Archived decisions
|
|
|
STRATEGIC PLANNING JOINT ADVISORY PANEL | ||
Date: 2 March 2005 Item 6
Report by: The Hampshire Director of Environment, Portsmouth Strategic Director for Environment and Transport and Southampton Executive Director of Development and Sustainability
HAMPSHIRE STRUCTURE PLAN POLICY H4 MONITORING PAPER
Written by: Sue Clark, tel: (01962) 845890 email: [email protected]
Purpose and Summary:
To inform the Panel of the conclusions arising from the Hampshire County Structure Plan Policy H4 Monitoring Paper 2005 and the outcome of consultation.
The Paper concludes that the forecast dwelling supply 2004-2011 exceeds the requirement in Regional Planning Guidance (RPG). The total supply exceeds the RPG requirement by almost 12,000 dwellings. This overall figure was subject to adjustments and sensitivity testing in recognition that not all potential will ultimately be developed within the timescales expected. The results show an adjusted figure that is still 5,000 dwellings above the RPG requirement. On the basis of this year's monitoring there appears to be no compelling justification at this time to release any of the Structure Plan housing reserve. However this does not mean that the reserve will not be needed at all in the period to 2011. There is some uncertainty regarding the supply figures, particularly in relation to the likely contribution from Major Development Areas (MDAs) and urban capacity. In addition, many proposed local plan allocations are still some way off from being released for development.
A total of 24 organisations and individuals commented on the Monitoring Paper. The Government Office for the South East (GOSE) has some confidence that in the short term there is sufficient supply to meet the requirement. However, writing on behalf of the Minister for Planning, the Office states that it is not possible for the Minister to agree with the conclusion of the 2005 H4 report until he has had time to consider the first progress report on the Hampshire Housing Action Plan. The progress report has been sent to the Minister and his views are awaited. The development industry remains sceptical regarding the overall supply figures used in the Paper; the accuracy of the forecasts and consequentially its conclusions. Other interested parties such as local planning authorities and local interest groups were more supportive of the Paper and its findings and most of them supported the general conclusions of the report.
RECOMMENDATIONS:
That the three Strategic Planning Authorities be recommended to:
(i) note the consultation responses;
(ii) recommend to the Regional Assembly that no reserve sites be released at the present time;
(iii) urge all local planning authorities to continue to take proactive steps to manage housing land supply to meet or exceed their Structure Plan baseline housing requirement and make provision for the reserve provision, where required; and
(iv) thank all consultees who responded to this year's Monitoring Paper for their comments, enclosing a copy of this report and appendix and informing them of the decisions made by this Panel in respect of it.
1. Introduction/Background
1.1 Policy H4 in the adopted Structure Plan provides a reserve of land for housebuilding that will be released if, and when, the strategic and local planning authorities decide it is needed. The purpose of the policy is to ensure that sufficient housing land is provided throughout the Structure Plan area to meet identified needs, while avoiding the unnecessary use of greenfield land.
1.2 Structure Plan Policy H4 states that "The strategic planning authorities will only support the release of individual greenfield allocations to meet this reserve provision where monitoring of the Structure Plan and Local Plans indicates there is a compelling justification to do so". Policy H4 is in line with Government guidance in PPG3 to give priority to re-using previously developed land within existing urban areas in preference to the development of greenfield sites.
1.3 The first three Policy H4 Monitoring Papers concluded that there was no case at that time for triggering the release of any of the reserve provision, but that the situation needed to be considered again when better information was available.
1.4 The Policy H4 Monitoring Paper 2005 was published in December 2004 and is based on completions information up to March 2004 and the most up-to-date estimates of future housing supply.
2. Aims and Visions of Corporate and Community Strategies
2.1 This report supports the aims and visions of the three strategic planning authorities' corporate and community strategies by helping ensure that sufficient new homes are made available whilst securing the regeneration of existing urban areas and avoiding the unnecessary development on greenfield land.
3. The 2005 Monitoring Paper
3.1 The 2005 Monitoring Report forecasts that housebuilding between 2001-2006 will exceed the RPG figure. Dwellings supply for the period 2006-2011 is also forecast to exceed the RPG figure.
3.2 The number of dwellings at the start of April 2004 with planning consent was 2% higher than the position a year earlier, despite a very high level of completions during the preceding 12 months. Some 75% of all permissions (14,100) are in full which means there are no planning obstacles to these homes being built.
3.3 The total supply potentially available 2004 to 2011 is almost 12,000 dwellings above the RPG requirement.
3.4 However, not all of this supply will actually be built in this period for a variety of reasons (eg planning, ownership and market). The total supply has accordingly been adjusted to take account of this. Adjustments applied were small for dwellings with planning permission, higher for local plan allocations and highest for urban capacity sites. The forecast of completions based on these adjustments indicates that housebuilding in 2004/05 should exceed the RPG figure and remain above the RPG for the rest of the plan period.
3.5 The adjusted supply for the period 2004 to 2011 is forecast to exceed the RPG requirement by some 5,000 dwellings - some 12% in excess of what Hampshire is required to build.
4. Consultation
4.1 The 2005 Monitoring Paper was sent to 83 consultees, representing a wide variety of interests (eg developers, local authorities, parish councils and conservation groups). In addition, a further three copies of the report were sent out on request.
4.2 Comments were received from 24 respondents:
(i) 9 developer interests;
(ii) 5 environmental/conservation groups;
(iii) 4 Hampshire District Councils;
(iv) 1 parish council
(v) GOSE; and
(vi) 4 others.
4.3 The number of responses this year was lower than last year (24 this year, 38 last year), with just over a third of the responses from developer interests. A summary of the main points arising from consultation responses with a response by the Strategic Planning Authorities is attached as an appendix.
5. Main Points Arising from Comments
Completions and Estimates of Housing Supply
5.1 Some respondents repeated comments made about previous Policy H4 Monitoring Papers, stating that the paper failed to give an accurate picture of housing supply as it did not address the backlog arising at the beginning of the Structure Plan period. In addition, some commented on the need to deliver housing equal to the baseline plus reserve for the period 1996-2011.
5.2 A few respondents from the development industry stated that, with the exception of the odd year, (including 2003/04) the supply of housing in Hampshire has consistently fallen beneath the amount required and they were concerned that the levels of housing completed last year were a one-off and unsustainable.
5.3 GOSE commented that Hampshire is now within 5% of the requirement set out in RPG9.
Officers' Response
5.4 GOSE has stated previously that there is no requirement to make up any shortfall before 2001 - the start year of the RPG. The shortfall was taken into account in setting the current RPG requirement (6,030 per annum).
5.5 Since 2001 the number of dwellings completed was below the RPG figure for the first two years and above it in the third year. The higher level of completions in 2003/04 made up much of the shortfall of the previous two years. This year it is estimated that completions will again exceed the RPG figure and a sustained period of completions in excess of the current RPG requirement will follow. The cumulative shortfall in dwellings (913) compared to RPG requirements will be recouped over the next two years. Using the monitoring paper's adjusted forecast, completions would exceed the current RPG requirement by over 5,000 over the whole period 2001 to 2011.
Discounting and Sensitivity Testing
5.6 The use of discounting and sensitivity testing was supported in general, by both the development industry and other consultees. However there were differing views about the rates applied, with some respondents commenting on the difficulty in assessing these rates without a clearer justification. GOSE stated that, compared to last year's report, more work had been done on calculating the adjusted supply, increasing confidence in the figures.
5.7 A few of the respondents from the development industry considered that the unadjusted supply figures were over optimistic, particularly for west of Waterlooville MDA, and therefore the adjusted supply may also be over optimistic. The Housebuilders Federation stated that they did not object to the fairly cautious approach taken.
5.8 Comments were also made about the deliverability of unidentified supply from several respondents, including GOSE. Where unidentified sites comprise a large component of the supply, anticipating significant increases over recent build rates, GOSE will be writing separately to those authorities asking what actions are being taken to deliver this supply.
Officers' Response
5.9 The discount rates which were applied were subject to consultation before analysis was begun on the monitoring paper.
5.10 The unadjusted supply from MDAs was reduced by 500 dwellings before the discount was applied, to take in to account the optimistic level of supply from this source. The 20% discount applied to the MDAs (in addition to the 500 dwellings discount) is considered to be appropriate.
5.11 The deliverability of the unidentified supply is less certain than most other sources. Three Urban Capacity studies have been examined by local plan inspectors who have made recommendations in relation to urban capacity and windfall sites. For the remaining districts an audit of urban capacity studies was undertaken by the strategic planning authorities which concluded that, whilst the majority of the studies appeared to produce realistic estimates, some appeared to underestimate capacity and others slightly overestimate capacity. It concluded overall that urban capacity for the ten districts studied is likely to be underestimated. Following a review of the inspector's reports and the audit of the remaining Urban Capacity Studies, the capacity from this source was reduced by 600 dwellings and then a further discount of 15% was applied. It is considered that this approach errs on the side of caution.
Overall Supply
5.12 Several comments were received stating the need for a more detailed breakdown of the information, including data on the situation in individual districts and three sub-areas to demonstrate that sufficient completed dwellings will be produced by 2011.
5.13 It was also proposed that housing supply should be placed in the context of the options emerging in the South East Plan. The potential for confusion, with local plans and Regional Spatial Strategy being approved concurrently with different targets, was commented on. Several respondents also argued for a reference to the Action Plans, the progress on these and commented on the ability of the Action Plans to deliver sufficient housing.
Officers' Response
5.14 The detailed breakdown of information by district or sub-area is interesting but is not needed to determine whether or not there is a compelling requirement to release any of the Structure Plan reserve. It has been excluded from this year's monitoring paper in order to produce a clearer and more focused report. A number of respondents have requested additional information which has been supplied.
5.15 It would be inappropriate to examine housing supply in the context of the options emerging in the South East Plan, as these are currently only draft options for the purposes of consultation and were not agreed when the report was published.
5.16 The Structure Plan Policy H4 monitoring paper is not considered the appropriate place for a progress report on the Hampshire Housing Supply Action Plan. A Progress Report on the Action Plan is a separate matter which is addressed elsewhere on this agenda.
Other Matters Raised
5.17 A number of other detailed points were raised. The officers' response to these are contained in the appendix.
6. Conclusions
6.1 Many of the comments about the Monitoring Paper are similar to those expressed in previous years.
6.2 There remains scepticism amongst the development industry regarding the overall supply figures used, the accuracy of the forecasts and consequentially its conclusions. Other interested parties, such as local planning authorities and local interest groups, were more supportive of the Paper and its findings and most of them supported the general conclusions of the report.
6.3 Despite the misgivings of some respondents, the overall conclusion of the Paper - that there will be sufficient supply to meet requirements to 2011 - is considered to be a fair assessment based on current information. There is currently no "compelling justification" (the test set in the Structure Plan Policy H4) to justify the release of any reserve provision. However, if there are further delays in bringing forward some of the large sites and MDAs, or if completions are not as high as predicted, next year's Paper may reach a different conclusion.
6.4 For these reasons local planning authorities should continue to identify the full reserve provision in their local plans, as required by the Structure Plan.
6.5 The Government is looking for the high level of housing completions achieved in 2003/04 to be sustained. Most planning authorities in Hampshire are rising to the challenge - the number of planning permissions granted continues to rise; progress is being made on local plan production and urban capacity studies have been produced for the whole of the county and are now being updated. Some planning authorities are now actively managing their land supply to increase the rate of development.
6.6 One area where progress is mixed is the implementation of the MDAs. Planning applications have been received for Andover MDA but progress at west of Waterlooville MDA has slowed and the expected planning application has not yet been received. The recommendations by the Eastleigh Local Plan inspector on the South East of Eastleigh MDA are expected shortly.
6.7 Local planning authorities should be urged to continue to take proactive steps to manage housing land supply to meet their Structure Plan baseline housing requirement and allow for the reserve provision, where required.
6.8 Local planning authorities should take action to ensure that the predicted housing supply comes forward by:
(i) monitoring urban capacity sites on an annual basis;
(ii) continuing to undertake the actions in the Hampshire Housing Supply Action Plan;
(iii) discussing with GOSE the need to fast track some of the baseline sites; and
(iv) providing planning departments with sufficient resources to bring forward the housing supply as soon as possible.
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
Consultee responses on Policy H4 Monitoring Report 2005 |
File D3/1.39(ii), Spatial Strategy Group |
178/SC
APPENDIX
POLICY H4 MONITORING PAPER 2005
Summary of main points arising from consultation
List of respondents
1. Gosport Borough Council
2. Rowlands Castle Parish Castle
3. English Nature
4. Woolf Bond Planning
5. Campaign to Protect Rural England
6. The Fareham Society
7. M E Moore - Barton Farm Local Plan Support Group
8. House Builders Federation
9. Barton Willmore Planning
10. RPS Group plc on behalf of the Abbotswood Consortium
11. East Hampshire District Council
12. City of Winchester Trust
13. Southampton and Fareham Chamber of Commerce and Industry
14. RPS Bristol on behalf of CALA Homes (South)
15. Adams Hendry on behalf of Heron Land Developments and Bovis Homes
16. Bishops Waltham Society
17. Tanner & Tilley on behalf of Pennyfarthing Homes Limited
18. Terence O'Rourke on behalf of North Hedge End Consortium
19. Save Barton Farm Group
20. Berkeley Community Villages
21. Hampshire Greenfield Alliance
22. Winchester City Council
23. Government Office for the South East
24. New Forest District Council
Completions Section
Respondent reference |
Nature of comment |
Response by Strategic Planning Authorities |
4,8,9,14,21 |
The Strategic Planning Authorities failure to acknowledge or take into account the performance during the first 5 years of the plan period creates an inaccurate picture of housing supply within the county. |
The RPG issued in 2001 supersedes the RPG issued in 1994. GOSE has confirmed that there is no requirement to make up any shortfall prior to 2001. |
4,8,10,13 |
Paper fails to address the backlog arising at the beginning of the Structure Plan period. |
See above. |
8,9,20 |
With the exception of the odd year, including 2003/04, Hampshire has consistently failed to perform in the delivery of housing completions. Concern that last year was a one-off and rates will not sustained. |
The number of completions in Hampshire has increased steadily each year since 2001/02. The high level of completions in 2003/04 was part of this trend. An increased number of planning permissions supports the view that completions will continue in excess of the annual RPG requirement. |
4,14 |
Paper fails fundamentally to accurately monitor housing completions in the County by not providing annual forecasts for each district. |
The decision was taken to focus this year's paper on the information needed to determine whether there is a need to release any of the reserve provision. This information is available in other published documents. |
23 |
Welcome significant improvement in completions on previous years and also an increase in planning permissions. |
Noted. |
20 |
Undersupply has worsened 2001-2004 despite the policy H4 monitoring paper. |
It is recognised that completions 2001-2004 were only 95% of the RPG requirement. However completions in 2003/04 were above the annual RPG requirement and this situation is forecast to continue over the next few years. |
10 |
Paper omits a review of completions to date (in last years paper) and a sub-area breakdown which allowed various trends to be identified and highlighted the underperformance of North Hampshire. |
The decision was taken to focus this year's paper on the information needed to determine whether there is a need to release any of the reserve provision. This information is available in other published documents. |
1 |
A bar chart showing how each authority's completions related to their annual requirements has been useful in previous papers. |
Noted. |
21 |
Figures should include the reduction in empty homes since 1996, believed to be in excess of 3,000 homes county-wide. |
The number of empty homes is not included as it will not influence the decision on whether to release the reserve provision. However information is included in the Structure Plan Monitoring Report 2004. |
Estimates of Housing Supply
Respondent reference |
Nature of comment |
Response by Strategic Planning Authorities |
4,8,14,20 |
Need to deliver baseline and reserve 1996-2011. The only way a surplus can be demonstrated is by focussing on RPG requirements and ignoring the Structure Plan requirement. |
Hampshire is required by Regional Planning Guidance to complete an average of 6,030 dwellings per annum. GOSE has confirmed that there is no requirement to make up any shortfall prior to 2001. |
8,20 |
In the future, rates will have to be substantially higher than achieved in the past and will have to be sustained over 7 years; this is unlikely and will not be achieved unless there is a release of reserve sites. The sooner action is taken to address this the more likely future under-delivery problems will be avoided. |
The Strategic Planning Authorities consider that the forecast level of housing completions is achievable. The Policy H4 Monitoring Paper shows that even with substantial discounting there is still sufficient supply to enable the RPG target to be satisfied up to 2011. |
4,8 |
Even if all the constituent authorities in Hampshire were to meet their baseline requirements, there would still be a significant shortfall in housing provision in Hampshire compared to the RPG requirement. |
The target is to meet the RPG figure. If as a minimum, all authorities built their annualised baseline requirement, the additional completions in some areas over and above that would ensure that the county as a whole exceeded the RPG figure. |
13 |
There is every reason to believe that the future rates required will need to be higher than current experience. There seems to be no harm in enabling individual districts to meet their own targets even if this results in a short term over-run on current targets. |
The target at the present time is to meet the RPG figure. Ever district must at least provide for its Structure Plan baseline figure. |
15 |
Figures for housing supply to 2011 have not been produced on a comparable basis to 2004 paper which did not include the West of Waterlooville and Andover MDAs. |
Agree that the MDAs have been included in the figures for identified sites this year. Comparable figures are available on request from the report author. |
14 |
Table 3 should differentiate between `Local Plan Allocations' and `Other Commitments'. |
This table provides a general summary of identified housing supply. |
Discounting and Sensitivity Testing
Respondent reference |
Nature of comment |
Response by Strategic Planning Authorities |
2,8,9,14 |
Support discounting and sensitivity testing and in general the adoption of a fairly cautious approach. |
Welcomed |
10,15,16,19 |
Discount rates appear arbitrary with no credible justification provided and it is impossible to properly consider these rates. |
The discount rates to be applied were subject to consultation before analysis was begun on the monitoring paper. The lowest discount (5%) was applied to the category most likely to be built - large sites with detailed planning permission. A higher discount (10%) was applied to housing on large sites where only outline planning permission had been granted as it was considered that the likelihood of these being completed by 2011 was slightly less certain. The highest discount (20%) was applied to Major Development Areas as it was considered that the greatest risk of the supply not being built by 2011 was on these sites. The Housebuilders Federation agreed that this level of discount was appropriate for the MDAs. The risk of the remaining supply not being completed by 2011 was considered to be less than in the MDAs but greater than sites with planning permission and therefore a discount of 15% was applied to this source of supply. |
8,14 |
Unadjusted supply figures for MDAs, large identified sites and urban capacity/windfall sites are unrealistically high, especially when compared to past completions. The way the requirement has been calculated has skewed the figures. |
It is acknowledged that some of the unadjusted supply figures are optimistic. For this reason the supply was reduced by over 1,000 dwellings before the discounts were applied |
23 |
There remains a risk over unidentified large sites. |
The adjusted supply figure for 2004-2011 appears reasonable when compared with past completions on this type of site (see Table 6 of Monitoring Paper) |
4,5 |
The surplus identified (Table 7) will not necessarily equate to a similar completions figure due to difficulties bringing forward certain identified sites. |
Discounting was applied to reflect that not all of the available supply will be developed by 2011. |
14 |
Sites that continue to be relied upon as identified components in successive monitoring reports repeatedly fail to deliver completions for example Popley Fields and Binfields in Basingstoke. |
Some sites have not come forward as quickly as we would like, for a variety of reasons, however it is still expected that they will make a contribution to housing supply before 2011. |
10 |
Discounting should only be applied to identified land - windfalls are only estimates and so should not be further discounted. |
The adjustments made to urban capacity and windfall sites reflect the uncertainty about when building will commence and the rates achievable and therefore the delivery of housing by 2011. |
10 |
Sites are identified if a red line can be drawn around it on an OS base, planning status and availability are separate matters. |
It is considered important that `identified sites' have some planning status such as planning permission or allocation in a local plan. It is recognised that the location of much of the `unidentified housing supply' is known to the local authorities. |
21 |
The County Council should not be making pessimistic but realistic forecasts. Hampshire should be working towards achieving targets and not exceeding them. |
Views noted. |
Urban Capacity
Respondent reference |
Nature of comment |
Response by Strategic Planning Authorities |
9,16,20 |
The ability of local authorities to deliver continued rates of brownfield sites is questioned. There has been a hardening of attitudes in Local Authorities in the light of opposition from local residents against development on brownfield sites. |
The paper could find no evidence of a slowdown in this source of supply at present. On the contrary, it highlights a significant increase in the number of dwellings built on large brownfield windfall sites in 2003-04. |
8 |
There is no way of assessing the research into urban capacity as this has not yet been made public. |
This is correct. Each urban capacity study has or will be scrutinised in the public arena of a Local Plan Inquiry. |
14 |
The paper assumes a major contribution from unidentified supply without strong justification. It lacks basic or raw data, particularly important given the apparent inconsistency with the districts urban capacity studies. |
The paper highlights the increasing proportion of completions on windfall sites since 2001. In addition, an audit of urban capacity studies was undertaken in order to establish whether the estimates for each district were realistic. |
10 |
Planning applications have been submitted on some urban capacity sites and therefore the report should not describe these as `unidentified'. |
These sites become `identified' when there is a resolution by the local authority to grant planning permission. |
5,21 |
Question decision to only make allowances for districts where urban capacity has been over-estimated, not the remaining 10 districts where it was underestimated. |
The purpose of the adjustments made to housing supply was to ensure that the supply was not over estimated. The monitoring report deliberately errs on the side of caution. However, it would have been difficult to make an allowance for the underestimation of supply from this source as the audit of urban capacity studies did not quantify any underestimation in urban capacity . |
Major Development Areas
Respondent reference |
Nature of comment |
Response by Strategic Planning Authorities |
9,14,20 |
It cannot be relied on that applications for MDAs will be submitted and resolved in time for the housing to be completed prior to 2011. |
It is recognised that there is some uncertainty about the commencement of development and the building rates achievable in the MDAs. In recognition of this a discount of 20% has been applied. Local authorities and developers are working to implement the MDAs and it is reasonable to expect a significant number of completions before 2011. |
14,16 |
It is essential to provide figures for separate MDAs instead of a combined figure. Further data is required to justify the adopted supply rates. |
All the discounts to the dwellings supply are applied on a county-wide basis. |
14,20 |
West of Waterlooville MDA completion figures are from 2005-06 but no application has been submitted as yet. The release of the reserve will not provide any housing completions by 2011. |
The Housing Land Supply monitoring information 2004 shows a small number of dwellings to be delivered by 2005/06. When making adjustments to the supply, the estimated supply from this source was reduced by 300 dwellings (from 1600 dwellings to 1300 dwellings) before the discount was applied. This recognised that the level of completions in the early years was optimistic. |
8 |
A discounting of MDAs by 20% may be overoptimistic. |
The discount applied reflected the testing undertaken on very large sites. |
Overall Supply and Policy Requirements
Respondent reference |
Nature of comment |
Response by Strategic Planning Authorities |
13,14 |
Consideration of housing supply for the county as a whole does not absolve each district from the requirement to meet its baseline supply figure. |
Agreed. |
9 |
Hampshire Action Plan action PA10 requires the County to identify where H4 releases could be made when the adjusted supply is within 5% - this assessment has not been undertaken. |
The adjusted supply exceeds RPG + 5% by almost 3,000 and therefore no assessment is required. |
9 |
Adjusted housing supply does not provide a sufficient margin to ensure that the Structure Plan and Regional Planning Guidance requirements will be met by 2011. |
The adjusted figure for total available supply to 2011 exceeds the RPG requirement by 5,000 dwellings. |
16 |
Tables 8 and 6 are inconsistent. |
Disagree, the tables have been misunderstood. |
16 |
A small downwards adjustment to supply 2004-07 is required in Table 8 as the figure stated is more than the outstanding permissions at April 2004. |
Disagree. The adjusted estimate of dwelling completions for 2004-2007 is 19,744. The total number of outstanding planning permissions (including those subject to section 106 agreements) at 1 April 2004 was 26,674. The estimated supply 2004/07 (controlled by the number of planning permissions for each district) is 20,397. As this figure is higher than the adjusted estimate, no further adjustment is necessary. |
Overall Conclusions
Respondent reference |
Nature of comment |
Response by Strategic Planning Authorities |
6,11,12,19, 22,24 |
Support overall conclusions. |
Noted. |
5,8,13,15,1821 |
A more detailed breakdown of the information, including the situation in individual districts and 3 sub-areas is required. |
This year's paper is shorter than previous years and focuses on the information needed to determine whether there is a need to release any of the reserve provision. Further information is available on request. |
4,10,15,16 |
Report does not convincingly demonstrate that sufficient completed dwellings will be produced by 2011. There are issues of deliverability and the conclusions reached cannot be justified. |
The conclusions are based on the information available and assumptions set out in the Monitoring Paper. These include steady increases in both planning consents and housing completions since 2001. |
4,10,13,19 |
Paper should go further in its conclusions. |
It is not considered necessary to do this as the Monitoring Paper concludes there is no need to release any reserve this year. |
8,10,16 |
There is insufficient information available in the report to allow proper consideration of the issue and in order to determine whether the conclusions are correct. |
This year's paper is shorter than previous years and focuses on the information needed to determine whether there is a need to release any of the reserve provision. |
23 |
It is not possible for the Secretary of State to agree with the conclusions reached in this paper until the progress report on the Action Plan has been received and considered. |
Progress report has been sent to GOSE and their comments are awaited. |
18 |
Find it deplorable that the County Council can conclude that the housing situation is healthy when Eastleigh BC can run contrary to Structure Plan policy in failing to identify reserve provision. |
The Inspector's report on the Eastleigh Borough Local Plan is due to be published shortly and will consider these points. Eastleigh Borough Council is required to meet its baseline provision in full and to identify its reserve provision. The SPG makes clear that non-identification of the reserve will not be a barrier to its release if/when that is justified. |
Other Matters Raised
Respondent reference |
Nature of comment |
Response by Strategic Planning Authorities |
1,2,6,12,19 |
Report is well presented, easy to read and understand and provides an in-depth analysis. |
Noted. |
10,16 |
Report suffers from a lack of detail, transparency and objectivity with some statements confusing and not properly justified. It has too narrow a focus on the Structure Plan housing requirements and falls short of the high standard of monitoring required. |
This year's paper is shorter than previous years and chose to focus on the information needed to determine whether there is a need to release any of the reserve provision. The Forward to the Paper makes clear that it is not a general monitoring paper and that there are other monitoring reports available. |
16 |
Report does not follow the H4 SPG requirement that a comparison be made between Structure Plan and Regional Planning Guidance in each district and Hampshire as a whole. |
The SPG only requires a county-wide assessment, unless it is concluded that some of the reserve should be released. Information about completions and housing supply by district is included in the appendices. |
10,12,13,15 |
Housing supply should be placed in the context of the options emerging in the South East plan. There is potential for confusion with local plans and Regional Spatial Strategy being approved concurrently with different targets. |
At the time of the completion of this paper, final options for housing supply were not confirmed. In any event, they are not relevant to decisions on whether to release the Structure Plan's reserve provision and would only confuse the picture. |
1,10,20 |
Reference should be made to the Action Plans. Comments on the ability of the Action Plans to deliver sufficient housing. |
A progress report on the action plan is the subject of a separate report to JAP. |
14,17 |
There is a strong case for releasing the Winchester City (North) MDA and bringing forward sites in the New Forest. |
Structure Plan Policy H4 states that the reserve will only be released when there is a `compelling justification to do so'. Based on the available information and assumptions set out in the Paper, there is no compelling justification at the present time to release any of the reserve. |
9 |
Releases should be targeted where sites are readily identified in LPs either under H4 or not and are directly and readily able to contribute to housing supply. |
Revised SPG on Implementing Policy H4 2004 provides details on determining in which district(s)/MDA(s) to make the release. |
3,6,21 |
The paper ignores affordable housing and the potential to increase the percentage on new sites instead of releasing the reserve. The real issue is how to meet the housing needs of the people of Hampshire. |
The paper does not present data on affordable housing because the SPG states that affordable housing need will not influence decisions on the release of the reserve provision. Such information is included in the Structure Plan Monitoring Report 2004. |
2,12 |
Concerns about the provision of infrastructure should be included within the policies for reserve housing sites. |
This is an important issue but is outside the remit of this report which compares the supply of land for future housebuilding with the requirements of RPG to assess the need to release reserve housing provision. |
7 |
Paper makes no reference to flood risk which should affect the release of the Winchester City (North) MDA. |
This is outside the scope of the Monitoring Paper. |
18 |
Monitoring paper places pressure on those authorities that accept their legal requirement to provide housing whilst facilitating an avoidance of this responsibility in others. |
Disagree. All local authorities are expected to meet their Structure Plan baseline housing requirement. |
12 |
Concern about the time lag between the date when monitoring was completed and when JAP will consider it. |
The time lag is considered reasonable. A considerable amount of staff time is required to collect information on completions and housing supply for 13 districts, collate, check and analyse it, write the report, allow sufficient time for consultation, analyse the results of the consultation and write a report for JAP. |
23 |
It would be helpful if the assumptions underlining Appendix 5 were made available as seem figures appear optimistic. |
Noted. |
19,21 |
Question the requirement for reserve provision on large Greenfield sites to be retained in sub-regional and district planning in view of the papers findings. |
It is necessary to retain the reserve provision as a safeguard in order to meet the RPG housing requirement. |
12 |
More emphasis could be given to the evidence that any lag in completions would not be attributable to the planning authorities in Hampshire. |
Noted. |


