Archived decisions

Hampshire County Council

Executive Member - Recreation and Heritage

Item 1

18 November 2004

Community Buildings Fund - 2004/05

Report of the Director of Recreation and Heritage

Contact: Margaret Plumridge, ext 6173

1. Summary

1.1 The County Council works in partnership with specific community organisations particularly community associations and village hall committees who seek to enable local people to meet the recreational, educational, social, cultural and environmental needs of their local communities. These organisations give local people an opportunity to participate in local activities and encourage local initiatives by people of all ages.

1.2 The Council has wide powers under Section 19 Local Government (Miscellaneous Provisions) Act 1976 to provide recreational facilities, and to contribute by way of grant or loan towards expenses incurred by voluntary bodies in providing such facilities.

1.3 Corporate Strategy

    Partnership funding from the Community Buildings Fund enables the community sector to maintain the quality of Hampshire's cultural assets, namely their village halls and community association buildings some of which are listed. This finance enables improvements to be made to those buildings and can assist with the development of new facilities where appropriate. The provision of these buildings by the voluntary sector enables local communities to access the services and facilities they need.

    By providing financial support to these organisations for the maintenance of their buildings the County Council is able to work in partnership with the community sector to achieve the Corporate Aim - Stewardship of the Environment.

2. Purpose of Report

2.1 The purpose of this report is:

    i) to provide details of the current financial position of the Community Buildings Fund, and

    ii) to provide details of requests for partnership funding from the fund.

2.2 The partnership funding distribution criteria is set out in Appendix 1.

2.3 Projects listed in Appendix 2 meet fully the criteria and have been allocated a proposed level of funding in line with the criteria.

2.4 Projects listed in Appendix 3 have applied for and are eligible for funding. However, further information is required about their funding package before they are brought forward for approval.

2. Finance

2.1 After provisionally setting aside £50,000 for major schemes there remained an allocation of £150,000 in the Recreation and Heritage capital programme for 2004/05 for the Community Buildings Fund. After allowing for decisions taken on 13 May (£60,755), 1 July (£42,520) and 16 September (£42,149) and the decision made by Councillor Thornber in respect of a request from Ringwood Community Association (£3,500) amounting in total to £148,924 there remains an unallocated balance of £1,076.

2.2 In order to meet the recommended allocations in this report of £6,033 it will be necessary to transfer £4,957 from the revenue budget to the capital programme. There remains an unallocated balance in the budget for annual revenue support to community organisations of £1,828. The balance of £3,129 can be met from a delayed staffing appointment achieved earlier in the year. If agreed, the formal transfer can be transacted in the coming budget process.

Recommendations

The following decision is sought:

    i) that partnership funding totalling £6,033 be approved for allocation from the Community Buildings Fund as listed below:

Hall/Centre

District

£

Bramshaw Village Hall

New Forest

4,200

The Parish Hall, Emsworth

Havant

1,833

Total

6,033

Section 100 D - Local Government Act 1972 - Background Documents

    The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

    NB the list excludes:

    Published works

    Documents, which disclose exempt or confidential information as, defined in the act.

    Title Location

Applications for financial assistance Community Support Service

              Recreation and Heritage Department

              Mottisfont Court

              Winchester

Appendix 1

The application criteria for the Community Grants Fund is as follows:

    Partnership funding is granted for:

      · Building repairs, extensions and refurbishments

      · Health and Safety issues

      · Equipment to improve the buildings and increase usage

      · Feasibility Studies

    Who can apply:

      · Village Halls (not parish run halls)

      · Community Associations

      · Other similar community groups

      · Church Organisations that have a separate community programme on their property

    Funding criteria:

      · For projects costing less than £15,000, the funding criteria is up to one third of the cost.

      · For projects costing more than £15,000, the grant is calculated at 50% of the combined district and parish contribution up to a maximum of 25% of the project costs or £12,500, whichever is the lesser.

      · Feasibility Studies - applications will be considered for 50% of the cost up to a maximum of £500

    Priority Criteria:

      1. Health and safety issues that could result in the building being closed or activities seriously curtailed if the work is not carried out.

      2. The work is absolutely essential in order to meet the terms of the Disability Discrimination Act. (It has been widely publicised that these types of buildings will not be closed provided reasonable steps have been taken to meet the terms of the Act).

      3. The project is part of a phased development and this element is essential to it's overall completion.

      4. Non priority work.

Appendix 2

    Summary of grant applications received

Priority 1 Health and Safety

Hall/Centre

District

£

     

Total

 

0

Priority 2 Disability Discrimination Act

Hall/Centre

District

£

     

The Parish Hall, Emsworth

Havant

1,833

     
     

Total

 

1,833

Priority 3 Phased Development

Hall/Centre

District

£

Bramshaw Village Hall

New Forest

4,200

Total

 

4,200

Priority 4 Applications for General Improvement Works

Hall/Centre

District

£

     

Total

 

0

Applications awaiting further information on their funding package:

Hall/ Centre

District

£

Priority

Beech Village Hall

East Hampshire

12,500

1

Brockenhurst Village Hall

New Forest

12,500

4

Froyle Village Hall

East Hampshire

10,000

2

Highclere Village Hall

Basingstoke & Deane

12,500

2

Kilmeston Village Hall

Winchester

12,500

2

Swanmore Methodist Church

Winchester

6,250

2

       

Total

 

66,250

 

Name:

Bramshaw Village Hall

Consultation:

The local member, Cllr Melville Kendal, has been consulted.

Project:

Erection of new front entrance, improve front façade, new fire screen in hallway, renew old plumbing and purchase of tables and seat cushions.

Priority:

3 - phased work

Criteria:

Building repairs, extensions and refurbishment

Equipment to improve the buildings and increase usage

Links to Corporate Strategy:

Improving buildings to enable local communities to access the services and facilities they need.

This project will improve the facilities for the use of the community

Cost:

£12,600

General Reserves:

£13,000

Project Reserves:

£9,000 reserved for this project

Statement:

Good progress has been made in increasing usage since phase one of the refurbishment programme last year. This work will continue the programme and improve income to the hall so that service to the community can continue.

Funding:

Own funding available - £9,000

New Forest District Council - application made - no amount specified

Bramshaw Parish Council - £100 applied for

Recommendation:

£4,200 as one third of project cost

Name:

The Parish Hall, Emsworth

(Church Parish of Warblington with Emsworth)

Consultation:

The local member, Cllr David Gillett, has been consulted.

Project:

Disabled access ramp

Priority:

2 - DDA

Criteria:

Building repairs, extensions and refurbishment

Equipment to improve the buildings and increase usage

Links to Corporate Strategy:

Improving buildings to enable local communities to access the services and facilities they need.

This project will improve the facilities for the use of the community.

Cost:

£5,499

General Reserves:

Estimated at £2,000 (Only accounts for the hall have been provided and not for the wider church parish)

Project Reserves:

£4,500 for this project

Statement:

Access ramp required to meet DDA legislation. The hall provides accommodation for a wide variety of community activities.

Funding:

Own funding available - £4,500

Havant Borough Council - £500 applied for

Recommendation:

£1,833 as one third of project cost

Appendix 3

Organisations that have applied for and are eligible for funding but more information about their funding package is required

Name:

Beech Village Hall

Local Member:

Cllr Anthony Ludlow

Project:

Demolish and replace existing building with new hall

Priority:

1 - Health and Safety

Criteria:

Building repairs, extensions and refurbishment (new building)

Links to Corporate Strategy

Improving buildings to enable local communities to access the services and facilities they need.

This project will provide new facilities for the use of the community

Cost:

£746,000

General Reserves:

£3,000

Project Reserves:

£20,000

Statement:

This project is needed to provide adequate meeting and recreational facilities within Beech as recommended in the village survey and analysis carried out in December 2002, and to ensure such facilities are compliant with the Disability Discrimination Act.

Funding:

East Hampshire District Council - £24,000 confirmed

Beech Parish Council - £10,000 confirmed

Own funds - £20,000

Lottery application - £300,000 (planned to be submitted in October 2004)

Local fundraising - £266,000

Other sources - £100,000

Recommendation:

£12,500 as 50% of combined district and parish council contribution subject to maximum funding limit.

Notes - Date and status of lottery application to be confirmed

Name:

Brockenhurst Village Hall

Local Member:

Cllr. Ken Thornber

Project:

Extend village hall to provide new stage, craft room and exhibition space.

Priority:

4 Non Priority

Criteria:

Building repairs, extensions and refurbishment.

Links to Corporate Strategy

Improving buildings to enable local communities to access the services and facilities they need.

This project will improve the facilities and extend its use to the community

Cost:

£821,000

General Reserves:

£112,500

Project Reserves:

£160,000 for development of buildings other than the Village Hall held as restricted funds

Statement:

The aim of the project is to extend the village hall to enable the provision of a cultural and arts centre for both Brockenhurst and the surrounding area.

Funding:

New Forest District Council - application made - no amount specified

Brockenhurst Parish Council - application made - £40,000

Arts Council - application made - £600,000 (decision not yet made)

Additional applications made to 12 charitable trusts

Recommendation:

£12,500 as 50% of combined district and parish council contributions subject to maximum funding limit and confirmation

Notes - Status of Arts Council bid to be confirmed

June - Arts council bid unsuccessful

    August - application made to landfill tax fund

    October - approximately £165,000 raised - scope of project now reduced to around £400,000.

    October - £50,000 recommended by landfill tax panel.

Name:

Froyle Village Hall

Local Member:

Cllr Sir James Scott

Project:

Extend kitchen, refurbish toilet area and provide disabled toilets and accessible entrance

Priority:

2 - Disability Discrimination Act

Criteria:

Building repairs, extensions and refurbishment

Health and Safety issues

Links to Corporate Strategy

Improving buildings to enable local communities to access the services and facilities they need.

This project will improve the facilities and extend their use to the community

Cost:

£98,700

General Reserves:

£28,000

Project Reserves:

Nil

Statement:

Required to provide more space to cope with village events and provide disabled toilet to comply with Disability Discrimination Act.

Funding:

East Hampshire District Council - £15,000 applied for

Froyle Parish Council - £5,000 confirmed

Own funds - £10,000

Other donations - £8,000

Lottery - £45,700 applied for

Recommendation:

£10,000 as 50% of combined district and parish council contributions subject to confirmation.

Note - October -lottery bid refused - scope of project being reduced

Name:

Highclere Village Hall

Local Member:

Cllr John Wall

Project:

Refurbish hall to include:

    · Creation of disabled toilet

    · Improved access for elderly and disabled

    · Removal of all damp and noise pollution

    · Improved insulation

    · Enlarged floor area & seating capacity

    · Upgrading and updating of electrics

Priority:

2 - Disability Discrimination Act

Criteria:

Building repairs, extensions and refurbishment

Health and Safety issues

Links to Corporate Strategy

Improving buildings to enable local communities to access the services and facilities they need.

This project will improve the facilities and extend their use to the community

Cost:

£159,875

General Reserves:

£18,023

Project Reserves:

Nil

Statement:

These works were identified following local consultation and an access audit.

Funding:

Own funds - £20,000

Basingstoke & Deane Borough Council - £43,000 applied for

Highclere Parish Council - £5,000 applied for

Lottery application - £75,000 applied for

Local donations - £6,875

Recommendation:

£12,500 as 50% of combined contributions from district and parish councils subject to maximum limit and confirmation

Notes - Lottery application refused

    Application being made to Landfill Tax Fund

    Bas. & Deane BC - £18,000 confirmed from developers contributions

          - £25,000 recommended from leisure funds - decision due September

Name:

Kilmeston Village Hall

Local Member:

Cllr Susan Glasspool

Project:

Refurbish hall, kitchen and toilets to modern standards and to meet DDA requirements

Priority:

2 - Disability Discrimination Act

Criteria:

Building repairs, extensions and refurbishment

Links to Corporate Strategy

Improving buildings to enable local communities to access the services and facilities they need.

This project will improve the facilities and extend their use to the community

Cost:

£118,182

General Reserves:

£20,000

Project Reserves:

£9,000 for this project

Statement:

Current building is non compliant with DDA and is barely acceptable for general use. Standards of heating are inadequate for use by elderly. There is no other facility available to encourage social inclusion in the village.

Funding:

Own funds - £19,000

Winchester City Council - £20,000 confirmed over 2 years

Kilmeston Parish Council - £5,000 applied for

Community fund - £70,849 application made

Recommendation:

50% of combined district and parish council contributions to a maximum of £12,500 subject to confirmation

Notes - October - lottery bid refused - scope of project being reduced

Name:

Rockbourne Village Hall

Local Member:

Cllr Katherine Heron comments that this is a small village on the county border and consequently the precept is very small. She requests that a larger contribution be considered.

Project:

Extend and refurbish hall to provide new and accessible facilities including new meeting room, kitchen, storage and toilets.

Priority:

2 - Disability Discrimination Act

Criteria:

Building repairs, extensions and refurbishment

Links to Corporate Strategy

Improving buildings to enable local communities to access the services and facilities they need.

This project will improve the facilities and extend their use to the community

Cost:

£150,000

General Reserves:

£7,900

Project Reserves:

Nil

Statement:

This work will particularly benefit older and disabled people living in Rockbourne which has poor public transport and no community transport scheme.

Funding:

Own funds - £8,150

New Forest District Council - £9,000 applied for

Rockbourne Parish Council - £1,000 applied for

Community Fund/DEFRA £127,350 applied for (response not expected before end of 2004)

Notes:

We have already contributed £500 in 2003/04 to a feasibility study. This study has also been supported by the Community Fund, district and parish councils. This application is for the main building project.

Recommendation:

50% of the combined district and parish council contributions to a maximum of £5,000 subject to confirmation (based on notified contributions)

Note - Date and status of Community Fund/DEFRA bid to be confirmed

Name:

Swanmore Methodist Church

Local Member:

Cllr Peter Mason

Project:

Demolish existing hall and replace with new hall.

Priority:

2 - DDA

Criteria:

Building repairs, extensions and refurbishment

Links to Corporate Strategy:

Improving buildings to enable local communities to access the services and facilities they need.

This project will provide new facilities for the use of the community

Cost:

£481,000

General Reserves:

Total church reserves £50,575

Declared free reserves £9,000

Project Reserves:

Nil

Statement:

The existing premises require major work to rectify problems and as they are situated on three levels cannot comply with DDA. Health & safety standards cannot be fully met with existing facilities. Redevelopment will increase usable space and provide better facilities for the local community which has risen by some 30% over past 12 years. The current hall is used by a range of community groups including Swanmore pre-school, The Swanmore Society, Community Education Art Classes, Brownies, West End Choir. Additionally the church itself provides a range of activities to support the community including free cinema sessions, mother and toddler group, ladies and mens groups and other activities for children. Local authority planning permission has been granted.

Funding:

Winchester City Council - £12,500 applied for with additional application to Community Chest fund

Swanmore Parish Council - application made - no amount specified

Other applications made to 18 charitable trusts

Recommendation:

Agree that project meets criteria but no allocation of funds until 2005/06 subject to confirmation of District, Parish and other funding applications.