Hampshire County Council Executive Member - Education Item 15 13 July 2005 Waterside Primary School, Hythe Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
1 |
Summary |
| |
|
1.1 |
The following decisions are sought: |
| |
|
| |
That the Executive Member for Education advises the Executive Member for Policy and Resources that approval be given to the project appraisal for the works at the Waterside Primary School at an estimated cost of up to £2,023,000, excluding fees. |
| |
|
2 |
Reason(s) |
| |
|
2.1 |
To provide a refurbished and extended Primary School and early years unit as part of the East New Forest Review of Primary Education |
2.2 |
This decision supports Aims 1 and 5 of the Corporate Strategy by providing improved facilities for all users of the school. |
| |
|
3 |
Other options considered and rejected |
| |
|
3.1 |
The need of the school for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost-effective way of meeting that need. |
| |
|
4 |
Conflicts of interest declared by the decision-maker or other Executive Member consulted |
| |
|
4.1 |
Not applicable |
| |
|
5 |
Dispensation granted by the Standards Committee |
| |
|
5.1 |
Not applicable |
| |
|
6 |
Reason(s) for the matter being dealt with if urgent |
| |
|
6.1 |
Not applicable |
Approved by: |
.......................... |
Date of decision: |
......................... |
| |
Councillor D Kirk |
|
|