Hampshire County Council Executive Member - Education 21 July 2004 Education capital programme issues Report of the County Education Officer and County Treasurer |
Item 8 |
Contact: Contact: Bob Eardley, Strategic Planning Manager, 01962 846275. Email: [email protected]
1. Summary
1.1 The following decisions are sought:
1. That, subject to the approval of the Executive Member, Policy and Resources, the following variations to the 2004/05 Education capital programme be approved:
(a) the addition of resources totalling £14.479m:
£1.788m from capital receipts;
£11.069m carry over schemes;
£1.622m unallocated in 2003/04.
(b) that projects listed in Appendix 1 be carried forward from 2003/04 to 2004/05;
(c ) that allocations for major projects in the 2004/05 capital programme be varied as follows:
School |
Current allocation £'m |
Revised allocation £'m |
Brune Park Community, Gosport |
1.184 |
1.255 |
Eggar's Secondary, Alton |
0.862 |
0.914 |
Frogmore Community |
0.752 |
0.797 |
Grateley Primary |
0.434 |
0.460 |
Hamble Community |
0.256 |
0.264 |
Hiltingbury Infant |
0.378 |
0.401 |
Long Sutton Primary |
0.397 |
0.421 |
Priestlands Community, Lymington |
0.877 |
0.930 |
Wherwell Primary |
0.520 |
0.551 |
(d) that the allocation for minor works in the 2004/05 capital programme carried over from 2003/04 be increased by £0.039m;
(e) that provision for the major project at Lakeside School, Chandler's Ford be increased by £0.300m to £2.100m from unallocated capital receipts;
(f) that provision for the major project at Hamble Community Sports College be increased by £0.050m to £0.557m through DfES grant and from the capital programme contingency;
(g) that resources of £0.330m be added to the provision for early years developments in the 2004/05 capital programme from the contingency to fund development of a Children's Centre at Sharps Copse Early Years Centre, Havant;
(h) that a major project to refurbish the community wing at Sharps Copse Early Years Centre, Havant be added to the 2004/05 capital programme, at an estimated cost of £0.330m;
(i) that a project at Beech Down Primary School, Basingstoke to upgrade facilities for use by a pre-school at a cost of £0.017m be added to the provision for minor works;
(j) that provision for a minor works scheme to upgrade facilities at the Oak Meadow Early Years Centre, Fareham be increased from £0.066m to £0.147m from the provision in the capital programme from the William Price Trust;
(k) that an allocation of £0.015m from the provision for secondary school science improvements be made towards the cost of work at Brune Park Community School, Gosport;
(l) that an allocation of £0.030m from the provision for workforce accommodation improvements be made towards the cost of work at The Connaught Secondary School, Aldershot;
(m) that the allocation for school security measures be increased by £0.006m from the capital programme contingency to £0.356m;
(n) that a contribution of £0.050m from the capital programme contingency be made available to support a project at The Butts Primary School, Alton, pending receipt of a developer's contribution;
(o) that resources of £0.848m be added to the provision for minor works in the 2004/05 capital programme in respect of specialist school allocations at the following schools:
School |
Amount of allocation £'m |
Bay House Secondary, Gosport |
0.100 |
Brune Park, Gosport |
0.100 |
Cranbourne Secondary, Basingstoke |
0.100 |
Crestwood Community, Eastleigh |
0.122 |
Eggar's Community, Alton |
0.100 |
Kings' Secondary, Winchester |
0.100 |
Robert Mays Secondary, Odiham |
0.100 |
The Crookhorn Community, Purbrook |
0.126 |
2. That approval be given for the application for planning permission until 31 August 2006 for a double temporary classroom to be located at The Vyne School, Basingstoke and for a further double temporary classroom to be located at Nightingale Primary School Eastleigh.
3. That it be a RECOMMENDATION to the Executive Member, Policy and Resources, that the application for temporary classroom accommodation listed in Recommendation 2 is approved until 31 August 2006.
2. Reason
2.1 To approve variations to the Education capital programme.
2.2 The proposals in this report support Aim 1 of the Corporate Strategy (Maximising life opportunities) by proposing allocations of funding to improve the learning environments of Hampshire schools.
3. Other options considered and rejected - none.
4. Conflicts of interest declared by the decision maker or a member or officer consulted - none
5. Dispensation granted by the Standards Committee - not applicable.
6. Reasons for the matter being dealt with if urgent - not applicable.
Approved by Date of decision
Councillor D Allen