15 March 2005

Capital Minor Works Programmes 2004/05 and 2005/06

Report of the Director of Environment

Item 7

Contact: Peter Barty, tel: 01329 824364 [email protected]

1. Summary

1.1 This report outlines:

      (i) progress with the 2004/05 Capital Minor Works Programme; and

    (ii) details of the 2005/06 Capital Minor Works Programme.

2. Capital Minor Works Programme 2004/05

2.1 As previously reported, the Minor Works Programme (also known as the Under £10,000 Programme) is funded from the capital allocation based on the Local Transport Plan submission to the Department for Transport. In the 2004/05 programme, £250,000 was allocated county-wide, of which £19,000 was allocated for Fareham. The schemes included in the programme were:

    (i) A27 West Street, Portchester £9,000

      Widening footway adjacent to Portchester Park

      (ii) Bridge Street, Titchfield £10,000

      Provision of footway between canal and river

      Total £19,000

2.2 The works in Portchester have been completed. Consultations for the footway in Bridge Street are ongoing due to its sensitive environmental location. It is anticipated works will start this financial year. A further phase of works to widen the existing footpath up to and including the canal bridge would be desirable and is included in the programme on Phase 2.

3. Capital Minor Works Programme 2005/06

3.1 The funding allocation for the 2005/06 programme county-wide is expected to be £200,000 of which Fareham, Havant and Gosport have a total allocation of £50,000. It is anticipated that this will enable one or two schemes to be implemented within Fareham during this financial year.

3.2 The attached appendix details the current schemes within the Capital Minor Works Programme. Each scheme has been subject to a set of ranking criteria based on its benefits. Highest rates schemes are:

      Bridge Street, Titchfield (Phase 2) £10,000

    Footpath widening

              Downend Road, Fareham (Phase 2)

              Provision of footway £10,000

Recommendation

That Members indicate their preference for minor works schemes in 2005/06 and the Executive Member for Environment be advised accordingly.

Section 100 D - Local Government Act 1972 - background papers

 

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

 

NB the list excludes:

 

1.

Published works.

 

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None.

 

9204/PB

APPENDIX

Area/

Scheme

Budget £'000

White Paper Objectives

Strategy Area Aim/Targets

Scheme Hierarchy

Implementation

Comments

Agent

Type of works

Is it improving

Is it helping

Level(s) of Importance

Is it

 

Fareham

 

Integration of Public Trans

Economy

Accessibility

Safety

Environment

Total 1

Public Transport Operators

Cyclists

Manage Demand

Pedestrians

Mobility Impaired

Total 2

Strategic

County

Area Strategy

Local Plan

Total 3

of Added Value

Deliverable in Financial Year

Total 4

Total 1-2-3-4

 

 

                                         

 

Bridge Street Titchfield

10

 

 

X

X

 

2

 

 

 

X

X

2

 

 

 

 

0

 

X

1

5

Cllr Mrs Hockley

 

 

Phase 2, widen footpath

                                     

 

Downend Road

10

 

 

X

X

 

2

 

 

 

X

X

2

 

 

 

 

0

 

X

1

5

Cllr Murray

 

 

Provision of new rural footway from fitness club to motorway (stage 2)

 

 

 

 

 

 

 

 

Footpath number 23 - Palomino Drive

8

 

 

X

 

 

1

 

 

 

X

X

2

 

 

 

 

0

 

X

1

4

 

 

 

Improve footpath levels and provide drainage, edging and two-course surfacing

 

 

 

 

 

 

 

Old Street

9

 

 

X

X

 

2

 

 

 

X

X

2

 

 

 

 

0

 

 

0

4

 

 

New footway to Cuckoo Lane. (Land required)

                                         

 

Titchfield Road Stubbington

10

 

 

X

X

 

2

 

 

 

X

X

2

 

 

 

 

0

 

 

0

4

 

 

New footway between Anzac Close and St Marys Road. (Land required. Await result of new toucan) 

 

 

 

 

 

 

 

 

 

 

Botley Road Park Gate

10

 

 

 

X

 

1

 

 

 

X

 

1

 

 

 

 

0

 

X

1

3

 

 

 

Reallocate lay-by as pedestrian area

                                       

 

                                             

 

 

 

                                         
 

Total required budget £k

57