Archived decisions
Hampshire County Council Buildings, Land and Procurement Panel Item 19 October 2004 Procurement Initiatives Report by the Director of Property, Business and Regulatory Services |
Contact: David Corcoran Ext: 7930 email: [email protected]
1 |
Summary |
1.1 |
The Executive Member for Policy and Resources approved at his meeting of 8 April 2004 the annual review of procurement initiatives for 2003/4 and a series of new initiatives to be implemented over the current financial year and beyond. |
1.2 |
This report is an interim review of the arrangements for the current financial year of all of present initiatives, including the Framework for Major Schemes and Programmes of Work and other Strategic Partnerships. The report also proposes a number of new initiatives which it is proposed to introduce over the remainder of the year. |
2 |
Framework for Major Schemes |
2.1 |
The report to BLPP on 24 March 2004 (approved by the Executive Member for Policy and Resources on 8 April 2004), provided the first review of the Framework Agreement for Major Schemes and Programmes of Work and detailed the award of the initial schemes, procured through the arrangements. It also proposed that a number of further significant capital projects would be undertaken through the arrangements. An earlier report to Cabinet on 27 May 2003 explained the philosophy behind the approach principally designed for major projects and programmes of work exceeding £1m. |
2.2 |
A key function in deciding on the award of further work has been the emergence of key performance information for the six contractors on projects in progress or completed. The report to BLPP in March 2004 also provided the results of an analysis of 34 recently completed major capital projects procured on the basis of best value and traditional lowest price competitive tendering . The results were presented in the form of a `Radar' diagram against a set of eight key performance indicators. |
2.3 |
Following on from this analysis, a sample of work undertaken by the six contractors who are involved with the Framework Agreement for Major Schemes and Programmes of Work has been assessed against the same headline KPI's comprising: · Contractor performance. · Health and Safety Management · Supply chain performance · Quality achieved · Customer satisfaction · Time predictability · Cost predictability · Avoidance of claims and disputes. The sample includes earlier procurement with the contractors prior to the implementation of the Agreements . |
2.4 |
The earlier report showed a 21% improvement between best value procurement and traditional lowest price tendering. The recent analysis of the six contractors shows a further 7 % improvement . This is illustrated by the `Radar' diagram in Appendix 1. |
2.5 |
The report to BLPP in March identified that some £47m of capital expenditure had been committed through the Framework Agreement for Major Schemes and Programmes of Work . A similar value of work has been committed since that report (see 2.10.1 below). |
2.6 |
The first major package of work committed through the Framework Agreement for Major Schemes and Programmes of Work is the Nursing Care Strategy, in particular the initial phase of schemes comprising 6 projects worth £30m. These projects are being undertaken through three of the contractors, each having two projects. Currently all of the projects are running to programme and to budget, and the work is of an excellent standard. A gateway review has recently been carried out with all of the new build elements now at a fairly advanced stage (see item 20 on the agenda). As part of this process each of the contractors' performance has been assessed and measured against the same set of performance indicators previously applied to other forms of procurement (see 2.3 above). The result shows that the level of performance achieved is on average 9% above the best value work sample and 30% higher than lowest price competitive tender sample. The effectiveness of the collaborative partnering approach is also demonstrated by the construction progress achieved only 18 months from approval of the design project appraisal (presented to this panel in March 2003). The speed and effectiveness of the delivery could not have been achieved through a traditional procurement approach. |
2.7 |
On the basis of this strong performance the final Nursing Care schemes will be awarded to the same three contractors who are delivering the first six projects. This strategy will also: · provide continuity in terms of maintaining the same integrated team arrangements who will move across to the next schemes · utilise established supply chains · provide opportunity for continuous improvement through learning and development. |
2.8 |
It should also be noted that the project has been selected as a demonstration project by the Movement for Innovation, which promotes the Government's modernisation agenda for construction procurement through `Constructing Excellence'. |
2.9 |
John Hunt of Everest |
2.9.1 |
This project been awarded to Wates Construction following a best value review process of submissions invited from four contractors under the Framework Agreement for Major Schemes and Programmes of Work, on the following basis: · preliminary costs (site management and facilities) · proposed team · approach to the project · programme · supply chain approach · risk management · sustainability |
2.9.2 |
The written proposals were evaluated and provisionally scored against financial and ability criteria using a pre-determined scoring matrix. This was supplemented by contractor presentations and interviews after which revised scores were agreed for each contractor. The submissions from all four contractors were of a high standard, supported by strong performances at the interviews giving confidence that any of the contractors could successfully deliver the John Hunt of Everest project. Based on the combined financial and ability scoring, and site visits, Wates' submission emerged as the strongest.
|
2.9.3 |
The second stage design development is now underway with Wates and a start on site during the summer of 2005 is planned. |
2.10 |
Overall Summary of Projects and Performance |
2.10.1 |
Appendix 2 summarises the projects allocated under the Framework Agreement for Major Schemes and Programmes of Work since the start of this financial year. A total of £55M of construction work is identified of which £49M has so far been awarded to specific contractors. |
11.2 |
Officers from Property, Business and Regulatory Services and employees from Mansell Construction Services Ltd (a County Council Framework Contractor) attended the site on 27 August to assess the damage and ascertain the extent of the initial emergency works required to make the site safe. | ||
11.3 |
It was agreed at that time to instruct Mansell Construction to instigate emergency works and initiate proceedings on site. This work included fencing of the area, the isolation of services and emergency clearance of asbestos debris created during the fire. | ||
11.4 |
Following on from the initial emergency works the extent and estimated cost of a full fire reinstatement scheme to return the school to normal conditions has been completed and a contract has been arranged with Mansell Construction. The cost of the work is £199,000 and will be a charge against the County Council's Fire Reinstatement budget. It is estimated that works will complete on 5 November 2004. | ||
Recommendations | |||
1 2. |
That the Panel note the following: 1. the projects to be undertaken through the Framework for Major Schemes and Programmes of Work as identified in Appendix `2'; 2. the appointment of Strategic Partners for Quantity Surveying services; 3. the appointment of Landscaping Consultancy Partners. That the Panel advices the Executive Member for Policy and Resources that approval be given to: 1. the procurement initiatives that have been implemented this year as set out in Appendices 2 and 3; 2. the procurement initiatives set out in Appendix 4 relating to the: · replacement of Wet Cooling Towers - Winchester · response after Fires and other Urgent Works ·Hiltingbury Infant School - Improvements ·replacement of uninterruptible power supply to the IT suite ·fire suppression and alarm systems in the IT suite · replacement of Warwick windows at Swanmore and Hayling Schools 3. the appointment of Asbestos Surveying Consultancy Partners 4. the appointment of both Town Planning and Urban Design and Transport Planning Strategic Consultancy Partners 5. the appointment of lead design consultants and key specialists for the redevelopment of Ashburton Court and the process to select a contractor for the project 6. the arrangements following the fire at Eggars School, Alton 7. the appointment of Elliot Group Ltd and SGB Rovacabin for the supply, transfer and hire of temporary buildings wef 1 November 2004 as set out in para 4.1. | ||
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act
........................
........................
BLPP1004F