Archived decisions

contracts to be let 0103

Regeneration of Older Urban Areas 2003/05 Programme: Outstanding project commitments

       

APPENDIX 4

 
           

District

Project

Status

ROUA 2003/05 funding

Partnership funding

Total

           

Fareham

Town Quay, Fareham

Feasibility underway. Anticipated start on site spring 2006.

£175,000

£90,000

265,000

 

Shore Road, Warsash

Start on site September 2005.

£300,000

   
           

Hart

Town Centre, Yateley

Start on site January 2006 utilising LTP/ROUA funding

£300,000

£149,000

449,000

           

Havant

Havant Railway Station

Draft proposals for improvements to upside platform prepared. Further progress pending match funding from SWT and confirmation of station redevelopment proposals.

75,000

*10000

75,000

           

New Forest

Rumbridge Street

Started. Phase One on site utilising LTP/ROUA funding. PA for Phase Two approved and due to start autumn 2005.

£300,000

£600,000

900,000

         
           
   

Outstanding commitments

£1,150,000

£839,000

£1,989,000

   

Overall ROUA 2003/05 programme financial summary

£1,985,000

£1,404,000

£3,389,000

           

* Network Rail contribution.