1.1 This report considers the various elements of the Street Lighting service which affect the Winchester area.
2. Street Lighting - Maintenance
2.1 The maintenance of the street lighting stock continues much the same as advised in previous reports, in that approximately 99% of all lights are on at any one time. The contractor's performance has improved in the area of planned maintenance, but he is still experiencing problems in completing some ordered works on time and reducing repeat visits.
3. Column Replacement Programme
3.1 Problems associated with replacing the County Council's obsolete stock continue and a £1.8 million programme is in place for this year. However, the stock is still deteriorating and it is anticipated that funding of about £5 million per annum is required for each of the next 10 years to get back on track with the current backlog of work.
3.2 The programme of replacements for the Winchester area for 2004/05 is as follows:
Fromond Road, Winchester |
works programmed to start 10/01/05 | |
De Lucy Avenue, Alresford |
Programme date to be arranged with contractor |
4. Community Safety Initiatives
4.1 The 2004/05 programme was agreed by the Executive Member for Environment in the spring and the County Council is currently in discussion with local councils to confirm the details of their respective schemes.
4.2 The CSI programme within the Winchester area for 2004/05 is set out below:
Ashburton Road, Alresford |
programme dates to be arranged with contractor |
Norman Road, Winchester |
programme dates to be arranged with contractor |
St Catherines/Portal Rd f/p, Winchester |
programme dates to be arranged with contractor |
The Weirs, Winchester |
programme dates to be arranged with contractor |
Waynflete Place, Winchester |
programme dates to be arranged with contractor |
Wykeham Place, Winchester |
programme dates to be arranged with contractor |
The Brook, Old Alresford |
programme dates to be arranged with contractor |
Braeside Close, Olivers Battery |
programme dates to be arranged with contractor |
5. Energy
5.1 The new `green' energy contract commenced on 1 April 2004 with no problems to date and will continue until March 2006. Monitoring of this contract is ongoing.
6. City Road and Eastgate Street - Lighting Improvements
6.1 As part of the Winchester Movement and Access Plan (WMAP) both City Road and Eastgate Street, Winchester have been relit. City Road was completed in April 2004 with a scheme which complemented the Station Hill refurbishment scheme, whilst Eastgate Street and the Broadway roundabout will be brought to standard following the recent building works on the south side of the road.
Recommendation
That this report be noted.
Section 100 D - Local Government Act 1972 - background papers | ||
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | ||
NB the list excludes: | ||
1. |
Published works. | |
2. |
Documents which disclose exempt or confidential information as defined in the Act. | |
TITLE |
LOCATION | |
None |
||
8902/ALS