2005/06 Environment Capital Programme Progress and Revisions

Report of the Director of Environment

Item

Contact: Helen Ackerman, ext 5077 email: [email protected]

1. Summary

1.1 This report provides summary programme and progress information for the following programmes:

      (i) LTP Capital and Externally Funded Programmes;

      (ii) Principal Roads - Structural Maintenance;

      (iii) Non Principal Roads - Structural Maintenance;

      (iv) Bridges;

      (v) Environmental Improvements;

      (vi) Regeneration of Older Urban Areas (ROUA);

      (vii) Hampshire Villages Initiative; and

      (viii) Waste Management.

2. 2005/06 LTP Capital Programme

2.1 The following table is a summary of the spending plan for 2005/06.

 

Forecast as March 2005

Forecast as May 2005

LTP Capital Allocation for 2005/06

£13.492 million

£13.492 million

     

Forecast spending on previous years' schemes during the year.

£4.4 million

£3.5 million

Allocated resources for developing future years' schemes during the year.

£1.0 million

£1.0 million

Forecast spending on the current year programme during the year.

£8.7 million

£11.2 million

     

TOTAL SPEND FORECAST

£14.1 million

£15.7 million

     

PLANNED SLIPPAGE ALLOWANCE

£0.6 million

£2.2 million

2.2 The Programme revisions outlined in Appendix 2 (Programme Amendment Schedule) increase the 2005/06 Programme value to around £17 million, of which £11.2 million is currently forecast to be spent this year with a further £3 million continued expenditure into 2006/07. Experience shows that some schemes are programmed to start late in the year, may be found to be unsuitable, or will experience delays during their development, consultation and design stages. It is therefore prudent to set a programme level in excess of the resources available and to manage the spending within that programme to achieve the target at the end of the year.

3. Amendments to the 2005/06 LTP Capital Programme included in the spending plan

3.1 The following schemes are new to the programme since March 2005. These are all included in Appendix 2:

SCHEME NAME

PROGRAMME VALUE

SUMMARY COMMENTS

New Footways, The Wallops

£30,000

Delay from 2004/05. Start of construction delayed from February to April.

Park Lane Traffic Management, Fareham

£45,000

Delay from 2004/05. Scheme now progressing separately in order to enable delivery.

A33 Ringway Roundabout, Popley Way Traffic Signals

£2,733,000

Delayed from 2004/05 in January. Part funded with contributions that are still being received. This value represents the maximum capital investment. Reductions to this value will be proposed as the contributions are received.

TOTAL ADDITIONS

£2,808,000

 

3.2 Amendments to programme values within the 2005/06 programme are all listed in Appendix 2. Overall, the 2005/06 programme value has risen by over £3 million, however the spending is considered to be within manageable limits of the target at this stage of the year.

    Safer Routes to School Sub-Programme

3.3 There are a number of proposed amendments to the Safer Routes to School sub-programme since March 2005. The revised programme is attached as Appendix 1A, with details of the amendments in Appendix 2A. These amendments increase the spending plan to £1.9 million, £400,000 above the allocation. This programme will be managed during the year to ensure that the allocation is not exceeded.

4. 2005/06 LTP Externally Funded Programme

4.1 Appendix 1 also sets out the revised 2005/06 LTP Externally Funded Programme. For the purpose of this report, external funding means "funding allocated from non LTP Capital resources".

4.2 The following table is a summary of the spending plan for 2005/06.

 

Forecast as March 2005

Forecast as May 2005

Forecast spending on previous years' schemes during the year.

£1.5 million

£1.9 million

Allocated resources for developing future years' schemes during the year.

Not reported

£0.5 million

Forecast spending on the current year programme during the year.

Not reported

£6.4 million

TOTAL SPEND FORECAST

 

£8.8 million

4.3 The Programme revisions also outlined in Appendix 2 (Programme Amendment Schedule) increase the 2005/06 Externally Funded Programme value to £9.5 million, of which over £1.0 million has already been spent in previous years against this programme, £6.4 million is currently forecast to be spent this year and in excess of £2 million continued expenditure into 2006/07. This programme contains joint funded schemes with LTP Capital funding, most notably the A33 Ringway Junction at Popley. Contributions are still being collected towards this scheme and will not be fully received until 2007. It is therefore proposed that the EF allocation will increase as this funding becomes available, and the corresponding capital allocations reduced accordingly.

5. Amendments to the 2005/06 Externally Funded LTP Programme included in the spending plan

5.1 The following schemes are new to the programme since March 2005 and are all included in Appendix 2.

SCHEME NAME

PROGRAMME VALUE

SUMMARY COMMENTS

A325 Farnborough Gate Cycles - Final Phase

£50,000

Delayed from 2004/05. Programmed bridgeworks clashed with proposed start of works. Raised parapets now included in the bridgeworks in preparation for the cycle route. Starting on site summer 2005.

SCHEME NAME

PROGRAMME VALUE

SUMMARY COMMENTS

A33 Ringway Roundabout, Popley Way Traffic Signals

£967,000

Previously reported as delayed from 2004/05 in January. This value represents the contributions currently held by the County Council. Further contributions are expected between now and March 2007. This value will increase as new funding arrives, and the corresponding LTP value will reduce.

Westbury Road, Fareham

£10,000

Delayed from 2004/05. Fareham Borough Council identified path as Public Right of Way so scheme can only progress with Cycle Tracks Act, which takes considerable time. This scheme now changed to be minor improvements such as vegetation clearance, street lighting and some surfacing so that cycleway may follow in due course by Borough Council.

Kipling Road Traffic Management, Eastleigh

£30,000

Delayed from 2004/05. Significant delays at Eastleigh Borough Council providing justification/ background. Staff shortages at County Council created further delays. Scheme now being progressed for summer.

Marchwood Pedestrian Facilities

£50,000

Delayed from 2004/05. Consultations with Parish extended, but have declined to comment. Scheme progressing for summer construction.

Falkland Road Puffin

£75,000

Delayed from 2004/05. Procurement and TRO process took longer than forecast. Start expected March but contractors not available. Scheme started 23 May.

A32 Mumby Road Pedestrian Improvements Phase 1

£20,000

New to programme.

Crossing requirements following completion of new Doctor's surgery.

SCHEME NAME

PROGRAMME VALUE

SUMMARY COMMENTS

A32 Mumby Road Pedestrian and Cycle Improvements - Phase 2

£30,000

New to programme.

Links with above. Being progressed separately as crossings can be constructed quickly. Other improvements to follow in the autumn.

Salterns Lane Traffic Calming

£49,000

Delayed from 2004/05. Construction started May 2005.

TOTAL ADDITIONS

£1,281,000

 

5.2 Amendments to programme values within the 2005/06 programme are also listed in Appendix 2.

6. 2005/06 Capital Highways Maintenance and Bridges

6.1 The following table is a summary of the capital starts programme for 2005/06.

 

Programme as April 2005

Programme as May 2005

Carried forward from 2004/05

Not reported

£1.031 million

     

Principal roads structural maintenance

£5.810 million

£5.874 million

Non-Principal roads structural maintenance

£14.178 million

£14.394 million

Non-Principal roads additional programme

£3.678 million

£3.678 million

Bridges

£3.662 million

£4.413 million

TOTAL SPEND FORECAST

£27.328 million

£28.359 million

NB The carried forward figures have been added to the individual lines. Total does not include c/f line.

6.2 A total sum of £27,328 million was originally provided for structural maintenance of roads and bridges within the 2005/06 starts Capital Programme. This sum comprised £14.614 million from the LTP together with £12.714 million from local resources. The latter figure included an additional £3.678 million for repairs to local roads and footways, continuing the level of support provided by the Council in the previous two years.

6.3 Appendix 3 sets out the details of the original 2005/06 starts programme for structural maintenance, agreed in consultation with the former Executive Member for Environment in March 2005, together with the latest programme amendments. The revised starts programme includes £1.031 million carried forward from 2004/05 to cover expenditure that is forecast to complete last year's programme.

7. Non Transport Capital Programmes

7.1 The following table is a summary of the starts programme for 2005/06.

 

Programme as April 2005

Programme as May 2005

Environmental Improvements

£0.406 million

£0.406 million

Regeneration of Older Urban Areas

£0.921 million

£0.921 million

Hampshire Village Initiative

£0.082 million

£0.082 million

Waste Management

£1.111 million

£1.111 million

TOTAL SPEND FORECAST

£2.52 million

£2.52 million

7.2 Appendix 4 sets out details of the non-transport capital programmes covering the above headings. These programmes were approved by the former Executive Member for Environment in April 2005.

7.3 The Waste Management Programme provides £61,000 towards landfill remedial works, £1 million towards the replacement and upgrading of household waste recycling centres, and £50,000 for environmental control at landfill sites.

7.4 Funding allocated towards household waste recycling centres will be used to help the County Council meet its statutory targets for recycling and to accommodate increasing demand as a result of new legislation. Customers already experience delays at many of the sites, particularly during peak times, and these pressures are expected to exacerbate the problem. It is estimated that seven sites need enlarging, or relocating to cope with the expected future demand, and provision is inadequate in a further four locations. Feasibility studies are underway and firm decisions will be required on the detailed allocation of the £1 million budget for 2005/06 once these assessments have been completed in the summer.

8. Monitoring and Reporting

8.1 In order to ensure that the spending fully utilises the available resources, these programmes will be regularly monitored and scheme spending adjusted. An update together with recommendations will be provided every quarter.

8.2 The LTP Annual Progress Report (APR) sets out the LTP targets in terms of spending and `deliverables' such as number of street lights, kilometres of new footways. This information is now being collected regularly as part of the LTP monthly monitoring cycle, and will form the basis of the APR targets outlined to Government. Monitoring the spending and delivery against these targets will commence in July, and it is anticipated that a statement of progress will be provided in these quarterly reports from September.

Recommendations

1. That the revised 2005/06 LTP Capital Programme be approved as set out in Appendix 1.

2. That the revised 2005/06 Safer Routes to School Programme be approved as set out in Appendix 1A.

3. That the revised 2005/06 Highways Maintenance and Bridges Programme be approved as set out in Appendix 3.

Section 100 D - Local Government Act 1972 - background papers

 

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

 

NB the list excludes:

 

1.

Published works.

 

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None

 

354Rpt/HA

APPENDIX 1

2005/06 LTP CAPITAL PROGRAMME

 

CAPITAL

EXTERNAL

 

FUNDING

FUNDING

Central Hampshire Transport Strategy

   

A343 Newbury Road, Andover (Enham Arch)

 

£350,000

Pulens Lane to Tor Way Cycles, Petersfield

 

£130,000

Charles Street/Lavant Street (Station to Town Centre), Petersfield

 

£70,000

Alton Traffic Management

£250,000

£13,000

Fletchers Field Cycles, Liphook

 

£55,000

A31 Junction Lymington Bottom, Four Marks - Junction Alteration

£100,000

£10,000

Andover Station to Town Centre Cycleway

£340,000

£10,000

Sparkford Road Traffic Management, Winchester

£40,000

£5,000

Salters Lane (Harestock Corner) Junction Improvements, Winchester

 

£140,000

Access to East Hampshire AONB

£20,000

 

Andover to Salisbury Bus Quality Partnership

£100,000

 

Winchester RTI replacement

£350,000

 

New Footways, The Wallops

£30,000

 

Andover Cycles - London Street to Newbury Street

£150,000

£50,000

 

£1,380,000

£833,000

New Forest Transport Strategy

   

Ringwood Pedestrians and Cycles

£50,000

 

Rookes Lane and Ridgeway Lane, Traffic Management

£155,000

 

A337 Pennington Cross to Roundabout - Belmore Road

£125,000

 

NFTS Decriminalised Parking

£120,000

 

New Forest Bus Infrastructure Improvements

£100,000

 

Lyndhurst to Ashurst Cycles

£490,000

 

New Forest Car Free Tourism

£10,000

 

New Forest Cycle Plan

£40,000

 
 

£1,090,000

 

North Hampshire Transport Strategy

   

NHTS Bus Infrastructure and Improvements (Yateley Route 3)

£200,000

 

Summit Avenue Toucan Crossing, Farnborough

 

£100,000

A33 Ringway Roundabout, Popley Way Traffic Signals.

£2,733,000

£967,000

 

CAPITAL

EXTERNAL

 

FUNDING

FUNDING

A30 Brighton Hill Roundabout, Signals

 

£1,500,000

North Popley to Town Centre Pedestrians/Cycle Routes, Basingstoke

£100,000

£320,000

NHTS Bus Infrastructure and Improvements-Farnborough Route 6 stage 2

£150,000

 

NHTS Village Initiatives

£60,000

 

B3272 Corridor, Yateley - Eversley Traffic Management

£200,000

 

Basingstoke Route 3, Quality Bus Partnership (Popley-South Ham)

£200,000

 

Old Trunk Road, Farnborough

£14,000

£50,000

Farnborough District Cycle Parking

 

£24,000

Fleet Town Centre

£400,000

£2,475,000

Gabriel Park to Leisure Centre Cycles, Basingstoke

 

£220,000

A325 Farnborough Gate Cycles, Final Phase

 

£50,000

 

£4,057,000

£5,706,000

Solent Transport Strategy

   

Yew Tree Drive, Whiteley

£250,000

£250,000

Chilworth to Southampton Cycles

£30,000

£120,000

Rownhams/Nursling Traffic Calming

£50,000

 

Factory Road, Eastleigh - Traffic Management

£375,000

£200,000

Knowle Village to Funtley Footways

 

£40,000

Gosport Urban Centre Improvements

£100,000

 

Hardley to Hythe Cycle Route*

 

£145,000*

Park Lane Traffic Management, Fareham

£45,000

 

FWW Western Distributor Road (Schooner Way-Warsash Road)

£1,025,000

£420,000

Westbury Road, Fareham

 

£10,000

Fontley Road Footway

 

£100,000

A3090 Winchester Road/Cupernham Lane, Romsey - Traffic Signals

£200,000

£100,000

Leigh Road Corridor, Eastleigh

£200,000

£300,000

A27 Botley Road Hedge End, Bus Access

£315,000

£100,000

Fareham Decriminalised Parking

£130,000

 

Havant Route 21 Quality Bus Partnership

£100,000

 

Southampton to Winchester Quality Bus Partnership

£350,000

 

Hamble Bus Route 16 - Capital Grant

 

£100,000

Kipling Road Traffic Management, Eastleigh

 

£30,000

Marchwood Pedestrian Facilities

 

£50,000

Hamble Lane/Ensign Way Pedestrian Schemes

 

£25,000

Falkland Road Puffin (part pedestrians programme)

 

£75,000

 

CAPITAL

EXTERNAL

 

FUNDING

FUNDING

A32 Mumby Road Pedestrian Improvements Phase 1

 

£20,000

Hound Road Cycleway, Netley

 

£125,000

Eastleigh Bus Quality Partnership - Derby Road, Passfield Avenue

 

£70,000

Chestnut Avenue Eastleigh, Cycles

 

£225,000

Salterns Lane Fareham, Traffic Calming

 

£49,000

A27 Corridor Fareham, Traffic Management (Pedestrian Crossings)

£260,000

£150,000

Hayling Billy Route, Havant Railway Station Cycleway - Phase 2

£250,000

£24,000

A335 Wide Lane Cycle Crossing (CLLR)

 

£193,000

Hythe Pier Maintenance

£90,000

 
 

£3,770,000

£2,728,000

    · Hardley to Hythe scheme currently under review

Safety Programme

   

Tukes Avenue

£50,000

 

Refurbishment and Betterment

£200,000

 

Surface Dressing Programme

£1,380,000

 

Low Cost Sites Programme

£1,000,000

 

Water Lane, Totton, Traffic Calming

£120,000

£245,000

Casualty Reduction Programme

£250,000

 
 

£3,000,000

£245,000

Other Integrated Transport

   

Minor Traffic Management Schemes

£460,000

 

Recreational Cycling Schemes

£77,000

 

Pedestrian Crossings Programme

£200,000

 

Passenger Transport Information

£172,000

 

Central ITS

£200,000

 

Community Safety Initiative

£97,000

 

Community Transport Schemes

£300,000

 

Minor Schemes Programme

£200,000

 

Safe Routes to School Programme

£1,500,000

 

Rail Stations and Interchanges

£50,000

 

Air Quality and Noise Monitoring

£69,000

 

LTP Monitoring and Initiatives

£277,000

 

Rural (Parish) Partnership Schemes (carried forward)

£65,000

 
 

£3,667,000

 
     

TOTAL 2005/06 LTP PROGRAMME

£16,964,000

£9,512,000

APPENDIX 1A

SAFER ROUTES TO SCHOOL PROGRAMME 2005/06

 

 

District

School

Scheme Description

£

Basingstoke

Woolton Hill Junior and St Thomas' Infants Schools

Traffic management measures, improved signing, improved facilities for pedestrians by way of informal crossing facilities and additional footpath.

115,000

East Hampshire

St John's Primary, Rowlands Castle

Provision of improved signing and lining plus informal crossing points.

45,000

East Hampshire

Liphook Infant and Junior School

Provision of speed reducing features, signing and lining.

55,000

East Hampshire

Sheet Primary School

Signing, lining and footway widening.

15,000

East Hampshire

Four Marks Primary School

Improved signing and lining.

20,000

Eastleigh

Bursledon Infant and Junior

Additional footpath on School Lane.

10,000

Eastleigh

Thornden School, Chandlers Ford

Entrance widening to provide improved pedestrian and cycle access.

25,000

Eastleigh

Shamblehurst Primary School, Hedge End

Provision of cycle shelters.

45,000

Eastleigh

Toynbee School, Chandlers Ford

Provision of cycle shelters and school safety zone.

26,000

Eastleigh

Fryern Infant and Junior Schools

Improved pedestrian access improvements.

50,000

Eastleigh

Hiltingbury Infant and Junior Schools

Contribution towards wider Hiltingbury Recreation Ground scheme which includes cycle and pedestrian access improvements.

30,000

District

School

Scheme Description

£

Eastleigh

Crescent Primary School

School crossing improvement scheme.

25,000

Eastleigh

Merdon Junior School, Chandlers Ford

Remaining spend from 2004/05 scheme.

2,000

Eastleigh

Alderman Quilley School

Scheme to provide new pedestrian and cycle access, footway and cycle parking, and to remove current conflict with vehicles.

120,000

Eastleigh

Freegrounds Infant and Junior Schools, Hedge End

Speed reducing features, informal crossing points and improved signing.

40,000

Fareham

Portchester Community School

tbc

70,000

Gosport

Gomer Infant School

Improved signing, lining and pedestrian facilities.

23,000

Gosport

Lee-on-the-Solent Junior School

Improved signing, lining and pedestrian facilities.

50,000

Gosport

Bay House School

tbc

70,000

Rushmoor

Linden Education Centre

Remaining spend from 2004/05 scheme.

30,000

Hart

Robert May's School, Odiham

Improved measures for pedestrians including new footpath along Firs Lane (subject to land availability).

50,000

Havant

St Thomas Moore RC School

tbc

30,000

Havant

Hart Plain Infant and Junior

tbc

50,000

Havant

Emsworth Primary School

tbc

20,000

District

School

Scheme Description

£

New Forest

Hounsdown School, Totton

Scheme to provide new cycle and pedestrian access, and to remove current conflict with vehicles.

110,000

Test Valley

Hurstbourne Tarrant CE Primary School

tbc

70,000

Test Valley

Winton Schools

tbc

100,000

Winchester

Newtown Soberton (Church Road)

tbc

30,000

Winchester

St Bede CE Primary School

Improved signing and lining

20,000

Winchester

Perins School, Alresford

Enhanced measures for pedestrians and cyclists.

100,000

Winchester

St Faith's CE Primary School

tbc

35,000

Winchester

Swanmore Primary School

tbc

50,000

Other

Further design work

Ongoing

250,000

Other

Minor Works

Ongoing

75,000

Other

School Crossing Patrol Upgrades

Ongoing

100,000

TOTAL

 

 

1,956,000

APPENDIX 2

2005/06 PROGRAMME AMENDMENT SCHEDULE

 

Formal Approved Value

Latest Cost Estimate

 
 

Capital

External

Capital

External

 
 

March 2005

June 2005

COMMENTS

CHTS

         

New Footways, The Wallops

   

£30,000

 

Contractor(RCS) delayed start of construction from February to April. Scheme therefore did not start within 2004/05 and is moved to the 2005/06 Programme.

NHTS

         

A325 Farnborough Gate Cycles

     

£50,000

Delayed from 2004/05. Programmed bridgeworks have delayed start of scheme. Raised parapets now included in bridgework in preparation for cycle scheme. Start now expected summer 2005.

A33 Ringway Roundabout, Popley Way Traffic Signals

   

£2,733,000

£967,000

Delayed from 2004/05 programme in January. Late start on site expected during 2005/06. Further £1.5 million contributions due between now and March 2007. It is possible that this scheme will be entirely EF funded, however until funding is in place LTP capital will be allocated.

STS

         

Park Lane Traffic Management, Fareham

   

£45,000

 

Delayed from 2004/05. Fareham Borough Council was progressing alongside Westbury Road (path) cycles, but because of Cycle Tracks Act issues this scheme is now progressing separately. Borough Council to confirm new programme.

Fareham Western Wards Western Distributor

£1,025,000

£375,000

£1,025,000

£420,000

Additional contributions added to this scheme. Capital funding remains unchanged until detailed costs are estimated.

 

Formal Approved Value

Latest Cost Estimate

 
 

Capital

External

Capital

External

 
 

March 2005

June 2005

COMMENTS

Westbury Road, Fareham

     

£10,000

Delayed from 2004/05. Fareham Borough Council has now identified that path is a Public Right of Way, therefore scheme needs to be progressed through Cycle Tracks Act which will take significantly longer than programmed. Scheme therefore changed to be minor improvements, such as street lighting, surfacing and vegetation clearance, so that cycleway can be constructed by Borough Council in the future.

Kipling Road Traffic Management

     

£30,000

Delayed from 2004/05. Significant delays at Eastleigh Borough Council in providing justification/ background for this scheme. Staff shortages within County Council resulted in further delays. Scheme now being progressed for summer.

Marchwood Pedestrian Facilities

     

£50,000

Delayed from 2004/05. Consultation with Parish extended, but it has declined to comment. Scheme now progressing for summer.

Falkland Road Puffin

     

£75,000

Delayed from 2004/05. Procurement and TRO process took longer than programmed. Start delayed until March when contractor not available. Works started in May.

A32 Mumby Road Pedestrian Improvements Phase 1

     

£20,000

New to Programme. Crossing requirements following construction of Doctor's surgery.

A32 Mumby Road Pedestrians/ Cycles

     

£30,000

New to Programme. Links with above. Additional pedestrian and cycle improvements to follow phase 1.

Salterns Lane, Fareham, Traffic Calming

     

£49,000

Delayed from 2004/05. Construction started in May.

 

Formal Approved Value

Latest Cost Estimate

 
 

Capital

External

Capital

External

 
 

March 2005

June 2005

COMMENTS

           

OTHER INTEGRATED TRANSPORT

       

Passenger Transport Information

£160,000

 

£172,000

 

Schemes controlled on an expenditure basis. Programme value increased by £12,000 carried forward from 2004/05.

Recreational Cycling

£50,000

 

£77,000

 

Schemes controlled on an expenditure basis. Programme value increased by £27,000 carried forward from 2004/05.

Air Quality and Noise Monitoring

£50,000

 

£69,000

 

Schemes controlled on an expenditure basis. Programme value increased by £19,000 carried forward from 2004/05.

Community Safety Initiative

£60,000

 

£97,000

 

Schemes controlled on an expenditure basis. Programme value increased by £37,000 carried forward from 2004/05.

Rural (Parish) Partnership Schemes

   

£65,000

 

Schemes controlled on an expenditure basis. Programme value for this heading is entirely carried forward from 2004/05.

LTP Monitoring and Initiatives

£150,000

 

£277,000

 

Schemes controlled on an expenditure basis. Programme value increased by £127,000 carried forward from 2004/05.

APPENDIX 2A

2005/06 SAFER ROUTES TO SCHOOL SUB-PROGRAMME AMENDMENT SCHEDULE

 

Formal Approved Value

Latest Cost Estimate

 
 

Capital

External

Capital

External

 
 

March 2005

June 2005

COMMENTS

BASINGSTOKE

         

Woolton Hill Junior School

£100,00

 

£115,000

 

Slight increase in costs from following provision of detailed estimates.

EASTLEIGH

         

Alderman Quilley School

   

£120,000

 

New to programme. New pedestrian and cycle access to school site.

Merdon Junior School

   

£2,000

 

New to programme. Omitted from previous report. Residual spend on previous year scheme.

Crescent Primary School

   

£25,000

 

New to programme. Omitted from previous report. School crossing improvements.

HART

         

Linden Education Centre

   

£30,000

 

New to programme. Omitted from previous report. Residual spend on previous year scheme.

WINCHESTER

         

Newtown Soberton

£50,000

 

£30,000

 

Decrease in original allocation following provision of detailed estimates.

APPENDIX 3

2005/06 Capital Highways Maintenance and Bridges

Principal Roads Structural Maintenance

Programme at 1 April 2005

Revised Programme

Carriageway, footway & Drainage routine repairs

£750,000

£750,000

     

Strengthening major maintenance schemes

£1,900,000

£1,900,000

Contingencies

£150,000

£150,000

     

Special Maintenance

£1,003,000

£1,003,000

Resurfacing

£882,000

£882,000

Surface Dressing - high performance roads contract

£512,000

£512,000

     

Design and supervision fees

   

    _ Major maintenance schemes

£150,000

£150,000

    _ Special maintenance, resurfacing and surface dressing

£173,000

£173,000

    _ Routine maintenance

£8,000

£8,000

     

Completion of 2004/05 works programme

 

£69,000

     

Reserves

£282,000

£277,000

     

Sub-Total.

£5,810,000

£5,874,000

     

Non-principal Roads Structural Maintenance

Programme at 1 April 05

Revised Programme

Carriageway, footway & Drainage routine repairs

£4,520,000

£4,520,000

     

Surface dressing - high performance roads contract

£1,382,000

£1,382,000

Surface dressing - minor roads contract

£935,000

£935,000

Surface dressing - footways contract

£300,000

£300,000

     

Special maintenance and recycling

£3,369,000

£3,369,000

Cattle Grids

£50,000

£50,000

     

Tactile surfacing and pram crossings

£136,000

£136,000

Resurfacing

£2,382,000

£2,382,000

Blacktop testing

£15,000

£15,000

Safety fencing

£250,000

£250,000

     

Portchester Homezone

£125,000

£125,000

Village Initiatives

£35,000

£40,000

     

Design and supervision fees

   

    _ Special maintenance, resurfacing and surface dressing

£589,000

£589,000

    _ Routine maintenance

£90,000

£90,000

     

Completion of 2004/05 works programme

 

£211,000

     

Sub total - non-Principal roads structural maintenance

£14,178,000

£14,394,000

     
     

Non-principal Roads Structural Maintenance (Additional Programme)

Programme at 1 April 05

Revised Programme

Footways special maintenance schemes

£1,862,000

£1,862,000

Carriageway haunch repairs, resurfacing & recycling

£1,458,000

£1,458,000

Footways surface dressing

£91,000

£91,000

Fees

£267,000

£267,000

     

Sub total - additional programme

£3,678,000

£3,678,000

     

Bridges Structural Maintenance

Programme at 1 April 05

Revised Programme

Strengthening schemes

£1,900,000

£1,700,000

Assessments, studies and feasibility

£360,000

£360,000

Structural maintenance

£1,052,000

£1,252,000

Road/Rail interface

£350,000

£350,000

     

Completion of 2004/05 works Programme

 

£751,000

     

Sub total - Bridges structural maintenance

£3,662,000

£4,413,000

     

TOTAL CAPITAL MAINTENANCE PROGRAMME

£27,328,000

£28,359,000

     
     
     
     
     

Reconciliation to Capital Programme

Programme at 1 April 2005

Revised Programme

     

Schemes supported from local resources:

   

    _ Structural maintenance of non-principal roads

£9,036,000

£9,036,000

    _ Additional provision for repairs to local roads and footways

£3,678,000

£3,678,000

     

Schemes supported by Government borrowing approvals (LTP)

£14,614,000

£14,614,000

    _ Including forecast expenditure on previous years' schemes of £453,000

   

Schemes carried forward from 2004/05;

   

    _ Supported from local resources

 

£578,000

    _ Supported by Government borrowing approvals (LTP)

 

£453,000

     

TOTAL 2005/06 CAPITAL MAINTENANCE PROGRAMME

£27,328,000

£28,359,000

NB - This is a starts programme and these figures represent the value of works that will start within the year and not the annual expenditure forecast. A review of progress on previous years' capital starts programmes will be included in subsequent reports.

APPENDIX 4

2005/06 Non-Transport Capital Programmes

Environmental Improvements

Programme at 1 April 2005

Revised Programme

Country Towns Initiative

   

    _ Odiham town centre

£208,000

£208,000

    _ Supplementary schemes: Swanmore Centre

£50,000

£50,000

Sub total -

£258,000

£258,000

     

Other Environmental Initiatives:

   

    _ Land Management

£21,000

£21,000

    _ Schools Landscape Programme

£30,000

£30,000

    _ Landscape Strategy

£23,000

£23,000

    _ Historic Parks and Gardens

£10,000

£10,000

    _ Heathlands

£34,000

£34,000

    _ Biodiversity

£30,000

£30,000

Sub total -

£148,000

£148,000

Total Environmental Improvements

£406,000

£406,000

     

Regeneration of Older Urban Areas

   

The Square, Hamble

£200,000

£200,000

Church End Green, Yateley

£200,000

£200,000

Old Totton

£300,000

£300,000

Programme/Project fees

£221,000

£221,000

     

Total Regeneration of Older Urban Areas

£921,000

£921,000

     

Hampshire Villages Initiative

   

Horndean - improve entrance to village

£50,000

£50,000

South Wonston - entrance sign to village

£3,000

£3,000

Steep Marsh - Gateway treatment and signing

£3,000

£3,000

West Liss - village green enhancement

£17,000

£17,000

Unallocated balance

£9,000

£9,000

     

Total Hampshire Villages Imitative

£82,000

£82,000

     

Waste Management

   

Landfill remedial works

£61,000

£61,000

Household Waste Recycling Centres

£1,000,000

£1,000,000

Landfill Sites - environmental control schemes (supported by Government funding)

£50,000

£50,000

     

Total Waste Management Programme

£1,111,000

£1,111,000

     

TOTAL NON TRANSPORT 2005/06 PROGRAMME

£2,520,000

£2,520,000

NB - This is a starts programme and these figures represent the value of works that will start within the year and not the annual expenditure forecast. A review of progress on previous years' capital starts programmes will be included in subsequent reports.