HAMPSHIRE, PORTSMOUTH AND SOUTHAMPTON MINERALS AND WASTE LOCAL PLAN (ADOPTED 17 DECEMBER 1998)

Policy 6

Permission will be granted for minerals and waste development provided the Mineral/Waste Planning Authority is satisfied that:

(i) there is a clearly established need for the development (as assessed in relation to the other relevant policies of the Plan) which outweighs any adverse environmental or other impact that the development would be likely to cause; and

(ii) the development would not be likely to give rise to an unacceptable level of adverse environmental, traffic or other impact, pollution risk or danger to public health, particularly in respect of any of the factors specified in Policy 7 and measures would be taken to ensure that any such impacts would, as far as is practicable, be minimised; and

(iii) the proposals provide for the satisfactory working or operation and landscaping of the site and for its satisfactory restoration and landscaping at the cessation of the operations or use or at the end of the life of the facility to a condition suitable for an agreed beneficial after-use which is compatible with adjoining land uses and the planning policies for the area.

Notwithstanding any need there may be for waste disposal, permission will not normally be granted for mineral extraction with restoration by infilling with waste materials unless there is a need for the mineral to be extracted.

Policy 46

The Waste Planning Authorities will normally permit the use of land and the erection of plant and buildings for the recycling, transfer, storage and other treatment or handling of waste (excluding waste processing facilities covered by Policy 45) provided that:

(i) the proposed site is located near to the likely source(s) of waste and/or the market(s) for the recycled or recovered materials; and

(ii) the proposed site is located close to and has adequate access to the Hampshire Lorry Route Network (as shown on the proposals map), so that the development would not be likely to cause unacceptable traffic impact (including the environmental impact of traffic) on the local highway network; and

(iii) the proposed site is located:

        (a) within an existing industrial site or on land which is permitted or allocated for industrial development; or

        (b) within an area of land in the countryside that has already been disturbed by permanent development (a brownfield site); or

        (c) at a waste disposal landfill or landraising site provided that the proposed development is connected with the waste disposal operation and is for a temporary period commensurate with the operational life of the waste disposal facility; and

(iv) the proposed site is located and the proposal includes adequate measures to ensure that no unacceptable impact would be likely to be caused to the occupants or users of houses, other residential buildings, schools, hospitals and other environmentally sensitive buildings and land uses by reason of noise, dust, fumes, smell or other cause; and

(v) the proposed site is located so as to avoid unacceptable impact on landscape, nature conservation and archaeological interests; and

(vi) the proposed site is located and the proposal includes adequate measures to ensure that there would be no significant risk of pollution or danger to public health or safety; and

(vii) the proposed site is located and, if necessary, the proposal includes landscaping measures to ensure that the development would not cause unacceptable visual intrusion.