AT A MEETING of the BUILDINGS, LAND AND PROCUREMENT PANEL of the County Council held at The Castle, Winchester on 2 February 2005.

PRESENT:

Councillors: T. K. Thornber, CBE (Chairman); M. F. Cartwright; B. D. Dash;

C. Davidovitz; D. A. Kirk; J. W. Stocks; J. K. West.

Also in attendance: Councillor Jo Kelly.

Councillor G. W. Davies-Dear for the Crescent Primary School Item and the

Mount Hospital Site Item (Minutes 229 and 237 refers).

220 DECLARATIONS OF INTEREST

Members were mindful that, where they believed they had a personal or

personal prejudicial interest in any matter to be considered at the meeting, they

should normally at the time of the debate declare their interest, and having

regard to the circumstances described in paragraphs 9, 10, 11 and 12 of the

County Council's Code of Conduct, consider whether to leave the meeting

whilst the matter was discussed.

221 MINUTES

The Minutes of the meeting held on 30 November 2004 were confirmed as a

correct record and signed by the Chairman.

222 CHAIRMAN'S COMMUNICATIONS

There were no Chairman's Communications.

223 DEPUTATIONS

    There were no deputations.

224 PROJECT APPRAISAL : COUNTRY TOWNS INITIATIVE - HYTHE

PROMENADE

    The Panel considered the report of the Director of Environment (Item 6 in the

    Minute Book) on a project appraisal for improvements to Hythe Promenade as

    part of the Country Towns Initiative. Members supported the proposals as a

    key opportunity to improve the economic prosperity of Hythe as a visitor

    attraction.

    RESOLVED:

    That the Buildings, Land and Procurement Panel advises the Executive

    Member for Policy and Resources that the project appraisal for improvements to Hythe Promenade as part of the Country Towns Initiative, at an estimated cost of £771,500, be approved.

225 PROJECT APPRAISAL : HOUSEHOLD WASTE RECYCLING

CENTRE, WADE ROAD, BASINGSTOKE - EXPANSION OF

OPERATIONAL AREA

    The Panel considered the report of the Director of Environment (Item 7 in the Minute Book) on a project appraisal to carry out works to expand the operational area at the Household Waste Recycling Centre in Wade Road, Basingstoke. Members supported the design proposals to significantly improve one of the busiest recycling centres in Hampshire by addressing some of the key issues of reducing congestion to improve the service for the local residents of Basingstoke.

    RESOLVED:

    That the Buildings, Land and Procurement Panel advises the Executive

    Member for Policy and Resources that the project appraisal to carry out works to expand the operational area at the Household Waste Recycling Centre at Wade Road, Basingstoke, at an estimated cost of £650,000, be approved.

226 BROOKFIELD COMMUNITY SCHOOL, SARISBURY GREEN,

SOUTHAMPTON - BUILDING DESIGN PROJECT APPRAISAL

The Panel considered the report of the Director of Property, Business and

Regulatory Services (Item 10 in the Minute Book) on a building design project

appraisal for internal refurbishment works to create a fully accessible school

for pupils with a wide range of impairments and to ensure that the curriculum

can be carried out at ground level.

RESOLVED:

That the Buildings, Land and Procurement Panel advises the Executive

    Member for Policy and Resources that the design project appraisal for the

    Brookfield Community School at an estimated cost of £880,000, excluding

    fees, be approved.

227 CALMORE INFANT SCHOOL, CALMORE, SOUTHAMPTON -

BUILDING DESIGN PROJECT APPRAISAL

    The Panel considered the report of the Director of Property, Business and

    Regulatory Services (Item 9 in the Minute Book) on a building design project

    appraisal for internal refurbishment works to provide an early years unit,

    language impairment unit, an area base for the early Educational and

    Childcare Unit and refurbished classrooms at Calmore Infant School.

    Members supported the scheme and the opportunities which existed to

    consider an overall integrated approach towards Early Years Centres at

    primary school age and beyond.

    RESOLVED:

    That the Buildings, Land and Procurement Panel advises the Executive

    Member for Policy and Resources that the building design project appraisal

    for Calmore Infant School, at an estimated cost of £377,000, excluding fees,

    be approved.

228 THE CRESCENT PRIMARY SCHOOL, EASTLEIGH - BUILDING

DESIGN PROJECT APPRAISAL

The Panel considered the report of the Director of Property, Business and

    Regulatory Services (Item 10 in the Minute Book) on a building design project

    appraisal for a new library and link corridor extension and two classroom

    extension at The Crescent Primary School. Members welcomed the proposals

    and also asked that consideration should be given to the removal of two

    temporary buildings and their replacement with permanent accommodation

    RESOLVED:

    That the Buildings, Land and Procurement Panel advises the Executive

    Member for Policy and Resources that:

    (i) the building design project appraisal for The Crescent Primary School, at

    an estimated cost of £696,000, excluding fees, be approved.

    (ii) consideration be given to the removal of the two temporary classrooms

    and their permanent replacement to be reported to the next meeting of the

    Panel.

229 CRESTWOOD PRIMARY SCHOOL, EASTLEIGH - BUILDING

DESIGN PROJECT APPRAISAL

The Panel considered the report of the Director of Property, Business and

Regulatory Services (Item 11 in the Minute Book) for a building design

appraisal for a new community sports hall, drama studio and fitness suite at

Crestwood Primary School.

RESOLVED:

That the Buildings, Land and Procurement Panel advises the Executive

Member for Policy and Resources that the building design project appraisal

for Crestwood Primary School, at an estimated cost of £3,193,127, be

approved.

230 NETLEY MARSH CHURCH OF ENGLAND INFANT SCHOOL, SOUTHAMPTON - BUILDING DESIGN PROJECT APPRAISAL

    The Panel considered the report of the Director of Property, Business and

    Regulatory Services (Item 12 in the Minute Book) for a building design project appraisal for new classrooms, extended classroom and extended hall at Netley Marsh Church of England Infant School.

    RESOLVED:

    That the Buildings, Land and Procurement Panel advises the Executive Member for Policy and Resources that the building design project appraisal for Netley Marsh Church of England School, at an estimated cost of £739,000, excluding fees, be approved

231 ST LAWRENCE CHURCH OF ENGLAND (CONTROLLED)

PRIMARY SCHOOL, ALTON - BUILDING DESIGN PROJECT

APPRAISAL

    The Panel considered the report of the Director of Property, Business and

    Regulatory Services (Item 13 in the Minute Book) on a building design project appraisal for an extension to provide a new hall, kitchen, link building and internal refurbishment at St Lawrence Church of England (Controlled) Primary School. The Panel noted the concerns of the Local Member regarding future plans to extend the playground into the church yard which he feels is unacceptable in a conservation area.

    RESOLVED:

    That the Buildings, Land and Procurement Panel advises the Executive

    Member for Policy and Resources that the building design project appraisal for St Lawrence Church of England (Controlled) Primary School, at an estimated cost of £684,000, excluding fees, be approved.

232 STAUNTON PARK COMMUNITY SCHOOL, HAVANT - BUILDING

DESIGN PROJECT APPRAISAL

The Panel considered the report of the Director of Property, Business and

Regulatory Services (Item 14 in the Minute Book) on a building design project

Appraisal for a Healthy Living Centre and ancillary accommodation at

Staunton Park Community School.

RESOLVED:

That the Buildings, Land and Procurement Panel advises the Executive

Member for Policy and Resources that:

(i) approval be given to carry forward the Capital Programme

(Modernisation) funding of £71,000, excluding fees, to the 2005-06

Capital Programme.

(ii) the building design project appraisal for Staunton Park Community School

at an estimated cost of £622,000, excluding fees, be approved.

(Note: Whilst (ii) represents an accurate record of the figure reported to the Panel, an error was subsequently found and the correct sum of £543,000 excluding fees has been included in the report to the Executive Member for Policy and Resources).

233 BISHOPS WALTHAM HOUSE : OLDER PERSON'S HOME -

PROPOSED IMPROVEMENTS (PHASE 1)

The Panel considered the report of the Director of Property, Business and

Regulatory Services (Item 15 in the Minute Book) on a building design project

appraisal for essential fire precaution improvements at Bishops Waltham

Older Person's Home.

RESOLVED:

That the Buildings, Land and Procurement Panel advises the Executive

Member for Policy and Resources that the building design project appraisal

for Bishops Waltham Older Person's Home, at an estimated cost of £455,000,

excluding fees, be approved.

234 MISCELLANEOUS APPROVALS

The Panel considered the report of the Director of Property, Business and

Regulatory Services (Item 16 in the Minute Book) on a range of issues

associated with revisions to the New Deal for Schools (NDS) Condition

Programme 2004/05, additional items into the capital repairs budget and the

erection of temporary buildings at All Saints Primary School, Winchester.

RESOLVED:

That the Buildings, Land and Procurement Panel advises the Executive

Member for Policy and Resources that approval be given to:

(i) the additional NDS allocations as detailed in paragraph 2.

(ii) the capital repairs allocations as detailed in paragraph 3.1.

(iii) seeking planning permission for the erection of temporary buildings at

All Saints Primary School, Winchester during the period of refurbishment

work in spring/summer 2005 at Langdown Infant School, Hythe during the

development of Waterside primary School 2005/06.

235 EXCLUSION OF THE PRESS AND PUBLIC

RESOLVED

That, by virtue of paragraph 9 of Part 1 of Schedule 12A of the Local

Government Act 1972, the press and public be excluded for the remainder of

the meeting.

236 BUSINESS SERVICES GROUP - BUSINESS PLANS 2005 - 2006

The Panel considered the confidential report of the Director of Property,

Business and Regulatory Services (Item 18 in the Minute Book) on the

2005- 2006 business plans of the Business Services Group.

During discussion of the Plans, Members noted with concern any negative

impact which the Corporate Pay and Benefits Project would have on the

viability of the Businesses.

RESOLVED:

That the Buildings, Land and Procurement Panel advises the Executive

Member for Policy and Resources that approval be given to:

(i) the business plans for HCS3, County Supplies, Hampshire Transport

Management Printing Services and the proposed use of the accumulated

surplus.

(ii) in future Members of the Panel be selected to assume a continuing

responsibility for one Business Unit.

237 PROPOSED PURCHASE OF THE MOUNT HOSPITAL SITE,

BISHOPSTOKE

    The Panel considered the confidential report of the Director of Property,

    Business and Regulatory Services (Item 19 in the Minute Book) on the

    purchase of the freehold interest in land at the Mount Hospital Site,

    Bishopstoke.

    RESOLVED:

    That the Buildings, Land and Procurement Panel advises the Executive

    Member for Policy and Resources that approval be given to

    (i) the County Council to enter into an agreement with the Winchester and

    Eastleigh NHS Healthcare Trust to purchase its freehold interest in

    approximately 14.2 ha (35.1 ac) of land at The Mount Hospital,

    Bishopstoke, as set out in the report and the Director of Property,

    Business and Regulatory Services (Head of Estates Practice) be

    authorised to settle terms and conditions.

    (ii) the preparation of planning and design proposals for the redevelopment

    of The Mount Hospital site.