Archived decisions
Framework Agreement for Major Capital Projects 2004/2005 Appendix 1
WORKS |
CONTRACTOR(S) |
VALUE |
SELECTION METHOD |
REASON FOR PROCUREMENT STRATEGY |
Nursing Care Initiative Strategy | ||||
Bickerley Green |
Brazier |
4,042,995 |
Continuation with same contractors following good performance on prior phase of the Enhance project |
· Continuity of team · Continuity of supply chains · Continuous improvement through further involvement · Secure resources to complete the instructions |
Westholme |
4,265,000 · | |||
Tatchbury Mount |
HBG |
6,400,000 |
||
Emsworth House |
Balfour Beatty |
4,990,000 |
||
Education Capital |
||||
Nightingale Early Years Centre |
Brazier |
1,805,792 |
Direct appointment through Major Framework call off arrangements |
· Contractor involvement with the planning and phasing of works · Collaboration over supply chain strategy · Contractor who has successfully completed a number of similar projects for the County Council. |
Lanterns Early Years Centre |
Mowlem |
2,329,951 |
Direct appointment through Major Framework call off arrangements |
· Programming and advance works to be undertaken · Collaborate over procurement and selection of key supply chins |
East Hants (CLD) School |
6,085,000 |
Best value selection based on submissions from two framework contractors |
· Early involvement of major contractor required due to scale and complexity of project. · Programming and advance works to be undertaken · Collaborate over procurement and selection of key supply chins | |
John Hunt of Everest New Secondary School |
Wates |
22,000.00 |
Best Value selection based on submissions from four Framework Contractors |
· Major project requiring a collaborative partnership approach · Engage with contractor over planning, programming and scheme development |
Framework Agreement for Major Capital Projects 2004/2005 Appendix 1
WORKS |
CONTRACTOR(S) |
VALUE |
SELECTION METHOD |
REASON FOR PROCUREMENT STRATEGY |
Education Capital |
||||
Bridgemary Healthy Living Centre |
Brazier |
3,000,000 |
Direct Appointment through Major Framework call off arrangements |
· Similarity with NOF developments by same major contractor. · Contractor able to provide resource to support design development. · Utilise same construction and supply approach as used for the NOF sports halls · Key main contractor team who successfully undertook NOF developments · Early major contractor in involvement |
Eastleigh Crestwood Sports and Drama Development |
2,835,000 · | |||
Other major schemes |
||||
Winchester Cultural Centre |
Mansell |
5,625,000 |
Best value selection based on submissions from two framework contractors |
· Programme, planning and execution of the advance works including piling and ground clearance. · Phasing and construction strategy for complex inner city project. · Early involvement of major contractor required due to scale and complexity of project. · Collaborate over procurement and selection of key supply chains |
Harriett Costello College, Basingstoke - replacement design/technology building |
HBG |
5,000,000 |
Direct Appointment through Major Framework call off arrangements |
· Contractor successfully completed similar scheme at Wildern School. · Programme, planning and execution of the advance works including piling and ground clearance. · Phasing and construction strategy for complex inner city project. · Early involvement of major contractor required due to scale and complexity of project. · Collaborate over procurement and selection of key supply chains |