Archived decisions
Hampshire County Council Amended Decision Sheet
Executive Member, Policy & Resources Item
9 June 2005
Bar End Developments, Winchester - Proposed Disposal to Emmaus Hampshire Ltd.
Report by the Director of Property, Business and Regulatory Services (Summary of CONFIDENTIAL decision)
|
Contact: Ian Gregory Ext: 6573 e-mail: [email protected]
1 |
Summary |
1.1 |
The following decisions are sought: |
1) the granting of a 125 year Building Lease of approximately 0.37 ha (0.88 acres) of surplus County Council land at Bar End to Emmaus Hampshire Ltd at a nominal rent to enable an Emmaus Community to be developed, subject to: | |
i) the Charity confirming its ability to fund all costs directly associated with the development of an Emmaus Centre, and contributing £180,000 as a fair and reasonable proportion of the County Council's costs of bringing forward the overall site for comprehensive development; | |
ii) the Emmaus Centre scheme incorporating the County Council's approved Development Framework principles as a fundamental part of the project; and | |
iii) Emmaus Hampshire Ltd securing planning consent in respect of the proposed development | |
2) to rescind the earlier approval in principle to the disposal of this land to the Winchester Eco Centre charity following their withdrawal from negotiations | |
3) all detailed terms and conditions in respect of the proposed disposal to be settled by the Director of Property, Business and Regulatory Services (Head of Estates Practice). | |
4) that Emmaus be advised that they should demonstrate diligent progress in securing the necessary planning permissions within the next 12 months, adequate financial provision within 24 months, and that a report be brought back to the Buildings, Land and Procurement Panel on progress at both stages | |
Approved by: |
.......................... |
Date of decision: |
......................... |
Councillor T K Thornber |
BLPP163X05 irg/21-Jun-05