APPENDIX
HAMPSHIRE COUNTY STRUCTURE PLAN 1996-2011 (REVIEW)
(ADOPTED MARCH 2000)
Policy MW2
Permission will be granted for minerals and waste development provided the mineral/waste planning authority is satisfied that:
(i) any adverse environmental or other impacts that the development would be likely to cause are outweighed by a clearly established need for the development; and
(ii) the proposals, where applicable, include a satisfactory scheme of working and landscaping including details of lorry routeing and, in all cases, include satisfactory measures to ensure that the development would not have any unacceptable environmental, traffic or other impact; and
(iii) the proposals, where applicable, provide for the satisfactory and prompt restoration and after-care of the site to a high standard and to a landform compatible with the local landscape and suitable for an agreed beneficial after-use.
HAMPSHIRE, PORTSMOUTH AND SOUTHAMPTON MINERALS AND WASTE LOCAL PLAN (ADOPTED 17 DECEMBER 1998)
Policy 6
Permission will be granted for minerals and waste development provided the Mineral/Waste Planning Authority is satisfied that:
(i) there is a clearly established need for the development (as assessed in relation to the other relevant policies of the Plan) which outweighs any adverse environmental or other impact that the development would be likely to cause; and
(ii) the development would not be likely to give rise to an unacceptable level of adverse environmental, traffic or other impact, pollution risk or danger to public health, particularly in respect of any of the factors specified in Policy 7 and measures would be taken to ensure that any such impacts would, as far as is practicable, be minimised; and
(iii) the proposals provide for the satisfactory working or operation and landscaping of the site and for its satisfactory restoration and landscaping at the cessation of the operations or use or at the end of the life of the facility to a condition suitable for an agreed beneficial after-use which is compatible with adjoining land uses and the planning policies for the area.
Notwithstanding any need there may be for waste disposal, permission will not normally be granted for mineral extraction with restoration by infilling with waste materials unless there is a need for the mineral to be extracted.
Policy 7
The Mineral and Waste Planning Authorities will grant planning permission for minerals and waste development provided they are satisfied that, where appropriate, the proposed development pays due regard to:
(i) the relationship of the proposal site to other properties and land uses (particularly residential and other environmentally sensitive properties) and the likely effects of the proposed development on the locality by reason of noise, dust, smoke, fumes, illumination or any other factor and the need for buffer zones between the development and residential and other properties;
(ii) the likely volume and nature of traffic that would be generated by the proposed development and the suitability of the proposed access to the site and of the road network that would be affected, in terms of highway capacity and safety and environmental impact, and whether any highway improvements required could be carried out satisfactorily without causing unacceptable environmental impact;
(iii) the likely visual impact of the proposed development and the need for additional planting and screening, including planting in advance of the commencement of the development;
(iv) the need to safeguard the character and amenities of individual settlements and to safeguard open gaps between settlements from permanent development which would cause long-term harm to the function of the land;
(v) the likely effects of the proposed development on and the need to protect and safeguard sites of nature conservation, geological, archaeological, historic, architectural and landscape importance and their settings;
(vi) the extent and quality of agricultural land to be taken by the proposed development and the proposals for its subsequent restoration and the likely effects of the proposals on farm structure and management;
(vii) the likely effects of the proposed development on and the need to maintain the distinctive character of the landscape; the likely effects of the proposed development on and the need to safeguard and protect individual species, habitats and landscape features, including woodland, trees and hedgerows; and the likely effects of the proposed development on forestry and woodland management;
(viii) the likely effects of the proposed development on sites used for recreation and public rights of way and the need to protect or secure the satisfactory diversion of public rights of way;
(ix) the likely effects of the proposed development on and the need to safeguard the flow and quality of watercourses, water supplies, floodplains, groundwater, the drainage of the site and adjoining land and the level of the water table in the locality and the likely effects of the proposed development on the immediate setting of any river;
(x) any potential danger to aircraft from birds being attracted to the site;
(xi) the possible amenity implications of any landfill gas that might be generated at the site and of any provisions that might need to be made to deal with it; and
(xii) the likely cumulative impact of the proposed development in combination with any other significant development taking place or permitted to take place in the locality and the need to minimise the impact of mineral extraction and waste disposal operations by securing, where appropriate, the phased release of sites and progression of working and restoration.
Policy 53
The Waste Planning Authorities will permit plant, machinery, buildings and other development ancillary to waste disposal, processing and transfer facilities within the boundary of or adjacent to the facility, provided that:
(i) the development is required solely in connection with the operation, administration or servicing of the waste facility; and
(ii) any plant, machinery, building or other structure is to be designed, constructed and landscaped so as to minimise any adverse impact on the amenities of the area and, in any case, it would not be likely to give rise to any unacceptable environmental or traffic impact or other detrimental effect; and
(iii) the size, type and nature of the development are appropriate to the scale of the waste facility for which it is required; and
(iv) any plant, machinery, building or other structure would be removed as soon as the use of the waste facility has ceased and the site would be restored to a satisfactory condition suitable for an agreed beneficial after-use.
9233app/JD