Archived decisions

Hampshire County Council

Executive Member - Education Item17

13 July 2005

Major Projects Status Report

Report of the Director of Property, Business and Regulatory Services

 

How the conclusion in this report fits with the Corporate Strategy

This scheme will impact on the delivery of the following Corporate Aims

Aim 1 - maximising life opportunities - by providing new and/or improved teaching accommodation to be enjoyed by the schools.

Aim 5 - improving services - by providing good quality buildings that enable service delivery.

1. Summary

1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

1.2 Appendix 3 shows those capital projects for which an allocation has been made in the Education Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.

2. Completed Schemes

2.1 Since the May 2005 meeting of the Executive Member - Education, schemes at the following schools have been completed and the new accommodation handed over to the County Education Officer. All of these schemes remain financially on target:

    SCHOOL COMPLETION DATE

                      Hatch Warren Infant and Junior Schools April 2005

                      Nightingale Primary - Early Years Centre June 2005

                      Swanmore Secondary School April 2005

                      Whitewater Primary June 2005

3. Additional Works and Funding Added Post Contract

3.1 The following schemes have had further funding added to the contract for specific additional works.

3.2 Brookfield Community School

3.2.1 The major project at this school to undertake internal refurbishment works was approved by the Executive Member for Policy and Resources in February 2005. Additional funding of £131,000, excluding fees, has since been made available from the Schools Access Initiative budget 2005/06 and will enable various access improvement works at the school.

3.3 Droxford Junior School

3.3.1 A major scheme is currently on site at the above school to construct a new hall, kitchen and playground. The school has recently added a contribution of £40,316 for various additional items of work that can be added to the main contract. Work is due to complete during August 2005.

3.4 Portchester Community School

3.4.1 A major scheme at this school to undertake internal alterations and reorganise the reception and administration areas and improve access is due to complete during August 2005. A contribution of £25,000 has been added to this contract from the Policy and Resources NDS Condition fund 2005/06 to enable a section of re-roofing.

4. Additional Works and Funding added at Pre Contract Stage

4.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

4.2 Additional funding has come from various sources including increased Education Capital Programme allocations and inflation and tolerance adjustments; additional school funding for specific additional requested works and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.

Conclusion

    The details of the major capital projects outlined in this report will provide greatly enhanced school accommodation and facilities.

Recommendations

1. That the position of the major projects being undertaken by the Director of Property, Business and Regulatory Services be noted.

2. That the additional funding added to the major capital projects at pre contract stage, previously approved by the Executive Members' Education and Policy and Resources at design project appraisal stage, be approved.

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the act.

                    TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS

      Tender schedules

      Project Appraisals

MAJOR PROJECT STATUS REPORT Appendix 1

School

Current Status

Start

Complete

Funding/

* Contract Sum

£

Source of Funding

£

 

Alton Community Infant School

- three classroom, staff room and link corridor extension

On site

Dec 04

Sep 05

* 859,888

Education Capital 04/05 779,888

P&R NDS Condition 04/05 50,000

P&R Capital Repairs 04/05 30,000

859,888

 

Brookfield Community School, Sarisbury Green

- internal refurbishment

Contract Formation

May 05

Oct 05

958,261

Education Capital 04/05 375,000

Contingency 55,000

NDS Modernisation 05/06 78,261

NDS Condition fund 04/05 450,000

958,261

 

Brune Park Community School, Gosport

- Extension to provide a new dance studio and dining hall

On site

Jan 05

Oct 05

        * 1,264,484

Education Capital 04/05 1,116,484

School - Devolved Capital 80,000

P&R NDS Condition 04/05 50,000

Underspend from previous

phase of work 18,000

              1,264,484

 

Bursledon CE (C) Infant School

- three classroom and ancillary accommodation and removal of temporary buildings

On site

Mar 05

Sep 05

* 788,173

Education Capital 04/05 742,107

School 46,066

788,173

 

Calmore Infant School

- internal alterations to form an integrated yet independent Early Years Centre

On site

May 05

Oct 05

* 425,616

Education Capital 04/05 329,064

School 96,552

425,616

 

Chiltern Primary School, Basingstoke

- Worting School amalgamation

Enabling works

On site

Jul 04

Apr 05

Aug 04

Nov 05

* 123,475

        * 1,377,678

1,501,153

Education Capital 04/05 1,463,153

SAI 04/05 22,000

P&R NDS Condition 04/05 6,000

School 10,000

1,501,153

 

Cove Junior School, Farnborough

- three classroom extension, Music/Drama and kiln room

Tender

Sep 05

Apr 06

743,000

Education Capital 05/06 717,000

School 18,000

P&R Capital Repairs 05/06 8,000

743,000

 

The Crescent Primary School, Eastleigh

- two classroom and library extension

Tender Analysis

Jul 05

Feb 06

802,200

Education Capital 05/06 571,000

SAI 05/06 32,700

School 53,500

HC3S 20,000

P&R NDS Condition 05/06 125,000

802,200

 

Crestwood Community School, Eastleigh

- Community Sports Hall, drama studio and Fitness Suite

Tender Negotiation

Sep 05

Jun 06

2,849,000

Estimated Capital Receipt 2,902,000

School 93,000

Capital Programme 05/06 212,000

Less financial commitments -358,000

2,849,000

 

Droxford Junior School

- demolish kitchen, convert hall to classroom and construct new hall, kitchen and playground

On site

Feb 05

Aug 05

* 673,718

add 40,316

714,034

Education Capital 04/05 673,718

School 40,316

714,034

 

East Hants Special School, Bordon

- new special school

On site

May 05

Oct 06

* 5,584,472

Edu Cap / TCF 05/06 4,637,472

P&R Capital Repairs 05/06 375,000

P&R Capital Receipt 572,000

5,584,472

 

Eggars School, Alton

- IT block, Sports Hall and internal refurbishment

On site

Mar 05

Dec 05

* 2,508,232

Education Capital 03/04 1,020,000

NDS Modernisation 03/04 65,000

Treloar College Funding 288,000

School 271,232

Eggars Trust Fund 688,000

P&R NDS Fire Alarm 04/05 76,000

P&R Landlord contribution 70,000

P&R External Works 04/05 30,000

2,508,232

 

Grayshott CE (c) Primary

- single storey extension and internal alterations

Tender Preparation

Sep 05

Apr 06

525,000

Education Capital 05/06 365,000

School 160,000

525,000

 

The Henry Cort Community College, Fareham

- extension to staff room, two new offices, internal remodelling and refurbishment

Contract Formation

Jul 05

Mar 06

395,948

Education Capital 05/06 97,948

School 262,000

P&R NDS Condition 05/06 15,000

P&R Capital Repairs 05/06 2,000

P&R L'lords M. Works 05/06 12,000

P&R Ext. Landscaping 05/06 7,000

395,948

 

Hiltingbury Infant School, Chandlers Ford

- two classroom extension and remove temps

On site

Oct 04

Jul 05

* 689,201

NDS Modernisation 03/04 332,596

P&R NDS Condition 03/04 316,605

School 40,000

689,201

 

John Hunt of Everest Community school, Basingstoke

- New School and Youth facility

Contract Formation

Jul 05

Dec 06

21,612,672

Capital Receipts 13,257,896

Developer's Contribution 2,467,201

B&D Borough Council 2,110,595

County Council 3,776,980

21,612,672

 

Kings' Secondary School, Winchester

twelve classroom teaching block

On site

Nov 04

Aug 05

* 1,433,569

School 1,433,569

 

Lakeside School, Chandlers Ford

- refurb. boarding accommodation; demolish surplus boarding house; new teaching block and refurbish teaching accommodation

Enabling

Phase 1

Phase 2

Jul 04

Nov 04

Jul 05

Aug 04

Apr 05

Feb 06

* 214,472

* 453,815

1,396,713

2,065,000

Education Mod'tion 04/05 1,565,000

Education Capital 04/05 261,000

P&R NDS Condition 04/05 49,000

P&R Fire Precautions 04/05 190,000

2,065,000

 

Lanterns Children's Centre

- new Early Years Centre

On site

Jul 04

Aug 05

* 2,329,951

Education Capital 03/04 616,000

Temp C'room Hire 04/05 147,000

Capital receipts 1,441,951

Friends of Medecroft 65,000

Medecroft - Devolved capital 60,000

2,329,951

 

Minstead Rural Study Centre, Lyndhurst

- new residential building, extension to schoolhouse and removal of temps

Contract Formation

Jul 05

Mar 06

        1,180,618

Education Capital 05/06 422,414

New Opportunities Fund 515,652

Study Centre 146,552

New Forest District Council 26,000

P&R Landlords contribution 70,000

1,180,618

 

Mountbatten School and Language College

- new Staff Room, Inclusion room and Multi-agency space

Negotiation

Aug 05

Feb 06

448,000

Edu. Capital - SEED 04/05 117,000

School 331,000

448,000

 

Netley Marsh Infant

- new classrooms and extended hall

Contrct Formation

Jul 05

Dec 05

693,763

Education Capital 0506 610,832

School 62,931

P&R NDS Condition 05/06 20,000

693,763

 

Neville Lovett Community School, Fareham

- new entrance foyer and reception; refurbishment of food tech area and hearing impaired unit.

On site

Jan 05

Aug 05

* 560,000

SAI 04/05 274,700

NDS Modernisation 04/05 111,300

School 174,000

560,000

 

Nightingale Primary School, Eastleigh

- new Early Years Centre

Complete

Nov 04

Jun 05

* 755,848

NDS Modernisation 04/05 261,000

NEDA 04/05 261,000

Education contingency 04/05 48,000

Early Education 04/05 98,782

P&R NDS Condition 04/05 87,066

755,848

 

Nightingale Primary School, Eastleigh

- extension to provide permanent classroom accommodation

On site

Feb 05

Dec 05

* 1,196,477

NDS Modernisation 04/05 391,304

Contingency 55,173

Capital Receipt 646,552

School 103,448

1,196,477

 

Perins Community School, Alresford

- dance studio, fitness suite and PE classroom

On site

Jan 05

Sep 05

* 1,762,319

Education Capital 04/05 828,024

Transfer of Fees 126,795

Specialist College Status 86,000

School 371,500

P&R Capital Repairs 04/05 300,000

P&R L'lords M/Works 04/05 25,000

P&R NDS Condition 04/05 25,000

1,762,319

 

Portchester Community School

- reorganise reception and administration; internal alterations and access improvements

On site

Jul 04

Aug 05

* 767,936

add 25,000

792,936

Education SAI 04/05 413,683

Nursery School Community 18,493

HC3S 34,500

School 195,474

P&R NDS Condition 04/05 108,286

P&R M'ment Partnership 04/05 7,500

P&R Fire Precautions 04/05 15,000

792,936

         

Priestlands Secondary School, Lymington

-music/drama facility and dining extension

On site

May 05

Dec 05

* 1,615,665

Education Capital 04/05 1,069,828

School 277,000

Specialist School Status 04/05 100,000

P&R NDS Condition 05/06 20,000

Transfer of Fees 148,837

1,615,665

 

Saint Lawrence CE (C) Primary

- new hall, kitchen, link building and internal refurbishment

Tender

Aug 05

Dec 05

684,000

Education Capital 05/06 684,000

 

South Baddesley CE (C) Primary

- phase 1 - new classroom and staffroom

- phase 2 - new hall and car park

On site

Design

May 05

tbc

Oct 05

tbc

* 424,722

500,000

Education Capital 04/05 47,000

School 52,722

NDS Condition 05/06 65,000

P&R Capital 05/06 260,000

        424,722

 

Staunton Park Community

- Healthy Living Centre

On site

Jun 05

Dec 05

* 542,862

NDS Modernisation 04/05 70,862

School 50,000

Sport England 422,000

542,862

 

Testwood School, Totton

- Synthetic Turf Pitch

On site

Jun 05

Sep 05

* 473,856

Football Foundation Grant 429,356

School 44,500

473,856

 

The Toynbee Community College, Chandlers Ford

- new Multi-Purpose Suite

Design

Aug 05

Apr 06

483,000

School 266,000

P&R Capital 05/06 174,000

Eastleigh Borough Council 43,000

483,000

 

Wherwell Primary School, Andover

- extensions and internal alterations

On site

Revised dates

Aug 04

Apr 05

Feb 05

Sep 05

* 538,513

NDS Modernisation 04/05 441,959

Staff Workplaces 04/05 34,783

Temp classroom hire 04/05 9,300

School 52,471

538,513

 

Whitchurch CE (C) Primary

- two new classrooms, ICT Suite and corridor

Contract Formation

Jun 05

Nov 05

498,000

Education Capital 04/05 431,000

School 67,000

498,000

 

Whitewater Primary School, Hook

- new hall

Complete

Nov 04

Jun 05

* 424,987

Education Capital 04/05 351,000

School 60,150

P&R NDS Condition 04/05 13,837

424,987

 

SPECIALIST SCHOOLS ACCOMMODATION PROGRAMME 2005/06 Appendix 2

School

Current Status

Start

Complete

Funding / * Contract Sum

Source of Funding £

Robert Mays Secondary School

- refurbishment of science laboratories and preparation rooms

On site

May 05

Aug 05

* 373,000

NDS Modernisation 05/06 132,000

Specialist School funds 04/05 87,000

School 154,000

373,000

Mill Chase Community School

- refurbish science laboratories and food technology rooms; refurbishment to form Learning Support Unit

On site

Jun 05

Aug 05

* 425,332

NDS Modernisation 05/06 317,573

SAI 04/05 107,759

425,332

Package 1 -

    - Toynbee School

    - The Hayling School

    - Noadswood School

    - Aldworth Science College

Tender Negotiation

Design

Jul 05

Aug 05

Sep 05

Nov 05

313,000

NDS Modernisation 04/05 313,000

          Appendix 3

Other Schemes in the Education Capital Programme

The following schemes are included in the Education 2005/06 Capital Programme and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member Education or Policy and Resources:

School Allocation

        (excluding fees)

          £'000

PRIMARY

North Basingstoke schools

776

Whiteley / Western Wards

1,240

 

2,016

SPECIAL

Sundridge School, Havant

4,440

 

4,440

NDS MODERNISATION

Broughton Primary

228

Curdridge Primary

618

Micheldever Primary

1,240

Stanmore Primary

217

The Bridge Centre

830

West Tytherley Primary

811

 

3,944

   

TOTAL

10,400