Archived decisions

Hampshire County Council

Executive Member - Environment: South Hampshire and Resource Management

28 June 2005

Business Travel Plan Partnership Fund

Report of the Director of Environment

Item 3

Contact: Amy Bristow, ext 7038 email: [email protected]

1. Summary

1.1 The following decision is sought:

    That £36,900 be awarded from the Business Travel Plan Partnership Fund allocation in the 2005/06 transport capital programme and £9,280 from revenue to the projects set out in attached Appendix 1.

2. Reason

2.1 This decision supports the following Aims of the Corporate Strategy:

      (i) Aim 2 (Stewardship of the Environment) - the introduction of measures to encourage use of sustainable modes of transport through the Business Travel Plan Partnership funded projects will have a positive impact on the environment; and

      (ii) Aim 3 (Achieving Economic Prosperity) - the projects delivered through the Business Travel Plan Partnership will widen travel choice for staff and visitors to these establishments, thereby increasing their attractiveness which should have a positive impact on business performance.

3. Other Options Considered and Rejected

3.1 No other options were considered appropriate for the delivery of the objectives or the principles of the Partnership Fund.

4. Conflicts of Interest Declared by the Decision Maker or Other Executive Member Consulted - None.

5. Dispensation granted by the Standards Committee - Not applicable.

6. Reason(s) for the Matter being dealt with if Urgent - Not applicable.

Approved by: Date:

Councillor T G Knight

317Decn/AB

APPENDIX 1

PROPOSED BUSINESS TRAVEL PLAN PARTNERSHIP FUNDED PROJECTS 2005/06

Organisation

Project

Expected Project Outcomes

Total project cost (£)

Bid for HCC contribution (capital) (£)

Bid for HCC contribution (revenue) (£)

Gifford and Partners Limited, Totton

Secure cycle parking

Increase in cycling

15,000

5,000

-

B&Q, Chandlers Ford

Carshare kiosk,

marketing campaign and materials

Increase car sharing and raise staff travel awareness

20,700

-

5,000

Deny's E Head (Bird World and Forest Lodge), near Farnham

Pool bicycles, cycle storage, display boards, maps and leaflets

Increase in cycling

9,750

3,875

1,000

Chandlers Ford Commuter Forum

Bespoke bus timetables and commuter information leaflets

Increase in bus use

1,500

-

750

Vitacress Salads Limited, St Mary Bourne

Secure cycle shelter

Increase in cycling

4,860

2,430

-

Southampton International Airport

Secure cycle shelter

Increase in cycling

10,000

5,000

-

Fareham and Gosport Primary Care Trust

Cycle shelter, improved car park signage, leaflets, posters and information for visitors

Increase in cycling and improve car park manage-

ment

14,028

4,000

1,000

Eli Lilly, Basingstoke

Pool bicycles, lockers for pool bike equipment, cyclists lockers, Carshare passes, Carshare space signage, dropped kerbs

Increase in cycling and car sharing

11,540

4,970

30

North Hants Hospital, Basingstoke

Staff and visitor cycle parking

Increase in cycling

6,249

3,125

-

Organisation

Project

Expected Project Outcomes

Total project cost (£)

Bid for HCC contribution (capital) (£)

Bid for HCC contribution (revenue) (£)

Queen Mary's College, Basingstoke

Pool bicycles, cycle to college leaflet, walk to college leaflet, path and cycle route, drop off bays and improved motorcycle parking

Increase cycle, walk and bus use

11,600

4,000

1,000

Brockenhurst College

Two cycle shelters, Carshare information

Increase in cycle use

10,000

4,500

500

TOTAL

36900

9280