1. Summary

1.1 This report outlines:

      (i) progress with the 2004/05 Highways Maintenance Programme;

        (ii) details of the 2005/06 Highway Maintenance Budget;

            (iii) details of the 2005/06 Highways Maintenance Programme; and

      (iv) progress on Minor Capital Works (Under £10,000 Schemes) for 2004/05 and proposals for the 2005/06 programme.

HIGHWAY MAINTENANCE PROGRAMMES

2. Background

2.1 Members will be aware from previous Panel meetings that the highway maintenance programme is funded from both revenue and capital allocations.

2.2 The revenue maintenance programme funds minor works such as pothole repairs; routine drainage work including gully cleaning; signs and road markings; environmental maintenance of grass verges, trees and shrubs; weed control and highway emergencies. Minor bridge works and winter maintenance are also funded from revenue. Budget allocations are set at a level that is intended to ensure the safety of the publicly maintained highway network.

2.3 The capital maintenance programme funds planned maintenance including special maintenance, resurfacing and surface dressing and also provides for essential repairs to the structure of the highway.

3. Progress with the 2004/05 Highways Maintenance Programme

      Revenue Maintenance Programme

3.1 The total revised allocation for Hampshire Highways Basingstoke for 2004/05 was £1,114,033. Progress throughout the year has generally been in line with the spend profile although during the latter part of 2004 pressures on routine maintenance has impacted on the Revenue budget. However a county-wide transfer of funding from the Capital budget to fund pressures on the Revenue budget in late January has alleviated this to some extent. At the end of January, 95% of the budget was committed and the full allocation is expected to be used by the end of the year. A budget monitoring statement is attached as Appendix 1.

      Capital Maintenance Programme

3.2 The total allocation for Hampshire Highways Basingstoke for 2004/05 was £2,389,400 which included an allocation of £483,500 of additional funding approved by the Executive Member for Environment targeted at areas of greatest need, ie minor unclassified roads and urban footways. However, county-wide £400,000 was required to help fund increased street lighting energy costs and this was funded by transferring money from the Capital maintenance programme. As a consequence the allocation for Hampshire Highways Basingstoke was reduced by £50,000 as a contribution towards the £400,000 - leaving a final allocation of £2,339,400 for 2004/05. The programme is now nearing completion and it is expected that it will be delivered as planned within time and budget constraints, with the exception of some safety fencing work. A budget monitoring statement is included within Appendix 1.

3.3 A status report detailing progress of all special maintenance, resurfacing and surface dressing is attached as Appendix 2.

4. 2005/06 Highway Maintenance Budget

4.1 This year Hampshire has received a significantly reduced Central Government grant through the Local Transport Plan process, £34.1 million compared to the £39.5 million received for 2004/05. The effect of this, plus other limitations on the budget this year, is a reduced budget for highway maintenance and hence a more limited programme of highway maintenance works county-wide.

4.2 The overall Highway Maintenance budget for 2005/06 approved by the Executive Member for Environment is £45.781 million (including the locally resourced capital budget). This comprises £22.131 million Revenue funding, £23.65 million funding from the Capital Programme provision and an additional £3.678 million of capital funding allocated by the Executive Member for highways maintenance works. The emphasis of this spending to be in the current areas of greatest need, that is minor rural road carriageways and urban footways. This means an additional £492,000 being spent in Basingstoke and Deane. The total allocations for Basingstoke and Deane are £1,037,000 for Revenue and £2,196,000 for Capital funded works.

5. 2005/06 Highway Maintenance Programme

      Revenue Maintenance Programme

5.1 As described previously, the revenue maintenance programme funds three main areas of highway maintenance:

      (i) reactive minor repair works to the road and footway network;

      (ii) minor traffic management improvements such as the renewal of signs and road markings; and

      (iii) environmental aspects of highway maintenance including grass cutting, weed treatment and tree and shrub maintenance (weedkilling has been addressed in a separate report for 2005/06).

5.2 The total allocation for Basingstoke and Deane in 2005/06 is £1,037,000. A detailed breakdown of the budget allocations for 2005/06 is set out in Appendix 3.

5.3 Additional revenue budgets are held centrally for the performance elements of the County Council's term maintenance contract. The performance based work contained in the contract includes:

        (i) gully emptying;

      (ii) potholes, road markings and studs on Principal (A) roads;

      (iii) visibility splay grass cutting;

      (iv) winter maintenance; and

      (v) ordinary bridge maintenance.

      Capital Maintenance Programme

5.4 The funding allocation for the capital maintenance programme is based on the HAMP rating system and reflects the agreed intervention levels for 2005/6. This system comprises an independent assessment of the condition of roads and footways that have been identified as potential candidates for substantial maintenance work, such as resurfacing. The HAMP rating intervention level directs funding to those maintenance schemes displaying a higher relative `maintenance need'. The provisional total allocation for Hampshire Highways Basingstoke in 2005/06 is £2,246,000. Details of the 2005/06 provisional allocations are set out in Appendix 3.

    Walworth Road

5.5 This class `C' road between Andover and Whitchurch has received more than normal wear and tear from heavy goods vehicles over the past few years. It was rated by HAMP in October 2003 and at that time did not reach the intervention level. However because the deterioration, especially at the edges of the road where HGVs over-run the metalled surface, has increased markedly in the last 18 months the HAMP rating has now risen to a level where intervention theoretically can be funded. The length of carriageway affected though is considerable (approximately 1.5 kilometres) creating a very heavy demand on the total financial allocation for Hampshire Highways Basingstoke in any single year. Consequently it is proposed that repairs will commence this year in a phased manner in order to initiate maintenance on this road but also to share the available funding with other needy locations. It is worth noting that this road is unique in that the majority of HGV traffic that it carries is travelling to and from a single business and that this route was set out by the County Council some six years ago as a preferred option for such traffic.

5.6 Planned structural maintenance repairs undertaken through the capital maintenance programme includes surface dressing, special maintenance and resurfacing schemes. A provisional list of schemes under each of these headings for 2005/06 is attached as Appendix 4.

MINOR CAPITAL WORKS PROGRAMMES

6. Introduction

6.1 This section of the report outlines:

      (i) progress with the 2004/05 Minor Capital Works Programme; and

      (ii) proposed schemes for the 2005/06 Minor Capital Works Programme and asks the Panel Members to prioritise the schemes for implementation subject to budget.

7. Background

7.1 The Minor Capital Works (MCW) Programme (formerly known as the `Under £10,000 programme') is funded from the Capital Programme allocations from the Department for Transport based on the Local Transport Plan submission. During the 2004/05 financial year, the MCW budget for Hampshire county-wide was in the region of £200,000. Although budgets have not yet been finalised for the 2005/06 financial year, it is anticipated that the budget will be set at a similar level to that of the previous year.

7.2 Members will recall that the MCW programme can only achieve a limited impact to the local infrastructure, but schemes can, and do, benefit local communities by assisting with mobility and safety on the highway.

      Progress with the 2004/05 `Under £10,000' Minor Capital Works Programme

7.3 The total allocation for Basingstoke in 2004/05 was £16,600. The schemes identified for the programme were:

      (i) Silchester Road, Pamber Heath - construction of a short length of new footway outside near Wakeford Court retirement home. Completed.

      (ii) Broad Layings, Woolton Hill - construction of a parking layby near the Post Office. Completed.

      2005/06 `Under £10,000' Minor Works Capital Programme

7.5 The `Under £10,000' MCW programme has historically been very popular with demand for schemes far exceeding the funds available. The funding allocation for Basingstoke for 2005/06 is anticipated to be in the region of £15,000 to £20,000, but is subject to final confirmation. This level of funding should allow up to two schemes to be implemented across the Hampshire Highways Basingstoke Borough during the financial year.

7.6 The attached Appendix 5 details the current MCW schemes that are on the rolling programme for Hampshire Highways Basingstoke. All schemes have been subject to a set of ranking criteria based on their benefits. The schemes have then been placed in priority order.

7.7 As in 2004/05, Members are invited to recommend their preference and priority ranking for the schemes to be contained in the 2005/06 programme. Schemes that can be implemented will be subject to the final funding allocation for Hampshire Highways Basingstoke.

Recommendations

1. That the section of this report on Highway Maintenance (paragraphs 2.1-5.6) be noted.

2. That the Panel selects two schemes from those listed in Appendix 5 for inclusion within the Minor Capital Works Programme for 2005/06.

Section 100 D - Local Government Act 1972 - background papers

 

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

 

NB the list excludes:

 

1.

Published works.

 

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None

 

230/P

E