Archived decisions

Hampshire County Council

Buildings, Land and Procurement Panel Item

1 June 2005

Major Projects Status Report

Report of the Director of Property, Business and Regulatory Services

 

How the conclusion in this report fits with the Corporate Strategy

This scheme will impact on the delivery of the following Corporate Aims

Aim 1 - maximising life opportunities - by providing new and/or improved teaching accommodation to be enjoyed by the schools.

Aim 5 - improving services - by providing good quality buildings that enable service delivery.

1. Summary

1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

1.2 Appendix 3 shows those capital projects for which an allocation has been made in the Education Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.

2. Additional Works and Funding added at Pre Contract Stage

2.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

2.2 Additional funding has come from various sources including increased Education Capital Programme allocations and inflation and tolerance adjustments; additional school funding for specific additional requested works and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.

3. Current Position

3.1 Wherwell Primary School

    In the last Major Projects Report to Executive Member Education and Policy and Resources, it was reported that work had stopped at this site following the discovery of bat roosts. As a protected species, a Bat Licence is required from DEFRA in order to recommence the works. This has now been obtained and work recommenced in April 2005 with a revised target completion date of September 2005. The additional costs to the County Council due to the delay are currently being negotiated with the Contractor and when concluded, will be reported to the Executive Member Education.

Conclusion

      The details of the major capital projects outlined in this report will provide greatly enhanced school accommodation and facilities.

Recommendations

1. That the position of the major projects being undertaken by the Director of Property, Business and Regulatory Services be noted.

2. That the additional funding added to the major capital projects at pre contract stage, previously approved by the Executive Members' Education and Policy and Resources at design project appraisal stage, be approved.

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the act.

                    TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS

      Tender schedules

      Project Appraisals

MAJOR PROJECT STATUS REPORT Appendix 1

School

Current Status

Start

Complete

Funding/

* Contract Sum

£

Source of Funding

£

 

Alton Community Infant School

- three classroom, staff room and link corridor extension

On site

Dec 04

Sep 05

* 859,888

Education Capital 04/05 779,888

P&R NDS Condition 04/05 50,000

P&R Capital Repairs 04/05 30,000

859,888

 

Brookfield Community School, Sarisbury Green

- internal refurbishment

Contract Formation

May 05

Oct 05

958,261

Education Capital 04/05 375,000

Contingency 55,000

NDS Modernisation 05/06 78,261

NDS Condition fund 04/05 450,000

958,261

 

Brune Park Community School, Gosport

- Extension to provide a new dance studio and dining hall

On site

Jan 05

Oct 05

        * 1,264,484

Education Capital 04/05 1,116,484

School - Devolved Capital 80,000

P&R NDS Condition 04/05 50,000

Underspend from previous

phase of work 18,000

              1,264,484

 

Bursledon CE (C) Infant School

- three classroom and ancillary accommodation and removal of temporary buildings

On site

Mar 05

Sep 05

* 788,173

Education Capital 04/05 742,107

School 46,066

788,173

 

Calmore Infant School

- internal alterations to form an integrated yet independent Early Years Centre

On site

May 05

Sep 05

* 425,616

Education Capital 04/05 329,064

School 96,552

425,616

 

Chiltern Primary School, Basingstoke

- Worting School amalgamation

Enabling works

On site

Jul 04

Apr 05

Aug 04

Nov 05

* 123,475

        * 1,377,678

1,501,153

Education Capital 04/05 1,463,153

SAI 04/05 22,000

P&R NDS Condition 04/05 6,000

School 10,000

1,501,153

 

Cove Junior School, Farnborough

- three classroom extension, Music/Drama and kiln room

Design

Jul 05

Feb 06

743,000

Education Capital 05/06 717,000

School 18,000

P&R Capital Repairs 05/06 8,000

743,000

 

The Crescent Primary School, Eastleigh

- two classroom and library extension

Tender

Jul 05

Feb 06

802,200

Education Capital 05/06 571,000

SAI 05/06 32,700

School 53,500

HC3S 20,000

P&R NDS Condition 05/06 125,000

802,200

 

Crestwood Community School, Eastleigh

- Community Sports Hall, drama studio and Fitness Suite

Tender Negotiation

Jul 05

Apr 06

2,849,000

Estimated Capital Receipt 2,902,000

School 93,000

Capital Programme 05/06 212,000

Less financial commitments -358,000

2,849,000

 

Droxford Junior School

- demolish kitchen, convert hall to classroom and construct new hall, kitchen and playground

On site

Feb 05

Aug 05

* 673,718

Education Capital 04/05 673,718

 

East Hants Special School, Bordon

- new special school

Contract

Formation

May 05

Dec 06

6,088,683

Education Capital 05/06 212,000

TGF 05/06 4,464,000

P&R 05/06 and 06/07 500,000

P&R Capital Repairs 05/06 335,000

P&R Capital Receipt 446,000

P&R NDS Condition 04/05/06 96,000

P&R Fire Precautions 04/05/06 61,000

6,088,683

 

Eggars School, Alton

- IT block, Sports Hall and internal refurbishment

On site

Mar 05

Dec 05

* 2,508,232

Education Capital 03/04 1,020,000

NDS Modernisation 03/04 65,000

Treloar College Funding 288,000

School 271,232

Eggars Trust Fund 688,000

P&R NDS Fire Alarm 04/05 76,000

P&R Landlord contribution 70,000

P&R External Works 04/05 30,000

2,508,232

 

Grayshott CE (c) Primary

- single storey extension and internal alterations

Design

Jul 05

Feb 06

525,000

Education Capital 05/06 365,000

School 160,000

525,000

 

Hatch Warren Infant and Junior Schools, Basingstoke

- two classroom extension at Infant and four classroom extension at Junior School

Complete

Mar 04

Apr 05

        * 2,988,522

add 19,429

3,007,951

Education Capital 03/04 1,818,287

P&R Capital Repairs 04/05 972,664

P&R NDS Condition 04/05 12,000

School - Infant 86,500

School - Junior 118,500

              3,007,951

 

The Henry Cort Community College, Fareham

- extension to staff room, two new offices, internal remodelling and refurbishment

Tender

Jul 05

Mar 06

359,948

Education Capital 05/06 97,948

School 262,000

359,948

 

Hiltingbury Infant School, Chandlers Ford

- two classroom extension and remove temps

On site

Oct 04

Jul 05

* 689,201

NDS Modernisation 03/04 332,596

P&R NDS Condition 03/04 316,605

School 40,000

689,201

 

John Hunt of Everest Community school, Basingstoke

- New School and Youth facility

Contract Formation

Jul 05

Dec 06

tbc

Capital Receipts 14,188,000

Developer's Contribution 2,382,000

B&D Borough Council 2,038,000

County Council tbc

tbc

 

Kings' Secondary School, Winchester

- six classroom teaching block

On site

Nov 04

Aug 05

* 1,433,569

School 1,433,569

 

Lakeside School, Chandlers Ford

- refurb. boarding accommodation; demolish surplus boarding house; new teaching block and refurbish teaching accommodation

Enabling

Phase 1

Phase 2

Jul 04

Nov 04

Jun 05

Aug 04

Apr 05

Jan 06

* 214,472

* 453,815

1,396,713

2,065,000

Education Mod'tion 04/05 1,565,000

Education Capital 04/05 261,000

P&R NDS Condition 04/05 49,000

P&R Fire Precautions 04/05 190,000

2,065,000

 

Lanterns Children's Centre

- new Early Years Centre

On site

Jul 04

Jul 05

* 2,329,951

Education Capital 03/04 616,000

Temp C'room Hire 04/05 147,000

Capital receipts 1,441,951

Friends of Medecroft 65,000

Medecroft - Devolved capital 60,000

2,329,951

 

Minstead Rural Study Centre, Lyndhurst

- new residential building, extension to schoolhouse and removal of temps

Tender

Jul 05

Mar 06

        888,000

Education Capital 03/04 182,000

New Opportunities Fund 442,000

Seed Challenge 04/05 144,000

Study Centre 94,000

New Forest District Council 26,000

888,000

 

Mountbatten School and Language College

- new Staff Room, Inclusion room and Multi-agency space

Design

Aug 05

Feb 06

448,000

Edu. Capital - SEED 04/05 117,000

School 331,000

448,000

 

Netley Marsh Infant

- new classrooms and extended hall

Tender

Jul 05

Dec 05

739,000

Education Capital 04/05 659,000

School 65,000

P&R Capital Repairs 15,000

739,000

 

Neville Lovett Community School, Fareham

- new entrance foyer and reception; refurbishment of food tech area and hearing impaired unit.

On site

Jan 05

Aug 05

* 560,000

SAI 04/05 274,700

NDS Modernisation 04/05 111,300

School 174,000

560,000

 

Nightingale Primary School, Eastleigh

- new Early Years Centre

On site

Nov 04

Jul 05

* 755,848

NDS Modernisation 04/05 261,000

NEDA 04/05 261,000

Education contingency 04/05 48,000

Early Education 04/05 98,782

P&R NDS Condition 04/05 87,066

755,848

 

Nightingale Primary School, Eastleigh

- extension to provide permanent classroom accommodation

On site

Feb 05

Dec 05

* 1,196,477

NDS Modernisation 04/05 391,304

Contingency 55,173

Capital Receipt 646,552

School 103,448

1,196,477

 

Perins Community School, Alresford

- dance studio, fitness suite and PE classroom

On site

Jan 05

Sep 05

* 1,450,819

add 311,500

1,762,319

Education Capital 04/05 828,024

Transfer of Fees 126,795

Specialist College Status 86,000

School 371,500

P&R Capital Repairs 04/05 300,000

P&R L'lords M/Works 04/05 25,000

P&R NDS Condition 04/05 25,000

1,762,319

 

Portchester Community School

- reorganise reception and administration; internal alterations and access improvements

On site

Jul 04

Jun 05

* 767,936

Education SAI 04/05 413,683

Nursery School Community 18,493

HC3S 34,500

School 195,474

P&R NDS Condition 04/05 83,286

P&R M'ment Partnership 04/05 7,500

P&R Fire Precautions 04/05 15,000

767,936

         

Priestlands Secondary School, Lymington

-music/drama facility and dining extension

Contract Formation

May 05

Arts -

Sep 05

Classrooms

Feb 06

1,615,665

Education Capital 04/05 1,069,828

School 277,000

Specialist School Status 04/05 100,000

P&R NDS Condition 05/06 20,000

Transfer of Fees 148,837

1,615,665

 

Saint Lawrence CE (C) Primary

- new hall, kitchen, link building and internal refurbishment

Design

Jul 05

Dec 05

684,000

Education Capital 05/06 684,000

 

South Baddesley CE (C) Primary

- phase 1 - new classroom and staffroom

- phase 2 - new hall and car park

On site

Design

May 05

Apr 06

Oct 05

Oct 06

* 424,722

500,000

Education Capital 04/05 47,000

School 52,722

NDS Condition 05/06 65,000

P&R Advantageous Land Purchases

        260,000

424,722

 

Staunton Park Community

- Healthy Living Centre

Tender

Jun 05

Dec 05

550,500

NDS Modernisation 04/05 71,000

School 57,500

Sport England 422,000

550,500

 

Swanmore Secondary School

- Multi Use Hall

Complete

Oct 04

Apr 05

* 578,004

Winchester City Council 578,004

 

Testwood School, Totton

- Synthetic Turf Pitch

Tender Analysis

Jun 05

Sep 05

532,423

Football Foundation Grant 482,423

School 50,000

532,423

 

The Toynbee Community College, Chandlers Ford

- new Multi-Purpose Suite

Design

Aug 05

Apr 05

483,000

School 266,000

P&R Capital 05/06 174,000

Eastleigh Borough Council 43,000

483,000

 

Wherwell Primary School, Andover

- extensions and internal alterations

On site

Revised dates

Aug 04

Apr 05

Feb 05

Sep 05

* 538,513

NDS Modernisation 04/05 441,959

Staff Workplaces 04/05 34,783

Temp classroom hire 04/05 9,300

School 52,471

538,513

 

Whitchurch CE (C) Primary

- two new classrooms, ICT Suite and corridor

Tender

Analysis

Jun 05

Nov 05

498,000

Education Capital 04/05 431,000

School 67,000

498,000

 

Whitewater Primary School, Hook

- new hall

On site

Nov 04

May 05

* 424,987

Education Capital 04/05 351,000

School 60,150

P&R NDS Condition 04/05 13,837

424,987

 

SPECIALIST SCHOOLS ACCOMMODATION PROGRAMME 2005/06 Appendix 2

School

Current Status

Start

Complete

Funding / * Contract Sum

Source of Funding £

Robert Mays Secondary School

- refurbishment of science laboratories and preparation rooms

Tender Analysis

Jun 05

Sep 05

373,000

NDS Modernisation 05/06 132,000

Specialist School funds 04/05 87,000

School 154,000

373,000

Mill Chase Community School

- refurbish science laboratories and food technology rooms; refurbishment to form Learning Support Unit

Tender Negotiation

Jun 05

Aug 05

439,000

NDS Modernisation 05/06 331,000

SAI 04/05 108,000

439,000

Package 1 -

    - Toynbee School

    - The Hayling School

    - Noadswood School

    - Aldworth Science College

Tender Negotiation

Jun 05

Aug 05

Sep 05

Nov 05

313,000

NDS Modernisation 04/05 313,000

          Appendix 3

Other Schemes in the Education Capital Programme

The following schemes are included in the Education 2005/06 Capital Programme and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member Education or Policy and Resources:

School Allocation

        (excluding fees)

          £'000

PRIMARY

North Basingstoke schools

776

Whiteley / Western Wards

1,240

 

2,016

SPECIAL

Sundridge School, Havant

4,440

 

4,440

NDS MODERNISATION

Broughton Primary

228

Cove Junior

717

Curdridge Primary

618

Micheldever Primary

1,240

Stanmore Primary

217

The Bridge Centre

830

West Tytherley Primary

811

 

4,661

   

TOTAL

11,117