
|
Not completed |
Undecided (yes and no) |
No comment | |
Do you agree that this is a suitable final phase of environmental improvements for Shore Road and Passage Lane? |
|
21 |
|
39 |
|
9 |
1 |
80 |
Question 2 |
||||||||
A 20 mph speed limit is being considered for Lower Shore Road. Do you think this should be extended further? |
|
40 |
|
22 |
|
8 |
0 |
80 |
Question 3 |
||||||||
Do you think the facilities for pedestrians are adequate? |
|
34 |
|
27 |
|
9 |
0 |
80 |
2.5 It should be noted that those comments that indicate a `no' for question 1 do so for different reasons. Of the 39 responses, 15 object to the scheme outright and 24 record a range of reasons. Of the 15, 9 cite the reversal of the one-way system as the principal reason for their objection. Of the remaining 24 `no' responses, where there is no outright objection to the scheme, 14 do so because of the reversal of the one-way system and 7 due to a range of minor issues.
2.6 It should be noted that 12 of those comments that indicate a `yes' for question 1 are qualified by the identification of the need for minor changes to the proposals and 1 for the reversal of the one-way system. The not completed and `undecided' responses to question 1 also include a total of 3 commenting on the need for reversal of the one-way system.
2.7 It is notable that overall a significant number of responses expressed no comment either in favour or against the proposals.
2.8 The main points raised for and against the proposals are outlined in the table below.
Aspects liked · More consideration and space for pedestrians · Reduction in traffic speed · Safer crossings for pedestrians · Level/improved pavements · Visually attractive |
Aspects disliked . Prefer to see one-way system reversed . Vehicles passing too close to historic buildings . Lack of footway and safe crossing facilities for pedestrians in Passage Lane and Lower Shore Road . Dislike use of stone setts . Alterations not in keeping with village character . Concern over use of area outside the Rising Sun Public House . Alterations not necessary . Revised access arrangements to car park . Continued use of local roads by heavy vehicles delivering to the village centre |
2.9 The proposal to retain the anti-clockwise one-way system within the scheme attracted the most individual comments.
Objection to the One-Way System
2.10 Concerns were raised about the effectiveness and safety of the `new' one-way system implemented in 2003. A Traffic Regulation Order introduced the previous one-way system for Lower Shore Road and Passage Lane on 28 May 1975. Before that date Lower Shore Road and Passage Lane were each subject to two-way traffic - an arrangement that appears to have been continuous until 1975.
2.11 In September 2001 Fareham Borough Council approved proposals to reverse that 'clockwise' one-way system around Shore Road and to revoke the one-way system at Passage Lane, between Thornton Avenue and the Passage Lane car park. On 7 March 2002 the Borough Council approved that Traffic Regulation Order being made permanent. The existing one-way system was implemented in January 2003.
2.12 The objectives of the reversal of the one-way system are:
(i) to enable drivers to gain direct access to the Passage Lane car park, thereby reducing traffic in Lower Shore Road; and
(ii) to give higher priority to pedestrians in the vicinity of The Hard, improving the safety and the environment of the water frontage.
2.13 The one-way system is therefore an integral feature of the long-term programme of improvements to the Warsash Conservation Area.
2.14 As part of the scheme design, safety audit inspections were undertaken at preliminary and detailed stages. A third audit inspection was carried out in March 2004 to review the scheme as implemented to date. This audit involved representatives of Fareham Borough Council, Hampshire County Council and Hampshire Constabulary. This inspection concluded that some changes were required to the local signs and road markings together with provision of some anti-skid surfacing to a section of Shore Road. The recommendations of the post scheme completion safety audit into the reversal of the one-way system were implemented before the consultation.
2.15 The features of the new and previous one-way systems have been reviewed as follows:
Observations on Alternative One-Way Layouts |
||
Issue |
Anti-clockwise (existing) |
Clockwise (previous) |
Passage Lane/Lower Shore Road junction (top) |
Turning right on incline - possible conflict with two-way traffic on Passage Lane but considered satisfactory, particularly following implementation of Safety Audit measures. |
Turning left with gradient. No conflict. |
Lower Shore Road/ Passage Lane junction (bottom) |
Turning left with gradient. Vehicle speeds naturally checked by bend. No conflict. |
If two-way traffic retained on Passage Lane, possible conflict with traffic to/from car park. If one-way extends to Thornton Avenue junction as before, loses benefit of Passage Lane access to car park. |
Access to The Hard |
Access via waterfront. Vehicles on Lower Shore Road are in full view of pedestrians. Cars using The Hard are required to negotiate the one-way system up Lower Shore Road in order to access a car park. |
Direct access to waterfront. Conflict between users, vehicles and pedestrians at corner of Rising Sun Public House. Vehicles on Lower Shore Road are hidden from pedestrians. Cars using The Hard are able to access the Shore Road or Passage Lane Car Parks in order. |
Passage Lane traffic speeds and volume |
Straight section of road with gradient giving access to public car park and residential area. Extra traffic using Passage Lane for direct access to top car park. |
Straight section of road with gradient giving access to residential area but not car park, unless two-way traffic retained for full length. |
Volume of traffic in Lower Shore Road |
Visitors for whom Shore Road Car Park is the preferred destination are required to negotiate the whole of the one-way system and Passage Lane if the facility is full. |
All visitors are required to negotiate the waterfront area to access car parking facilities. |
Access to Stone Pier Yard |
Large delivery vehicles are able to access the yard directly with the trailer in a convenient position for loading. |
Large vehicles contravene the one-way system to effectively access the yard. |
Vibration in Lower Shore Road |
Vehicles are negotiating the incline in a lower gear and therefore there may be more engine noise and air-borne vibration. |
Vehicles are moving with the gradient, although braking may be taking place to reduce speeds. |
Noise in Lower Shore Road |
See above |
See above |
Pedestrian access in Lower Shore Road |
Pedestrians accessing the waterfront from Lower Shore Road are facing the traffic. Pedestrians leaving the area by the same route are in full view of drivers. |
Pedestrians in Lower Shore Road with their backs to vehicles are at risk of being hidden from traffic. |
Access to Passage Lane Car Park |
Direct access to car park. Allows more effective use of facility. |
Indirect access via waterfront. |
2.16 It is considered that the objectives of the reversal of the one-way system are now being achieved. It is also considered that:
(i) the final stage of improvements in Shore Road and Passage Lane (below Thornton Avenue), including extensive resurfacing in an appropriate natural colour stone; and
(ii) the implementation of a 20 mph zone in Lower Shore Road and Passage Lane, supported by 27 respondents to question 2 at the public exhibition on 23 April 2004;
will further enhance both the safety features of the scheme and add to the environmental enhancements already achieved. However, it is recommended that the arrangements be monitored and effects measured, and, if considered appropriate, changes could be put in place.
Pedestrian Safety
2.17 With regard to comments on the safety of pedestrians crossing Passage Lane at the junction with Lower Shore Road, and the provision of footway facilities along the length of the latter, this has been reconsidered and is reflected in the proposals contained in the project appraisal. In view of the comments expressed about the loss of character, the above facilities have been designed to reflect the distinctive village qualities of Warsash.
Vibration Concerns
2.18 The concern about the impact of vibration from vehicles passing too closely to the Listed Buildings in Lower Shore Road is recognised. The proposals have been adjusted to remove the potential for excessive vibration and to ensure consistency with the objective to provide a safe footway in Lower Shore Road. Steps are also being taken to ensure that the implementation programme, and specification of works, effectively minimises these risks. A meeting with the residents immediately affected by this issue is being planned.
Use of Stone Setts
2.19 The use of stone setts in the carriageway and paved areas is a clear concern. The use of this material in all of the three previous phases of work at the waterfront Warsash has established a palette of materials that responds to the local character and nature of the place, provides a robust and effective surface finish for the long term, and raises the environmental quality of the area. The need to provide safe and comfortable surfaces for all users is recognised and has informed the specification and selection of material. The use of stone setts is not considered to be excessive, inappropriate or unsafe. However, the proposals have been reviewed. The area of setts has been reduced and the extent of smooth surfaced setts has been clarified.
Access to Shore Road Car Park
2.20 With regard to comments on access to Shore Road car park, the proposal to combine an in and out arrangement at the northern end, and closure of the southern exit in favour of a pedestrian only area, has been reconsidered. In light of concerns about the conflict of pedestrians and vehicles, traffic turning in front of vehicles emerging from the car park, the scale of the combined entrance, and the use of the area in front of the Rising Sun, the proposals have been redesigned to retain the current access arrangements.
Loss of Character and Alterations Unnecessary
2.21 The current proposals represent the fourth and final phase of environmental improvements funded by the Regeneration of Older Urban Areas programme in the Warsash Conservation Area. Each of the previous phases has met with some concern about the effects of the proposed changes. However, the proposals result from initial extensive consultation into the issues and widespread agreement about the need for change in this area. Significant research has also taken place into the history and character of the area and the project development has been informed by Fareham Borough Council's policy and guidance for this Conservation Area. The previous phases are considered to be appropriate and of high quality, and are generally recognised by the local community, businesses and visitors as successful. The final phase of work has been designed to further add to these benefits.
Use of Roads by Heavy Vehicles
2.22 It is agreed that the use of Passage Lane and Lower Shore Road by heavy vehicles delivering to the village centre is inappropriate and undesirable. The concerns have been noted and alternatives for managing this traffic will be considered. However, this is beyond the remit of this project.
General Comments
2.23 Several comments made related to the inclusion of other areas outside the scope of the enhancement area. The resources available have been secured to meet particular objectives of the Regeneration of Older Urban Areas programme and to improve the environment of the Conservation Area. The other areas suggested can be kept under review and the impact of the proposed changes be monitored, with a view to looking at possible changes if required in the future.
2.24 Other comments were received about the design of the corner of the Rising Sun, the potential conflict of pedestrians and vehicles, and the need for large vehicles to negotiate the bend. These aspects have been taken into account during the project development and the proposals are considered satisfactory in this regard.
3. Conclusion
3.1 The overall view from members of the public is that the proposals for Shore Road, Warsash represent an appropriate improvement to the Conservation Area and waterfront, but there are concerns about a range of details and a significant number of objections to the retention of the anti-clockwise one-way system.
3.2 The proposal to retain the anti-clockwise one-way system raised the largest number of objections. Concerns about this were known to the County Council before the consultation exercise and a range of measures have been taken, within and without the current scheme, to address these. The completion of the overall scheme is considered to be a fundamental part of the strategy of ensuring the success of the one-system, and it is difficult to measure the effectiveness of this until these improvements are in place. It is considered that the benefits of the current proposals, and previous phases, would be reduced by the reversion of the one-way system to clockwise working.
3.3 Many of the concerns raised, such as the issues of access to the car park and improving facilities for pedestrians, have been looked at in more detail to help overcome these objections. Other issues have also been reviewed and the proposals have been revised as a result.
3.4 Taking account of all the comments received, and in light of the success of previous phases, it is considered that the overall benefit to the area will be a positive one and the revised proposals presented in the project appraisal should be progressed in their entirety.