Archived decisions
| How the conclusion in this report fits with the Corporate Strategy This scheme will impact on the delivery of all Corporate Aims, focusing most immediately on: Aim 5 - improving services: by improving educational services and making the best use of resources. |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act.
Title Location
Architect's plans PMIS file
Building Profile Reports TMH
Hampshire County Council
Building Design Project Appraisal |
Buildings, Land and Procurement Panel
30 June 2005
Executive Member - Education
13 July 2005
Executive Member - Policy and Resources
14 July 2005
Project: |
Blackfield Primary School | |
Extension and remodelling of Blackfield Junior School to create a 2.5FE Primary School | ||
Commencement date: |
November 2005 | |
Completion date: |
September 2006 | |
Planned year of start in accordance with Capital Programme: |
2005/06 | |
Recommendation:
That the building design project appraisal for the Blackfield Primary School scheme be approved.
1 Finance
Capital Expenditure |
Current Estimate £'000 |
Capital Programme £'000 |
Buildings |
1,250 |
1,185 |
Fees |
200 |
190 |
Land to be purchased |
_ |
_ |
Total |
* 1,450 |
1,375 |
* The means by which the difference between the Current Estimate and the Capital Programme
allocation is to be met is shown in the table below.
Financial Provision for Total Scheme |
Buildings £'000 |
Fees £'000 |
Total cost £'000 |
1 From own Resources: |
|||
a) Capital Programme (05/06) |
1,185 |
190 |
1,375 |
b) School |
65 |
10 |
75 |
Total |
1,250 |
200 |
1,450 |
Building Cost - Net Cost = £1,696 per m2
- Gross Cost = £2,633 per m2
Devolved Capital allocations - Infant School £'000
2004/05 22
2005/06 22
Devolved Capital allocations - Junior School
2004/05 33
2005/06 32
Estimated Devolved Capital allocations - Primary School
2006/07 62
2007/08 52
Total 223
Landlord funded work connected with this scheme
There is no Landlord funded work associated with these proposals.
Value of land already acquired for this project
Blackfield Junior School site is vested in the Governing Body, having been statutorily transferred to them in 1993 on obtaining Grant Maintained status.
Revenue implications
(a) Employees £'000 |
(b) Other £'000 |
(a+b) Net Current Expenditure £'000 |
(c) Capital Charges £'000 |
(a+b+c) Total Net Expenditure £'000 | |
Revenue Implications Additional+ /Reductions |
- 82 |
- 54 |
- 136 |
76 |
- 60 |
Unit cost (£) (e.g. per place) |
- |
- |
- |
- |
- |
% variation to Committee's budget |
- |
- | |||
Number of additional Staff (fte) |
- |
- |
Energy costs
The estimated annual energy consumption for the new accommodation will meet that required by current Building Regulations. It is anticipated that the increase in fuel cost for the school will be in the order of £3,808 per year (£4.90 for each m² of new accommodation) with an additional 21 tonnes of CO2.
2 Details of site and existing infrastructure
Location/adjoining land and buildings
The Infant and Junior Schools share a site located to the north west of Blackfield. To the north and west are open fields with the village of Holbury further to the north. The east of the site is bounded by Hampton Lane with housing beyond and to the south is further housing and Blackfield village centre.
Area including comparison with local/national standards
The total site area is 6.72 acres (2.71 hectares). The scheme will result in an additional 0.36 acres (0.14 hectares) being added to this site from the existing infant school area.
The DfES guideline for a school of this size is 5.58 acres (2.26 hectares).
Access
There are currently three vehicular and pedestrian entrance points to the shared site along the eastern boundary of the site from Hampton Lane. It is proposed that the new Primary School will retain one entrance point at the very north east corner, which will enable greater security and the control of pedestrians onto the site. The existing road access will be retained and will be widened on the southern side to allow a two way road (currently a single road). A narrowing to the access road is proposed, as a traffic calming measure, encouraging vehicles to slow down.
A new pedestrian route is proposed alongside the vehicular access. Car parking is to be located adjacent the pedestrian route with bollards positioned to prevent cars encroaching onto the verge. These proposals offer further separation of vehicles from pedestrians.
A vehicle turning circle is proposed at the top of the access road to allow vehicles, especially coaches, to always turn in the same direction, thus offering greater safety to pedestrians. A separate new access to the rear of the proposed new Infant accommodation will be constructed for use by emergency vehicles.
During the construction period the contractor will have sole use of the southern most vehicular entrance from Hampton Lane, with direct access to a compound located adjacent the proposed new accommodation.
Existing buildings and temporary buildings
The original Junior school was constructed in 1958 and has since been extended by way of a SCOLA teaching block in 1970's and more recently in the 1990's, an administration accommodation extension and a new classroom block. There are no temporary buildings on the site.
Results of trial boreholes
A site investigation is currently being undertaken and results will be known in due course. Previous investigations undertaken at this site for previous phases of work have recommended the use of traditional strip foundations.
Mains services position
The external services to the existing Junior School are inadequate to serve the proposed Primary School. It is therefore proposed that a new electrical cable is brought to the site via the main entrance from Hampton Lane.
The schools currently operate with oil heating. The extension will be heated with a gas fired boiler independent from the main school boilers. A new gas supply will be laid in the access road to serve the proposed extension with sufficient capacity to provide gas for replacement of the existing oil system. It is intended that the old boilers which are nearing the end of their life be replaced in the future under a separate contract.
3 Scope of the Project
Type of project, layout and facilities provided
A single storey extension to the southern elevation of the existing Junior School building will provide:
· four Infant classrooms
· library
· dedicated Infants entrance
· link to existing main building
· staff toilets
· male and female pupil toilets
· toy store
· cloak areas
· cleaner and caretaker's stores.
The new extension will offer covered external play areas linked to the Infant classrooms, offering shelter from rain and sun, thus allowing continued outside activities all year round.
Places provided
Following the amalgamation of the infant and junior schools the net capacity assessment for the primary school will be 540 places.
4 The Proposed Building
Type of construction, finish and appearance
The classroom and staffroom extension will be single storey. External walls are facing bricks with a shallow pitched standing seam metal roof. Windows will be aluminium polyester powder coated. It is designed to complement the most recent extensions to the school.
The roof will have a significant overhang to the glazed elevations to provide shade and covered external areas.
Accessible facilities
The new accommodation will have level access with ramps provided where necessary. An accessible toilet will be provided in the new accommodation.
Heating and ventilation systems
The extension will be served by a new gas-fired boiler independent of the existing boiler, which does not have the capacity to heat the proposals and is nearing the end of its life. Underfloor heating is proposed for the extension. Extract ventilation will be provided to the toilets.
Fire risk assessment
In consultation with the Hampshire Fire and Rescue Service, a fire risk assessment concludes that this is a low fire risk category building. Therefore a sprinkler system will not be installed.
Health and safety
A designer's risk assessment and a design health and safety plan, in accordance with Regulation 15 of the Construction Design and Management Regulations 1994, is currently being undertaken for the proposed scheme.
5 External Works
Car parking
Car parking will be located alongside the new access road to the north of the site. A total of 57 car parking spaces will be provided which includes two new disabled car parking bays.
Landscape proposals
The proposed new extension will be constructed on an area of existing play court which will be re-provided to the south west of the Junior building and will become a dedicated Junior playground. The Infant playground will be designated on an existing play area to the east of the new extension along with new play areas for reception aged pupils to the west, which will enclosed by fencing for greater security.
A new parent waiting area will be established in a space between the Infant and Junior accommodation with pedestrian links to the main site entrance.
As detailed earlier in this report the entrance and parking will be reconfigured and associated landscaping will include planting of new trees and low level shrubs to help define vehicular and pedestrian areas and to improve the frontage to the school.
New fencing and planting will be implemented along the boundary with the site designated for residential development.
Situation on site and environmental impact
The new accommodation will be positioned to the south of the existing building away from any roads. New trees and plants will be included around the site to help soften the building and enhance its setting.
6 Planning
A detailed planning application was submitted to the Director of Environment during April 2005 and the results will be known in June 2005.
7 Building management
Existing arrangements will apply to cleaning, catering, local management and maintenance arrangements.
8 Furniture and equipment
Any furniture and equipment requirements to be identified will be funded from the block vote in the Education Capital Programme.
9 Professional resources
Architectural Services } Property, Business and Regulatory
Quantity Surveying } "
Electrical and Mechanical Engineering } "
Structural Engineering } WSP
Landscape Architect } RPS
10 Consultations
The following have been consulted during the development of the project: Headteacher and Governors of the school, County Education Officer, Environment Department, Access Officer, local County Councillor, Fire and Rescue Officer.