Archived decisions

Best Value Procurement 2004/2005 Appendix 3

PROJECT TITLE

CONTRACTOR(S)

VALUE

SELECTION METHOD

REASON FOR PROCUREMENT STRATEGY

Negotiated Work

Brookfield School

Schools Access Initiative

Brazier

500,000

· Negotiation with preferred contractor

· Contractor input required to carefully consider the works.

· Successful completion of major package of work for additional teaching spaces by some contactor and continuity for the school.

· Potential to involve contractor in design development of scheme.

Nightingale Primary School

Fire Reinstatement work

Tew Brothers

450,000

· Negotiated with preferred contractor

· Contractor familiar with the type of work required.

· Establish pricing framework.

Harriet Costello

Reinstatement work following fire

(Final Phase)

Tew Brothers

310,000

· Negotiation with contractor currently on site

· Final phase of temporary work required to complete the fitting out of temporary classroom facilities.

· Contractor already on site undertaking emergency work following fire

· Benchmark pricing documents and cost plan established as basis for negotiations

Connaught Secondary School

Extension and alterations to fitness suite over extensions to administrative area

Gregory Havant

310,000

· Negotiate with preferred contractor

· Following unsuccessful competitive tender process it is proposed to develop a revised scheme with a preferred contractor.

· Contractor selection has successfully assisted with design and development of similar work.

Sharps Copse Children's Centre

Final Phase

Brazier

250,000

· Negotiation with preferred contractor

· Contractor has previously been involved with work on this site

· Contractor has a good understanding of the environment and working relationship with the school

· Work commencing during the summer and similar to previous phases of work so logical to use same contractor.

Elizabeth II Court

Drew Smith

150,000

· Negotiation with preferred contractor

· Contractor required at short notice to enable planned refurbishment following relocation of HR Team.

· Planning and execution of work in required timescale in conjunction with contractor.

Brune Park Community School

Science Laboratory Refurbishment

Mansell

134,000

· Negotiation with preferred contractor

· Further package of work added to Science Labs programme with the same contractor undertaking the programme and continuity and economy of scale.

Woodcot Primary School

Re-cladding & Re-roofing Works

Wessex Windows

125,000

· Negotiation with preferred specialist

· Securing specialist work to align with main contract

· Continuing with standardised specialist system previously installed.

PROJECT TITLE

CONTRACTOR(S)

VALUE

SELECTION METHOD

REASON FOR PROCUREMENT STRATEGY

Negotiated Work

Woodlea Primary School

Extension

Gregory Havant

120,000

· Negotiation with preferred contractor

· Key construction activities required over the summer holiday period necessary in early contractor appointment desirable.

· Negotiated route so resources secured in the timescale required.

· Contractor has already worked successfully with the same architectural team to deliver similar schemes.

Shamblehurst Primary School

Edgar and Wood

113,000

· Negotiation with preferred specialist

· Work to be undertaken over summer holiday period.

· Contractor undertaking similar work elsewhere in the county.

Capitol House

Office Accommodation

Hampshire Partitioning Contractors Limited

110,000

· Negotiation with preferred contractor

· Negotiate with contractor successfully undertaking similar work incentive for the County Council.

· Urgent project linked to a chain of relocation.

Chiltern Primary School

Enabling Works incorporating work by Term Engineering Contractor

Pool & Sons with electrical work by Churchers

100,000

· Negotiation with preferred contactor and specialist

· Engage with preferred contractor to ensure works re completed over summer 2004 holiday period.

· Contractor familiar with and good relations with school .

The Neville Lovett Community School and CEC

Re-roofing and refurbishment of windows to D block.

Survey & Construction

95,000

· Negotiation with roofing framework contractor

· Additional project added to the framework contractor with resources available to meet programme requirements.

· Work undertaken during the summer to minimise disruption to the school

Oak Farm Community School and CEC

Refurb of catering/food technology rooms

Nolan Davis

90,000

· Negotiation with preferred contractor

PROJECT TITLE

CONTRACTOR(S)

VALUE

SELECTION METHOD

REASON FOR PROCUREMENT STRATEGY

Selective Tendering (Short List)

Romsey Discovery Centre

Conversion of Library building and Extensions

575,000

· Two stage tender process with list of 3 preferred contractors

· Early appointment desirable to enable contractor involvement in development of the scheme.

· Contractor input in planning and programming the works

· Complex work involving working around existing library facilities

Long Sutton Primary School

Extensions and Alterations

LST Building Services

438,000

· Two stage tender approach competitively tendered - three preferred contractors

· Engage with preferred contractor to resolve issues associated with constrained site and complex phasing.

Aldershot Register Office

Jenkins & Falvey

Nolan Davis

Dorelbury Ltd

100,000

· Short list of three preferred contractors invited to submit competitive tenders.

· Preferred contractor required as the work may be disruptive and there needs to be minimal impact to the operation of the Register Office.

Shepherds Down Special School

Improvement to Upper Years Playground

Kieron Beattie Landscaping

96,386

· Short list of three preferred firms invited to submit competitive tenders.

· A detailed job with a mix of small landscape, ground working and civil engineering requiring preferred contractor selection.

· Small number of suitable firms on approved list.

· Early commitment required to complete the work by end of school holidays

Eastleigh House

Relocation of HR Team

Nolan Davis

RV Dart

Drew Smith

150,000

· Short list of three contractors invited to submit competitive tenders

· Preferred contractors desirable due to complexity and timing of works.

Negotiated packaged work

External Redecorations

Package A-04

Anton Junior School

Burley Primary School

Burley House

Ealing Infant

Foxhills Infant School

Hale Primary School

Merdon Junior School

Netley March CE Infant School

Orchard Close

Totton Fire Station

Atkins Painting & Decorating

211,313

    · Negotiation with preferred contractor

· Secure resources to undertake a large programme of seasonal work.

· Firms who have delivered similar work to a high standard required.

· Previous projects will serve as a sound basis to negotiate.

· Packaging to achieve value for money.

· Simplification of management arrangements by strategically grouping programmes of work with contractor.

Package B-04

The Hurst Community College

Aldershot Military Museum

Anstey Junior School

Chawton CE Primary School

Liphook Fire Station

Petersfield Fire Station

Belgravia Renovations Ltd

294,111

Package C-04

Noadswood School

Hambledon Infant School

Monument House

Oak Lodge School

Ringwood Junior School

St Lukes CE Primary School

Brockenhurst Fire Station

Ferris Painting

259,320

Package D-04

Eggars School

The Mark Way School

Hampshire Record Office

Tower Hill Community School

Harestock Hostel

Riverside Community Special School

Heathfield Special School

Locks Heath Infant School

Newtown CE Primary School

Red Barn Community Primary School

Wallisdean Junior School

Horndean CE Junior School

Purbrook Junior School

Bidbury Infant School

Catherington Primary

Alresford Fire Station

Bishops Waltham Fire Station

Mitie Property Services

496,416

· As above

· As above

Package E-04

Bridgemary Library

South Wonston Primary School

Stubbington Study Centre

Droxford Junior School

Rachel Maddocks School

Botley CE Primary School

Winnall Primary School

Woodcot Primary School

Malmsbury Lawn OPH

Hayling Island Fire Station

Richardsons Decorating Contractors

265,305

Package F-04

The Romsey School

St Michaels CE Infant School

St Patricks Catholic Primary School

North Baddesley Infant School

Western Primary School

Wellow School

Cherbourg Primary School

Hiltingbury Junior School

Cupernham Infant School

Eastleigh Fire Station

Eastleigh Fire Divisional HQ

Tew Brothers

360,648

Package G-04

Kings School

Ashcroft Arts Centre

Curdridge Primary School

Itchen Abbas Primary School

Botley Fire Station

Stockbridge Fire Station

Warwick & Son Ltd

277,791

· As above

· As above

Package H-04

Winton School

Guillemont Junior School

Kings Somborne CE Primary School

Portway Infant School

Liss Infant School

Liss Junior School

South Farnborough Junior School

Balksbury Junior School

Weeke Primary School

Hardley Fire Station

Tadley Fire Station

Yateley Fire Station

Kingsclere Fire Station

Pool & Son

272,085

Package I-04

Sparsholt Primary School

Poulner Infant School

Poulner Junior School

Abbotts Ann Primary School

Ampfield Primary School

Andover Primary School

Barton Stacey Primary School

Braishfield Primary School

Bushey Leaze Centre

Denmead Infant School

Glenwood Special School

Langrish Primary School

Bradec

265,976

Package J-04

Leesland Infant School

Ropley Primary School

Hawthorns Hostel

Hawthorns School

Purkiss Ltd

109,426

WORKS

CONTRACTOR(S)

VALUE

SELECTION METHOD

REASON FOR PROCUREMENT STRATEGY

External Ramps and Hard Landscaping Framework

South Hampshire Framework

Horndean Infants

Horndean Junior

Cowplain Community

Padnell Infants

Meadow Lands Junior

Mengham Infants

Barncroft Junior

Mengham Junior

Leesland Junior

Upland Primary

Locks Heath Junior

Hamble School

Netley Abbey Junior

Wildground Junior

Pennington Junior

Ashley Infants

Ringwood Junior

Abbotswood Junior

Fordingbridge Junior

Lymington Junior

Ranvilles Infant

Ranvilles Junior

Holbrook Primary

Drew Smith

151,520

· Competitive tender for model designs and supporting schedule of rates

· Pilot to determine long term viability of packaging a large number of small projects of a similar type to achieve economy of scale and fixed prise on overheads

· Early alignment of contractor resources required for seasonal works.

· Performance management pilot continuous improvement required to develop long term arrangements.

North Hampshire Framework

St John the Baptist

Kingsclere Primary

Bramley Primary

Fleet Infants

Southwood Infants

Alton Infants

Norwood Primary

Hazel Wood Infants

Foxhills Infant

Bratley Junior

Wellow Primary

Locks Heath Infants

Denmead Junior

Morelands Primary

Merdon Primary

Rocon Contractors

Reserve John Sisk, dependent on enlargement of package

(Potential to create a third framework package

124,235