Archived decisions

Hampshire County Council

Havant Highway and Transport Advisory Panel

2 November 2004

Street Lighting Report - Havant

Report of the Director of Environment

Item 11

Contact: Tony Stephens, ext 6938 email: [email protected]

1. Summary

1.1 This report considers the various elements of the Street Lighting service which affect the Havant area.

2. Street Lighting - Maintenance

2.1 The maintenance of the street lighting stock continues much the same as advised in previous reports, in that approximately 99% of all lights are on at any one time. The contractor's performance has improved in the area of planned maintenance, but he is still experiencing problems in completing some ordered works on time and reducing repeat visits.

3. Column Replacement Programme

3.1 Problems associated with replacing the County Council's obsolete stock continue and a £1.8 million programme is in place for this year. However, the stock is still deteriorating and it is anticipated that funding of about £5 million per annum is required for each of the next 10 years to get back on track with the current backlog of work.

3.2 The programme of replacements for the Havant area for 2004/05 is as follows:

Swanmore Road, Havant

works programmed to start 04/11/04

Calshot Road, Havant

works programmed to start 04/11/04

St Thomas Avenue, Havant

works programmed to start 15/11/04

4. Community Safety Initiatives

4.1 The 2004/05 programme was agreed by the Executive Member for Environment in the spring and the County Council is currently in discussion with local councils to confirm the details of their respective schemes.

4.2 The CSI programme within the Havant area for 2004/05 is as follows:

Holybourne Road to Petersfield Road f/p

awaiting dates from contractor

Appleshaw Green to Petersfield Road f/p

awaiting dates from contractor

Spencer Road to Petersfield Road f/p

awaiting dates from contractor

Belmont Grove to Bedhampton Road f/p

awaiting dates from contractor

Puffin Walk to Bedhampton Road f/p

awaiting dates from contractor

4.3 In addition, the Borough Council is separately funding improved lighting schemes for Covert Grove to Tamerisk Close footpath and Emsworth Recreation Ground.

5. Energy

5.1 The new `green' energy contract commenced on 1 April 2004 with no problems to date and will continue until March 2006. Monitoring of this contract is ongoing.

Recommendation

That this report be noted

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

1.

Published works.

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None

8909/ALS