Hampshire County Council Executive Member Policy and Resources 14 April 2005 Major Projects Status Report Report by the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 email: [email protected]
|
|
|
|
|
|
1 |
Summary |
| |
|
| |
The following decisions are sought: |
| |
|
| |
1 That the additional funding added to the major capital projects at pre-contract stage, previously approved by the Executive Members for Education and Policy and Resources at design project appraisal stage, be approved. 2 That approval be given to the schemes being undertaken at various secondary schools under the NDS Modernisation 2005/06 Schools Specialist Accommodation Programme. |
2 |
Reason(s) |
| |
|
2.1 |
To provide enhanced science laboratory, food technology and textile laboratory accommodation at various secondary schools |
| |
|
2.2 |
This decision supports Aims 1 and 5 of the Corporate Strategy by providing improved school facilities which will benefit the school and its users and allow service delivery. |
| |
|
3 |
Other options considered and rejected |
| |
|
3.1 |
The need of the school for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost-effective way of meeting that need. |
| |
|
4 |
Conflicts of interest declared by the decision-maker or other Executive Member consulted |
| |
|
4.1 |
Not applicable |
| |
|
5 |
Dispensation granted by the Standards Committee |
| |
|
5.1 |
Not applicable |
| |
|
6 |
Reason(s) for the matter being dealt with if urgent |
| |
|
6.1 |
Not applicable |
| |
|
|
|
|
Approved by: |
.......................... |
Date of decision: |
..................... |
| |
Councillor TK Thornber |
|
|