Archived decisions

Appendix 2

           

APPENDIX 2

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

0

2004/05 PROGRAMME AND AMENDMENT SCHEDULE

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                 

1

 

FORMAL APPROVED VALUE

 

LATEST COST

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

1

 

Date Change Identified

ESTIMATE AS APPENDIX 1

COMMENTS

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

1

 

CAPITAL

EXTERNAL

 

CAPITAL

EXTERNAL

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

1

 

Reported 21 January 2004 (Exec Member Environment)

 

March 2005

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                             
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Central Hampshire Transport Strategy

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Longslade Cycle/Foot Bridges

20,000

 

Feb-2005

30,000

 

Design of both bridges improved following consultation with NF Verderers and equestrian society to ensure two horses can cross in opposite directions, and metal will be clad in wood to stay in keeping with surrounding area.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

North Hampshire Transport Strategy

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

NHTS Village Initiatives

130,000

 

Feb-2005

25,000

 

Start value reduced because of schemes being withdrawn:Cricket Hill, added to programme late, but now unlikely to start until 2005/06 - therefore is no longer part of this programme.Odiham (TM in Dunley's Hill) - On hold pending the results of the EF

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Solent Transport Strategy

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Eastleigh Bus Quality Partnership. (Access to Station)

 

50,000

Feb-2005

 

70,000

Initial cost estimates had no allowances for supplementary items or design fees. Additional contributions are available to cover increases.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

West Lane, Hayling Island

7,000

13,000

Feb-2005

13,000

13,000

Historic costs not originally included in forecast.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Havant Bus Station

1,520,000

80,000

Feb-2005

1,850,000

80,000

Additional inflation of 2.5% as a result of delaying start of main contract (approx £100k). Additional fees for HBC approx £40k. Clarification of requirements during detailed design stage resulting in various increases in estimates. Some unknown elements

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Newgate Lane/Tukes Avenue, Fareham - Cycles

 

104,000

Feb-2005

 

121,000

Additional street lighting costs £6k, plus possible costs for improvements to signs and barriers.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Casualty Reduction Programme

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

A339 Ramsdell Junction (High Cost)

120,000

 

Feb-2005

150,000

 

Additional works costs identified as a result of unexpected cable found during construction. Slight design fee increase too. No significant effect on programme.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Other Safety Projects (04/05)

200,000

 

Feb-2005

0

 

Starts value transferred to the Refurb & Betterment budget heading.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Loss of Control Priority Sites

900,000

 

Mar-2005

1,010,000

 

Additional poor surface sites identified in January.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Casualty Reduction Partnership

250,000

 

Mar-2005

350,000

 

Investigation of new sites following 9 Fatal RTA's in January.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Low Cost Safety Programme

1,200,000

 

Mar-2005

1,300,000

 

Additional sites added to programme in January.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Refurbishment and Betterment 2004/05

150,000

40,000

Mar-2005

370,000

40,000

Starts value from "other safety schemes" transferred into this heading. No overall change to the capital programme.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Other Integrated Transport

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Hill Road / Station Road Railway Bridge, Portchester - Traffic Signals

100,000

 

Feb-2005

60,000

 

Detailed Design estimates including contingencies are lower than original allocation.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Greatbridge Road Rail overbridge - Safety Scheme

100,000

 

Feb-2005

130,000

 

£100,000 was an early indication. After detailed design by ITS/Eng, it is expected to cost £130,000 (including contingencies)

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Recreational Cycling (04/05)

140,000

 

Feb-2005

100,000

 

Although previously increased to £140k to cover scheme slipping from 03/04 programme, original budget of £100 is now considered to be adequate to complete all schemes. Therefore the value of this sub-programme is returned to £100k

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Appendix 3

             

APPENDIX 3

SCHEMES MOVED FROM 2004/05 SINCE PREVIOUS REPORT.

   
                 

B3272 Corridor - Yateley - Eversley Traffic Management

     
                 

£200,000

LTP

LTP contribution to ROUA Scheme. Programme

   
   

significantly delayed, partly due to nature of project

   

Moved to

 

but also due to resourcing difficulties for specialists during 2004.

2005/06

 

Start on Site September 2005.

       
                 

Bordon /Whitehill - A325 Cycleway Extension

       
                 

£13,000

EF

Scheme identified as costing in the region of £150,000.

 
   

Full funding from development sources unavailable at

 

Moved to

 

present. Scheme therefore deferred from the programme

 

Prep.Pool

 

for the timebeing.

         
                 

Fareham Western Distributor Road (Schooner Way to Warsash Road)

   
                 

£1,025,000

LTP

Japanese knotweed problem identified on line of proposed site.

£375,000

EF

3-year programme of removal prior to works.

   
   

Scheme should therefore be removed from the delivery

 

Moved to

 

programme at this time.

       

Prep.Pool

               
                 

Hedge End Rail Station Improvements

         
                 

£60,000

EF

Contract was to be let with Maunsell Way works in order to

 
   

achieve economies. Estimate increases to this scheme

 

Moved to

 

would increase whole contract above schedule of Rates limit.

 

Prep. Pool

 

Scheme now under review.

       
                 

Knowle Hospital - Knowle Village to Funtley Footways

     
                 

£40,000

EF

Works delayed by ongoing land negotiations. Works now

 
   

expected during the summer - subject to successful negotiation.

Moved to

               

2005/06

               
                 

New Forest Bus Infrastructure Improvements

       
                 

£100,000

LTP

Bus operator yet to agree services for improvement.

   
   

Scheme now slipped to 5/6.

       

Moved to

               

2005/06

               
                 

NHTS Bus Infrastructure & Improvements - Farnborough Route 6

   
                 

£100,000

LTP

Orders for shelters, RTI and bus stops made, but highway works

   

unlikely to start on site prior to end of March. Therefore this

 

Moved to

 

scheme is to be slipped into 5/6.

     

2005/06

               
                 

Southampton Road, Dibden - Cycle Refuge

       
                 

£20,000

LTP

Scheme under review due to technical and safety reasons as to

   

why it can not progress. HCC cycling officer to determine way

 

Moved to

 

forward.

           

Prep. Pool

               

Appendix 5

           

APPENDIX 5

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

1

2005/06 PROGRAMME AND AMENDMENT SCHEDULE

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                 

1

 

FORMAL APPROVED VALUE

 

LATEST COST

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

1

 

Date Change Identified

ESTIMATE AS APPENDIX 4

COMMENTS

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

0

 

CAPITAL

EXTERNAL

 

CAPITAL

EXTERNAL

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

0

 

Reported 21 January 2004 (Exec Member Environment)

 

March 2005

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                             
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Central Hampshire Transport Strategy

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Pulens Lane to Tor Way Cycles, Petersfield

   

Feb-2005

 

130,000

EF received Jan 05, so scheme possible for 05/06 implementation.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Salters Lane (Harestock Corner) Junction Improvement, Winchester

   

Feb-2005

 

140,000

New to programme. All EF funding now in place.Consultation underway now.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Charles Street/Lavant Street, (Station to Town Centre) Petersfield

   

Feb-2005

 

70,000

Confimation of develooper contributions. Scheme now included in 5/6 programme

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

New Forest Transport Strategy

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

New Forest Bus Infrastructure Improvements

   

Feb-2005

100,000

 

Bus operator has yet to agree services for improvement. Scheme now slipped to 05/06.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

North Hampshire Transport Strategy

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Victory Roundabout Subway Improvements, Phase II

   

Feb-2005

 

45,000

New to programme. Part two of works at Subway that are weather dependent, or that have slipped from original subway scheme.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

NHTS Bus Infrastructure & Improvements -Farnborough Route 6

   

Feb-2005

100,000

 

Orders for shelters, RTI and bus stops made, but highway works unlikely to start on site prior to end of March. Therefore this scheme is slipped into the 5/6 programme.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

New Street Bus Lane Contraflow

 

200,000

Mar-2005

 

0

Scheme now deferred as not supported by BDBC.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

B3272 Corridor - Yateley - Eversley Traffic Management

   

Feb-2005

200,000

 

LTP contribution to ROUA scheme. Programme significantly delayed, partly due to nature of project, but also resourcing problems during 4/5. Now starting September 05.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Solent Transport Strategy

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         

Hayling Billy Route, Havant Railway Station Cycleway - Phase 2

   

Feb-2005

250,000

24,000

£24k, not £30k contribution from HBC cycle capital budget. Scheme slipped to 5/6 as contract not starting until April 05 earliest.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Fareham Western Distributor Road (Schooner Way to Warsash Road)

   

Feb-2005

1,025,000

375,000

Advanced works to commense with removal of Japanese Knotweed delayed from 04/05.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Knowle Hospital - Knowle Village to Funtley Footways

   

Feb-2005

 

40,000

Works delayed from 04/05 by ongoing land negotiations. Starting in summer 05 subject to successful outcomes.

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

Appendix 4

Capital Programme for 2005/06

 

APPENDIX 4

       

Central Hampshire Transport Strategy

BCA

EF

 

Fletchers Field, Liphook - Cycles

 

£55,000

 

Charles Street/Lavant Street, (Station to Town Centre) Petersfield

 

£70,000

 

Sparkford Road, Traffic Management - Winchester

£40,000

£5,000

 

Winchester RTI Replacement

£350,000

   

Andover - Salisbury BQP 2005/06

£100,000

   

Pulens Lane to Tor Way Cycles, Petersfield

 

£130,000

 

Access to East Hampshire AONB (05/06)

£20,000

   

A31 Jct Lymington Bottom, Four Marks - Junction Alteration

£100,000

£10,000

 

Andover Station - Town Centre Cycleway

£340,000

£10,000

 

A343 Newbury Road, Andover (Enham Arch)

 

£350,000

 

Alton Traffic Management

£250,000

£13,000

 

Eastern Avenue, Andover

£150,000

£50,000

 

Salters Lane (Harestock Corner) Junction Improvement, Winchester

 

£140,000

 
 

£1,350,000

£833,000

 

New Forest Transport Strategy

     

A337 Pennington Cross Roundabout - Belmore Road

£125,000

   

New Forest Cycle Plan

£40,000

   

Ringwood Peds and Cycles - 05/06

£50,000

   

New Forest Bus Infrastructure Improvements

£100,000

   

NFTS Decriminalised Parking

£120,000

   

New Forest Demand Management / Car Free Tourism

£10,000

   

Lyndhurst to Ashurst Cycles

£490,000

   

Rookes Lane and Ridgeway Lane - Traffic Management

£155,000

   
 

£1,090,000

£0

 

North Hampshire Transport Strategy

     

NHTS Village Initiatives (05/06)

£60,000

   

NHTS Bus Infrastructure & Improvements-Farnborough Route 6

£100,000

   

North Popley to Town Centre Peds/Cycle Routes, Basingstoke

£100,000

£320,000

 

Old Trunk Road, Farnborough

£14,000

£50,000

 

Victory Roundabout Subway Improvements, Phase II

 

£45,000

 

A30 Brighton Hill Roundabout - Signals

 

£1,500,000

 

Gabriel Park Leisure Centre Cycle Route

 

£220,000

 

Summit Avenue, Farnborough - Toucan Crossing

 

£100,000

 

Basingstoke Route 3 - Quality Bus Partnership (Popley - South Ham)

£200,000

   

Farnborough District Cycle Parking

 

£24,000

 

NHTS Bus Infrastructure & Improvements (Yateley Route 3)

£200,000

   

NHTS Bus Infrastructure & Improvements-Farnborough Route 6 Stage 2

£150,000

   

B3272 Corridor - Yateley - Eversley Traffic Management

£200,000

   

Fleet Town Centre

£400,000

£2,475,000

 
 

£1,424,000

£4,734,000

 

Solent Transport Strategy

     

Havant Route 21 - Quality Bus Partnerships 05/06

£100,000

   

Factory Road - Traffic Management, Eastleigh

£375,000

£200,000

 

Hound Road Cycleway, Netley

 

£125,000

 

Chestnut Avenue, Eastleigh - Cycles

 

£225,000

 

A27 Corridor, Fareham - Traffic Management (Pedestrian Crossings)

£260,000

£150,000

 

Hayling Billy Route, Havant Railway Station Cycleway - Phase 2

£250,000

£24,000

 

Knowle Hospital - Knowle Village to Funtley Footways

 

£40,000

 

Knowle Hospital - Fontley Road Footway

 

£100,000

 

Southampton - Winchester BQP

£350,000

   

Hamble Bus Route 16 - Capital Grant

 

£100,000

 

Yew Tree Drive, Whiteley

£250,000

£250,000

 

Gosport Urban Centre Improvements

£100,000

   

Leigh Road Corridor, Eastleigh

£200,000

£300,000

 

Hythe Pier Maintenance (05/06)

£90,000

   

Fareham Decriminalised Parking

£130,000

   

Hardley to Hythe Cycle Route

 

£145,000

 

A3090 Winchester Road/Cupernham Lane, Romsey - Traffic Signals

£200,000

£100,000

 

Rownhams/Nursling Traffic Calming

£50,000

   

Chilworth to Southampton cycles

£30,000

£120,000

 

Eastleigh Bus Quality Partnership (Derby Road - Passfield Avenue)

 

£70,000

 

A27 Botley Road Hedge End, Bus Access

£315,000

£100,000

 

Hamble Lane/Ensign Way Pedestrian Refuges

 

£25,000

 
 

£2,700,000

£2,074,000

 

Casualty Reduction Programme

     

Surface Dressing Programme 2005/06

£1,380,000

   

Tukes Avenue

£50,000

   

Water Lane, Totton - Traffic Calming

£120,000

£245,000

 

Refurbishment and Betterment 2005/06

£200,000

   

Casualty Reduction Programme (05/06)

£250,000

   

Low Cost Sites Programme - 05/06

£1,000,000

   
 

£3,000,000

£245,000

 
       

Other Integrated Transport

     

Community Safety Initiative 05/06

£60,000

   

Air Quality and Noise Monitoring (05/06)

£50,000

   

Safer Routes to School Programme - 05/06

£1,500,000

   

Minor Traffic Management

£460,000

   

Recreational Cycling (05/06)

£50,000

   

Rail Stations/Interchanges (2005/06)

£50,000

   

Community Transport Schemes 05/06

£300,000

   

Central ITS (05/06)

£200,000

   

LTP Monitoring & Initiatives (2005/06)

£150,000

   

Pedestrian Crossing Programme 2005/06

£200,000

   

Passenger Transport Information (05/06)

£160,000

   

Minor Schemes (05/06)

£200,000

   
 

£3,380,000

£0

 
       

Total Starts Value

£12,944,000

£7,886,000

 

Appendix 1

CAPITAL PROGRAMME FOR 2004/05

APPENDIX 1

     

Central Hampshire Transport Strategy

   
 

BCA

EF

Eastgate Street, Street Lighting Improvements, Winchester

£30,000

 

New Footways, The Wallops

£30,000

 

City Road, Street Lighting Improvements, Winchester

£20,000

 

CHTS Village Initiatives (04/05)

£60,000

 

Holybourne to Four Marks Cycles - Stge 3 Anstey Rd, Alton

 

£86,000

CHTS Bus Infrastructure Improvements (04/05)

£150,000

 

Winchester Road, Andover - Footways

 

£50,000

B2177 Corridor (Colden Common)

£200,000

 

Foxcotte Road /Charlton Lane / Hatherden Rd - Traffic Management

£370,000

 
 

£860,000

£136,000

New Forest Transport Strategy

   

Longslade Cycle/Foot Bridges

£30,000

 

Ringwood Peds and Cycles - 04/05

£100,000

 

Station Road, New Milton - Puffin (Not Ped Facilities Programme)

£77,000

£15,000

North Street, Traffic Management - Pennington/Lymington

£70,000

 
 

£277,000

£15,000

North Hampshire Transport Strategy

   

A327 Summit Avenue, Farnborough - Cycle/Peds

£100,000

£220,000

Yateley - Blackwater Cycles

£80,000

 

North Camp, Farnborough - Traffic Management

£120,000

 

A30 Blackwater Pedestrian Enhancements

 

£60,000

Blackwater Valley QBP - Aldershot Bus Infrastructure

£100,000

 

A325 Farnborough Gate Cycles - Final Phase

 

£50,000

A30/A340 Route 1 Bus Quality Partnership

 

£500,000

A323 Ash Road, Aldershot - Traffic Management

£250,000

 

Blackwater Valley QBP - Real Time Information.

£300,000

£170,000

A30 Blackwater CCTV

 

£30,000

A327 Elles Road, Farnborough - Street Lighting

 

£120,000

Victory Roundabout Subway Improvements

 

£100,000

NHTS Village Initiatives

£25,000

 

Highway Improvements West Aldershot

 

£200,000

Chineham Bus Infrastructure

 

£20,000

Ayling Lane Traffic Calming

 

£55,000

Lynchford Road Toucan Crossing, Farnborough

£75,000

 
 

£1,050,000

£1,525,000

Solent Transport Strategy

   

Broom Way Cycleway, Fareham

 

£424,000

Anglesea Gardens, Gosport Footway Improvements

 

£30,000

Fareham-Gosport QBP - Gosport BDIS

£105,000

 

Marchwood Pedestrian Facilities

 

£50,000

Hamble Lane/Portsmouth Road Toucan

 

£50,000

Hythe Pier (CTI Programme) - Capital Contribution

£70,000

 

Eastleigh Bus Quality Partnerships (Leigh Rd SVD)

£70,000

 

Hythe Pier Maintenance (04/05)

£90,000

 

St Margarets Lane Safety Scheme,Phase 1, Titchfield

£60,000

 

Pirelli - Eastleigh Controlled Parking Zone

 

£175,000

Clanfield Village Initiative

£27,000

 

A335 / B3037 Twyford Road Roundabout, Eastleigh

 

£96,000

Salterns Lane Junction, Fareham - Traffic Calming

 

£49,000

West Lane, Hayling Island

£13,000

£13,000

Havant Decriminalised Parking

£110,000

 

Westbury Road, Fareham - Cycles

 

£10,000

Havant Bus Station

£1,850,000

£80,000

Park Lane, Traffic Management - Fareham

£45,000

 

Kipling Road Traffic Management, Eastleigh

 

£30,000

Rumbridge Street Totton - Traffic Management

£600,000

£400,000

Falkland Road Puffin (ex Chestnut Avenue Cycles) (Part Peds Prog)

 

£75,000

Newgate Lane/Tukes Avenue, Fareham - Cycles

 

£121,000

North Baddesley to Rownhams Cycle Route

£400,000

 

Valley Park to Toynbee Cycles (Stage 2)

 

£285,000

A32 Gosport, Traffic Signal Improvements

 

£15,000

Maunsell Way Traffic Calming

 

£365,000

Abshot Road/Warsash Road (additional costs)

£20,000

 

Abshot Road/Hunts Pond Road (Additional costs)

£60,000

 

Templars Way/Castle Lane Traffic Signals, Pedestrian and Cycle Facilities

 

£100,000

Havant Route 21 - Quality Bus Partnerships (04/05)

£200,000

 

Bournemouth Road (Asda), Chandlers Ford Pedestrian Crossing

 

£80,000

Fareham - Gosport QBP 04/05 - Bus Infrastructure Improvements

£145,000

£50,000

Romsey Route 15 QBP - Bus Infrastructure Improvements

£150,000

 

Denmead Traffic Management

£160,000

£70,000

Eastleigh Quality Bus Partnerships. Bus Infrastructure Improvements

£200,000

 

Eastleigh Bus Quality Partnership. (Access to Station)

 

£70,000

Havant Accessibility

£85,000

£15,000

 

£4,460,000

£2,653,000

Casualty Reduction Programme

   

Refurbishment and Betterment 2004/05

£370,000

£40,000

Loss of Control Priority Sites

£1,010,000

 

A339 Ramsdell Junction (High Cost)

£150,000

 

Casualty Reduction Partnership (04/05)

£350,000

 

Low Cost Safety Programme - 04/05

£1,300,000

 
 

£3,180,000

£40,000

Other Integrated Transport

   

Homezones (04/05)

£100,000

 

Safer Routes to School Programme - 04/05

£1,250,000

 

Air Quality and Noise Monitoring (04/05)

£50,000

 

Pedestrian Crossing Programme 2004/05

£430,000

£138,000

MIRACLES Project, Winchester (CIVITAS) (04/05)

£100,000

 

Community Transport Schemes 04/05

£650,000

 

Passenger Transport Information (04/05)

£160,000

 

Greatbridge Road Rail overbridge - Safety Scheme

£130,000

 

Rail Stations/Interchanges

£200,000

 

Rural (Parish) Partnership Schemes 04/05

£200,000

 

Community Safety Initiative 04/05

£60,000

£25,000

Central ITS (04/05)

£200,000

 

Hill Road / Station Road Railway Bridge, Portchester - Traffic Signals

£60,000

 

LTP Monitoring & Initiatives (2004/05)

£200,000

 

Minor Schemes (04/05)

£250,000

 

Recreational Cycling (04/05)

£100,000

 
 

£4,140,000

£163,000

     

Total Starts Value

£13,967,000

£4,532,000