Hampshire County Council Basingstoke and Deane Highway and Transport Advisory Panel 6 April 2005 Traffic Management Programmes Report of the Director of Environment |
Item 8 |
Contact: Richard Hague, tel 01962 857807 email: [email protected]
1. Summary
1.1 This report covers the main programmes of traffic management work in the Basingstoke and Deane area in 2004/05 and 2005/06. These are the revenue funded Traffic Regulation Orders (TROs) and signing and lining schemes for 2004/05. This programme will be completely funded from capital for the year 2005/06.
2. Background
2.1 Under the revised agency agreements for traffic management completed on 17 November 2004, Basingstoke and Deane Borough Council has continued to take direct responsibility for certain traffic management functions throughout the Borough area on behalf of the County Council.
2.2 As part of the agency arrangements, regular liaison meetings take place between officers of the County and Borough Councils to discuss proposed schemes and develop positive partnership arrangements.
3. Traffic Regulation Orders, Signing and Lining Schemes
3.1 Traffic management issues are raised in a number of ways, usually by local Borough or County Members, or the public, and occasionally by the Police or other emergency services. Schemes that have been progressed as part of the 2004/05 programme in the Basingstoke and Deane area are shown in Appendix 1. Schemes included in the list are, at this stage of the year, either operational or expected to be completed by the end of the financial year.
3.2 Schemes for the 2005/06 programme in the Basingstoke and Deane area are listed in Appendix 2. The programme is provisional at this stage, with scope to include additional schemes that may arise as a high priority. Schemes already in the programme are often subject to delay, modification or deletion as consultations progress, or where the TRO advertising procedure gives rise to objections. For the first time, the 2005/06 traffic management programme will be funded from the Capital Programme. Overall funding levels will continue to support an extensive county-wide programme of schemes with scope for top-up funding on a priority basis to individual Traffic Management Agencies over and above the annual allocation.
4. Parish Partnership Programme
4.1 Further progress has been made on those schemes already identified in the Parish Partnership Programme within the Basingstoke and Deane Borough area. Appendix 3 includes those schemes expected to be completed in 2004/05 and Appendix 2 includes those schemes programmed for 2005/06.
Recommendation
That this report be noted.
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
None |
229/RJH
APPENDIX 1
UPDATED 01.03.05
BASINGSTOKE AND DEANE HIGHWAY AND TRANSPORT ADVISORY PANEL
TRAFFIC MANAGEMENT PROGRAMME 2004/05
LOCATION |
TYPE |
PROGRAMME |
TRAFFIC REGULATION ORDERS |
||
Queen Mary Avenue and Area (II), Basingstoke |
Waiting Restrictions |
Consultation required |
Fairfields Area, Basingstoke |
Amend Residents Parking |
Review underway |
The Green, Tadley |
Prohibition of Waiting |
BDBC exec decision sought |
Kings Road, Basingstoke |
One-way and Waiting Restrictions |
Completed |
Eastrop Way Area (I), Basingstoke |
Waiting Restrictions |
Operational 26/04/04 |
Eastrop Way Area (II), Basingstoke |
Waiting Restrictions |
Operational 31/01/05 |
Leisure Park, Basingstoke |
Parking Places |
Operational 28/02/05 |
PoDs/Bus Gates, Basingstoke |
Amend Prohibition of Driving |
Scheme being progressed |
Homesteads Road Area, Basingstoke |
Prohibition of Waiting |
Operational 11/10/04 |
5-Ways Area, Basingstoke |
Prohibition of Waiting |
Deferred due to objection by BDBC Member |
Shooters Way and Doswell Close, Basingstoke |
Waiting Restrictions |
Operational 23/08/04 |
Darlington Road and Merton Road, Basingstoke |
Waiting Restrictions |
Operational date to be agreed |
Millard Close, Basingstoke |
Prohibition of Waiting |
BDBC Exec decision sought |
Joule Road and Hubbard Road, Basingstoke |
Prohibition of Waiting |
Operational date to be agreed |
Camrose Way, Basingstoke |
Prohibition of Waiting |
BDBC Exec decision sought |
Chequers Road Area, Basingstoke |
Waiting Restrictions |
Operational date to be agreed |
Upper Chestnut Drive, Basingstoke |
Waiting Restrictions |
Operational 28/02/05 |
LOCATION |
TYPE |
PROGRAMME |
TRAFFIC REGULATION ORDERS (contd) |
||
Kingsmill Road, Basingstoke |
Waiting Restrictions |
BDBC Exec decision sought |
Castle Hill School Area, Basingstoke |
Prohibition of Waiting |
Operational 28/03/05 |
Winklebury School Area, Basingstoke |
Prohibition of Waiting |
Operational 28/03/05 |
Various roads outside schools, Basingstoke |
Regularisation of School Keep Clear Markings |
Operational 11/10/04 |
Various roads, Basingstoke |
Disabled Parking Bays |
Operational |
SPEED LIMITS |
||
B3400 Worting Road, near Leisure Park, Basingstoke |
40 mph |
Operational date to be agreed |
Chequers Road area, Basingstoke |
20 mph zone |
Operational date to be agreed |
TRAFFIC MANAGEMENT AND SIGNING SCHEMES |
||
Welshmans Road/Chapel Lane, Mortimer West End |
Traffic Calming |
Consultation with West Berkshire |
A34 junction at Tufton, Whitchurch |
Layout change, sign/line improvements |
Completed, awaiting Highways Agency reply on further signs |
A34 junction at Lichfield, Whitchurch |
Layout change, sign/line improvements |
Completed |
A34 junction at Lichfield to St Mary Bourne, Whitchurch |
Lorry signing |
Completed |
Kingsclere |
Youth Club sign |
Completed |
Salters Heath |
Signing |
Completed |
Whitchurch |
Silk Mill pedestrian signing |
Completed |
Whitchurch |
Replacement ADS |
Siting locations to be finalised |
Whitney Road, Basingstoke |
Play Centre signing |
Awaiting reply from applicant |
LOCATION |
TYPE |
PROGRAMME |
TRAFFIC MANAGEMENT AND SIGNING SCHEMES (contd) |
||
North Waltham |
The Fox Public House signing |
Completed |
Sherfield-on-Loddon |
Wildmoor direction signing |
Completed |
Overton |
Cricket Club disabled signing |
Completed |
Old Basing, Basingstoke |
Hampshire Clinic direction signing |
Completed |
Ramsdell |
Lining/Signing |
Operational date to be agreed |
APPENDIX 2
UPDATED 01.03.05
BASINGSTOKE AND DEANE HIGHWAY AND TRANSPORT ADVISORY PANEL
TRAFFIC MANAGEMENT PROGRAMME 2005/06
LOCATION |
TYPE |
PROGRAMME |
TRAFFIC REGULATION ORDERS |
||
Kingsclere Road, Basingstoke |
Waiting Restrictions |
Review underway |
Highwood Ridge, Basingstoke |
Waiting Restrictions |
To be advertised |
The Cornfields, Basingstoke |
Waiting Restrictions |
Scheme to be prepared |
Hanmore Road/Renown Way, Basingstoke |
Waiting Restrictions |
To be advertised |
Pinkerton Road, Basingstoke |
Waiting Restrictions |
Scheme to be prepared |
Binfields Farm Lane, Basingstoke |
Waiting Restrictions |
Consultation underway |
Various roads, Basingstoke |
Residents Parking Permits |
Scheme to be prepared |
5 residential areas, Basingstoke |
Waiting Restrictions |
Operational date to be agreed |
Various roads, Basingstoke |
Consolidation Order |
Scheme to be prepared |
Penrith Road area, Basingstoke |
Residents Parking |
Review underway |
The Anvil/Alencon Link, Basingstoke |
Waiting/Loading Restrictions |
To be advertised |
New Street, Basingstoke |
Contra flow bus lane |
Consultations |
Swan Street, Kingsclere |
Waiting Restrictions |
Scheme being prepared |
High Street (B3400), Overton |
Disabled Parking |
Scheme to be prepared |
Various roads, Whitchurch |
Waiting Restrictions |
Scheme to be prepared |
Greywell Road, Old Basing |
Prohibition of Driving |
Consultations |
LOCATION |
TYPE |
PROGRAMME |
SPEED LIMITS |
||
Chequers Road, Basingstoke |
20 mph zone |
Consultations |
St Mary Bourne |
30 mph extensions |
Scheme to be prepared |
Sherborne St John |
30 mph extensions |
Scheme to be prepared |
Up Nately |
30 mph |
Operational date to be agreed |
Various roads, Kingsclere |
20/40 mph |
Investigations |
Chilton Candover (B3046) |
40 mph extension |
Consultations |
TRAFFIC MANAGEMENT AND SIGNING SCHEMES |
||
Gershwin Road, Basingstoke |
Signing/lining |
Scheme being developed |
Thornhill Way, Chineham |
Singing/lining |
Scheme being developed |
Hanmore Road, Chineham |
Signing/lining |
Scheme being developed |
Farleigh Road, Cliddesden |
Signing/lining |
Scheme being developed |
Church Road, North Waltham |
Signing/lining |
Scheme being developed |
Various roads, Oakley |
Signing/lining |
Scheme being developed |
Various roads, Overton |
Signing/lining |
Scheme being developed |
Brookvale, Basingstoke |
Local signing |
Scheme being prepared |
Chineham |
Direction Signing |
Scheme being designed |
BCOT, Basingstoke |
Signing |
Scheme being designed |
Various roads, Whitchurch |
Signing/lining |
Scheme being designed |
Old Basing |
Signing/lining |
Scheme being developed |
A30/Maidenthorn Lane, North Waltham |
Right Turn Provision |
To be designed |
LOCATION |
TYPE |
PROGRAMME |
PARISH PARTNERSHIPS 2005/06 |
||
Soke Road, Mortimer West End |
Traffic Calming |
Scheme to be prepared |
Stratfield Saye |
Traffic Calming |
Consultations |
APPENDIX 3
UPDATED 01.03.05
BASINGSTOKE AND DEANE HIGHWAY AND TRANSPORT ADVISORY PANEL
TRAFFIC MANAGEMENT PROGRAMME 2005/06
LOCATION |
TYPE |
PROGRAMME |
Newnham |
Narrowing at junction |
Operational date to be agreed |
Baughurst/Tadley |
Priority build-out |
Trials completed |
Little London |
Priority build-outs |
Completed May 04 |
Sherborne St John |
Traffic calming, markings and signing |
Phase 1 completed |