Archived decisions

Hampshire County Council

Executive Member Education Item18

13 July 2005

Minor Projects - Progress Report

Report of the Director of Property, Business and Regulatory Services

Contact: Steve Clow Ext: 7858 e-mail: [email protected]

1. Summary

1.1 The purpose of this report is to provide an update of the progress made in implementing those schemes in the Education Capital Programme with a value of between £43,000 and £216,000 (exclusive of fees).

2. Current Position

2.1 The attached tables summarise the current position in relation to schemes funded by the Education 2003/04 and 2004/05 Capital Programme including Minor Works, Seed Challenge, William Price Trust, Schools Access Initiative (SAI), New Opportunities Fund (NOF) and Staff Workplaces budget. The tables provide details of the funding, a brief description of the works and a summary of the current position.

3. Education Minor Works 2005/06

3.1 Grange Junior School

    This school has been allocated £20,000, excluding fees, from the Education 2005/06 Capital Programme under Management of Falling Rolls.

    It is proposed that the funding, together with a contribution from the School of £58,621, excluding fees, will be used to provide an ITC Suite and Porch extension.


It is proposed to go out to tender during June 2005 with an estimated start date of July 2005 with completion anticipated in September 2005.

4. Education - Staff Workplaces 2005/6

4.1 Itchen Abbas Primary School, Winchester

    This school has been allocated £43,104, excluding fees, from the Education 2005/06 Capital Programme under Staff Workforce Remodelling.

    It is proposed that the funding, together with a contribution from the School of £73,276, excluding fees, and £17,242, excluding fees, from the Education School Security budget will be used to relocate the administration and Headteacher's office providing improved security and working facilities.


It is proposed to go out to tender during September 2005 with an estimated start date of October 2005 with completion anticipated in January 2006.

Recommendation

    1. That the changes to the minor works programme be approved.


      Section 100 D - Local Government Act 1972 - background papers

      The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

      NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the act.

                    TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information File, PBRS

Minor Works Capital Programme 2005/06 (* including carry forwards)

School

Funding Position £

Summary of works

Comments

Alderman Quilley School, Eastleigh

Environment - Safe Routes to

School 04/05 150,000

Relocation of school car park to new location behind Sports Hall with new access roads, footpaths and cycle ways

The Scheme has been approved by Executive Member Environment on 14 September 2004. It is proposed that works will commence on site in July 2005 with completion anticipated in October 2005.

Bordon Junior School

Capital Programme 05/06 43,103

School - Devolved Capital 60,000

P&R NDS Condition 05/06 25,000

              128,103

Entrance lobby, canopy and internal alterations to admin office.

This scheme is currently out to tender. It is proposed that works will commence on site during July 2005 with completion anticipated in October 2005.

Butts Primary School, Alton

Capital Programme 04/05 77,587

P&R Capital Repairs 20,000

School - Devolved Capital 67,242

              164,829

Extend existing building to improve administrative accommodation and provide a multi purpose teaching room.

Works are due to commence on site in July 2005 with completion anticipated in November 2005.

Hamble Primary School

Capital Programme 05/06 100,000

School - Devolved Capital 55,000

              155,000

Extension to classroom to create additional teaching space, cloak and alterations to lobby/entrance area.

It is proposed to invite tenders during September 2005 with works commencing on site in November 2005 and completion anticipated in April 2006.

Havant SEN, Havant

Capital Programme 04/05 129,000

Possible contribution to future major scheme.

May form part of capital scheme. Project currently on hold.

Hayling School, Hayling Island

Capital Programme 04/05 151,200

Landscaping works to include resurfacing, seating, planting and student seating shelter

Works commenced on site in May 2005 with completion anticipated in September 2005.

Hounsdown Secondary School, Totton

Environment - Safe Routes to

School 04/05 41,379

Safe Routes to School 05/06 62,069

School Funding 59,483

              162,931

Improvements to the entrance to the School to include a new footpath/
cycleway, a covered and secure cycle park, new access into and out of the School and alterations to the existing car park.

Subject to the approval of the Environment 2005/6 Capital Programme, it is proposed that work will commence during July 2005 with completion anticipated in October 2005.

West End Infant School, Aldershot

Capital Programme 04/5 66,087

School - Devolved Capital 125,070

              191,157

Internal alterations and entrance extension.

Work is due to commence on site in June 2005 with completion anticipated in September 2005.

Staff Workplaces 2005/06 (*including carry forwards)

School

Funding position £

Summary of Works

Comments

Connaught Secondary School, Aldershot

Capital Programme 04/05 30,000

P&R Capital Repairs 2,000

School - Devolved Capital 48,249

              80,249

Upgrade staff accommodation and male staff toilets.

Work is due to commence during July 2005 with completion expected in September 2005.

Itchen Abbas Primary School, Winchester

Capital Programme 04/05 43,104

Education - School Security 17,242

School - Devolved Capital 73,276

              133,622

Relocation of admin office and Headteacher's office to first floor to provide improved security and staff office facilities

It is proposed to invite tenders during September 2005. Works are due to commence on site in October 2005 with completion anticipated in January 2006.

Warblington Secondary School

Capital Programme 04/05 50,000

P&R NDS Condition 05/06 15,000

              65,000

Staff and admin upgrade

Work is due to commence during July 2005 with completion expected in September 2005.

SEED Challenge 2004/05 and 2005/06 (*including carry forwards)

School

Funding position £

Summary of Works

Comments

All Saints CE Junior School, Fleet

SEED 04/05 35,888

School - Devolved Capital 94,333

              130,221

To create a Continuous Professional Development Centre/workroom for all staff. In addition a group space for SEN will also be provided.

Works commenced on site during June 2005 with completion anticipated in September 2005.

Ashford Hill Primary School, Basingstoke

SEED 04/05 57,391

School - Devolved Capital 70,870

              128,261

Creation of a group room for SEN to include updating and improving administration and reception areas.

Works commenced on site in January 2005 and completed during May 2005.

Denmead Junior School, Waterlooville

SEED 04/05 57,536

School - Devolved Capital 91,164

              148,700

New ICT room.

Work commenced during May 2005 with completion anticipated in August 2005.

Dove House Special School, Basingstoke

SEED 04/05 *68,739

School - Devolved Capital 86,102

School - LMS 32,078

              186,919

Build a purpose built classroom and resource centre for severely autistic children.

Works commenced on site during July 2004 and completed during March 2005.

Durley Primary School

SEED 04/05 39,385

P&R Management Partnership 3,000

School - Devolved Capital 77,615

              120,000

Mezzanine staff room on the first floor with alterations to the ground floor to provide staff with a work area and Headteacher's office. To include new entrance lobby and waiting area.

Works commenced on site in February 2005 and completed during May 2005.

Hawley Primary School, Camberley

SEED 04/05 48,651

School - Devolved Capital 99,144

              147,795

To provide staff work area and improve staff room. To provide improved facilities for special needs and a small space for food technology. Minor pupil toilet works are also to be undertaken. Works will also include provision cookery room.

. Works commenced on site in January 2005 and completed April 2005.

Limington House School, Basingstoke

SEED 04/05 37,033

School - Devolved Capital 51,399

              88,432

Creation of tutorial areas for pupils in 14-19 age range who exhibit challenging behaviour plus a hygiene area to reflect the changing needs of the post 16 group. To include a new teaching area.

Works are due to commence on site during June 2005 with completion anticipated in September 2005.

Mark Way Special School, Andover

SEED 04/0527000

School - Devolved Capital43000

              70,000

Adaptation of garage to a teaching area for 14-19 technology. Update reception area. Provide teaching room to allow "time out"/ counselling facility.

Works commenced on site in February 2005 and completed during April 2005.

Meadowlands Infant School

SEED 04/05 36,439

School - Devolved Capital 50,685

              87,124

A comprehensive and complete redesign and redevelopment of the front area of the school to provide a dedicated staff workspace with ICT facilities.

Work commenced on site in May 2005 with completion anticipated in September 2005.

Merton Junior School, Basingstoke

SEED 04/05 50,109

School - Devolved Capital 76,942

              127,051

Improve reception area and its security. Reorganised office accommodation. To increase the size and facilities of the staff room. To create a group/tutorial space for children with SEN.

Work commenced on site during May 2005 with completion anticipated in August 2005.

New Milton Infant School

SEED 04/05 56,926

School - Devolved Capital 89,131

              146,057

Provision of SEN space and additional staff room accommodation. Construction of a corridor to bypass the hall. Provision of an adequate library and PE storage to free up space in hall area.

It is proposed that works will start on site during July 2005 with completion anticipated in October 2005.

Riverside Community Special School, Waterlooville

SEED 04/05 57,955

School - Devolved Capital 76,539

              134,494

Teaching and learning resources/training area and multi-sensory room development.

Tenders were invited in February 2005. Works commenced on site in May 2005 with completion anticipated in August 2005.

St Thomas' Infant School

SEED 04/05 50,018

School - Devolved Capital 84,145

              134,163

To create a new administration office and staff work room. To create a new SEN room for group work.

Tenders were invited during March 2005. Works commenced on site in April 2005 with completion anticipated in August 2005.

Wallisdean Junior School, Fareham

SEED 04/05 42,434

School - Devolved Capital 57,888

              100,322

Build a new staff room freeing up space to be developed as an ICT suite/ meeting room.

It is proposed to invite tenders in May 2005. Works are due to commence on site in June 2005 with completion anticipated in August 2005.

Westfields Junior School, Yateley

SEED 04/05 52,240

School - Devolved Capital 58,760

              111,000

Alterations to toilets and alterations to provide food technology, ICT and space for SEN.

Tenders were invited in June 2005. Works are due to commence on site in July 2005 with completion anticipated in September 2005.

Woodlea Primary School, Bordon

SEED 04/05 51,739

School - Devolved Capital 58,190

P&R Capital Repairs 04/05 10,000

              119,929

Extension to existing Year R classroom and inclusion of two WC's to make area self contained. Development of outside play space currently shared with Year 1 and 2.

This scheme has been negotiated with Gregory's following approval at July 2004 Executive Member Policy and Resources. Works commenced on site during November 2004 and completed in May 2005.

Schools Access Initiative (SAI) / Disability Discrimination Act (DDA) 2005/06 (*including carry forwards)

School

Funding Position £

Summary of Works

Comments

Abbottswood Junior School, Totton

Capital Programme 04/05 60,058

Capital Programme 05/06 40,870

              100,928

Hygiene room and WC modifications and level access

The Hygiene Room and modifications to the toilets are complete. The level access works will commence on site in July 2005 with completion anticipated in August 2005.

Cheriton Primary School, Alresford

Capital Programme 04/05 52,174

School - Devolved Capital 39,060

              91,234

New office extension and SEN Room.

Work commenced during November 2004 and completed during April 2005.

Frogmore Community School, Yateley

Capital Programme 04/05 69,565

Toilet upgrade and physio rooms with ramp access.

Feasibility/design underway and programme being agreed.

Guillemont Junior School, Farnborough

Capital Programme 05/06 56,304

Accessible WC and ramp access across site

Works will commence on site in July 2005 and completion anticipated in August 2005. Ramp access works may form part of framework agreement.

Horndean Junior School, Waterlooville

Capital Programme 04/05 63,930

School - Devolved Capital 9,500

              73,430

Accessible WC and alterations to girls WC and alterations to provide level access

Due to the high value of tenders returned, this scheme is being revised and will be re-tendered in the near future.

Kings School, Winchester

Capital Programme 05/06 52,174

Internal lift access

Feasibility/design underway and programme being agreed.

Olivers Battery Primary School, Winchester

Capital Programme 04/05 27,200

School - Devolved Capital 33,000

P&R Management Partnership 6,000

              66,200

Creation of a hygiene room, refurbishment of the toilets and ramp access on site.

Works commenced on site in January 2005 and completed April 2005.

Portchester Community School, Portchester

Capital Programme 04/05 48,160

P&R NDS Condition Fund 04/05 83,286

              131,446

Proposed canopy/covered entrance for drop off and pick up of physically disabled pupils

This scheme has been successfully negotiated with Brymor Contractors who are undertaking other SAI works and recladding at the School. Work commenced during March 2005 and completed during April 2005.

Ringwood Infant School, Ringwood

Capital Programme 05/06 56,522

Internal access and modifications to WC's

It is proposed to invite tenders during September 2005 with works commencing on site in October 2005 and completion anticipated in February 2006.

Ringwood Junior School, Ringwood

Capital Programme 04/05 119,883

School - Devolved Capital 41,200

              161,083

Access and therapy extension and internal alterations to the staff room

Tenders were invited during September 2004. Works are due to commence on site January 2005 and completed April 2005.

Siskin Junior School, Gosport

Capital Programme 04/05 50,000

Capital Programme 05/06 25,478

              75,478

Accessible WC and adaptation to staff WC, Medical room and stores

It is proposed to invite tenders during March 2005 with works commencing on site in June 2005 with completion anticipated in September 2005.

Uplands Primary School, Fareham

Capital Programme 04/05 54,957

External access and internal platform lift

Phase1 of the works completed in September 2004. Phase 2 of the works include providing access around the site. Work commenced on site in May 2005 with completion anticipated in June/July 2005.

Weyford Infant School

Capital Programme 05/06 70,174

Ramps, accessible WC and platform lift

Works will commence on site in July 2005 with completion anticipated in August 2005. Ramps may form part of framework agreement.

Wildern Secondary School, Hedge End

Capital Programme 05/06 58,522

Alarm system for HI, modifications to WC's and level access

Feasibility/design underway and programme being agreed.

Wyvern Technology College, Fair Oak

Capital Programme 05/06 108,696

Accessibility and internal modifications

Feasibility/design underway and programme being agreed.

William Price Trust 2005/06 (*including carry forwards )

School

Funding Position £

Summary of Works

Comments

Oak Meadow Early Years Centre, Fareham

Capital Programme 05/06 * 127,826

Internal alterations to form additional meeting areas, creation of new external entrance, provide staff room, kitchen and storage areas. Also formation of car park with 25 spaces including some accessible spaces, new footpath, entrance and external storage shed.

A programme of works has now been agreed with the school. This scheme is currently out to tender. It is proposed that works will commence on site in June 2005 with completion anticipated in December 2005.

New Opportunities Fund (NOF) - 2005/06 (*including carry forwards)

School

Funding Position £

Summary of Works

Comments

Bridgemary Community School, Gosport

NOF 05/06 *156,000

School - Devolved Capital 30,000

186,000

Multi Use Games Area (MUGA)

Works are due to commence on site in June 2005 with completion anticipated in September 2005.

Cowplain Secondary School, Waterlooville

NOF 05/06 *156,000

School - Devolved Capital 30,000

186,000

Multi Use Games Area (MUGA)

Works are due to commence on site in July 2005 with completion anticipated in December 2005.

Park Community School, Havant

NOF 05/06 *156,000

School - Devolved Capital 30,000

186,000

Multi Use Games Area (MUGA)

Works are due to commence on site in June 2005 with completion anticipated in September 2005.

Siskin Junior School, Gosport

NOF 04/05 85,000

Gosport Borough Council 50,200

School - Devolved Capital 20,000

P&R External Works 15,000

Surestart Funding 38,000

              208,200

Multi Use Games Area (MUGA) and playground improvement works

Works are due to commence on site in August 2005 with completion anticipated in November 2005.

Specialist School College Status Allocations 2004/05 (including carry forwards)

School

Funding Position £

Summary of Works

Comments

Alderman Quilley Secondary School, Eastleigh

Capital Programme 04/0587,000

School funding tbc

Specialist school allocation (Engineering)

Feasibility/design underway and programme being agreed.

Amery Hill Secondary School, Alton

Capital Programme 04/0587,000

School funding tbc

Specialist school allocation (Music)

Feasibility/design underway and programme being agreed.

Bay House Secondary School, Gosport

Capital Programme 04/0587,000

School funding tbc

Specialist school allocation

This work will form part of the major capital scheme being undertaken at the school.

Crestwood College for Business and Enterprise, Eastleigh

Capital Programme 04/05 105,000

School funding tbc

Specialist school allocation

Feasibility/design underway and programme being agreed.

Eggars Community School, Alton

Capital Programme 04/0587,000

School funding tbc

Specialist school allocation

Feasibility/design underway and programme being agreed.

John Hanson School, Andover

Capital Programme 04/0587,000

School funding tbc

Specialist school allocation

(Science)

Feasibility/design underway and programme being agreed.

The Petersfield School, Petersfield

Capital Programme 04/0587,000

School funding tbc

Specialist school allocation (Sports)

Feasibility/design underway and programme being agreed.

Priestlands Secondary School, Lymington

Capital Programme 04/0587,000

School funding tbc

Specialist school allocation (Arts)

Feasibility/design underway and programme being agreed.

Testwood Secondary School, Totton

Capital Programme 04/0587,000

School funding tbc

Specialist school allocation (Arts)

Feasibility/design underway and programme being agreed.

NDS Modernisation Programme 2005/6 - Schools Specialist Accommodation Programme

School

Funding Position £

Summary of Works

Comments

Brune Park Secondary School, Gosport

Capital Programme 04/05 87,000

School funding tbc

Specialist school allocation

Feasibility/design underway and programme being agreed.

Court Moor Secondary School, Fleet

Capital Programme 04/05 87,000

Capital Programme 05/06 87,000

School Funding 52,900

              226,900

4 No. Science Lab refurbishments

Work commenced on site during March 2005 with completion anticipated during June 2005. It is hoped to negotiate the refurbishment of the additional two science laboratories with Nolan Davis who are currently on site.

Cowplain Secondary School

Capital Programme 05/06 50,000

1 No. Science lab refurbishment

Feasibility/design underway and programme being agreed.

Frogmore Community School, Yateley

Capital Programme 04/05 87,000

School - Devolved Capital 101,724

              187,724

Food technology and textiles refurbishment

Works will commence on site during June 2005 with completion anticipated in August 2005.

Hamble Community Sports College, Hamble

Capital Programme 05/06132,174

School funding 38,000

170,174

2 No. science lab refurbishments and new external fire escape stair

This scheme is to be successfully negotiated with Nolan Davis Contracting. It is proposed that works will commence on site in July 2005 with completion anticipated in September 2005.

The Mountbatten School, Romsey

Capital Programme 05/06 67,000

School funding 19,000

86,000

1 No. science lab refurbishment

This scheme is to be successfully negotiated with the contractor awarded the Recladding Works. It is proposed that works will start on site in July 2005 with completion anticipated in August 2005.

Portchester Community School

Capital Programme 05/06 87,000

2 No. science lab refurbishment

Feasibility/design underway and programme being agreed.

Test Valley Secondary School

Capital Programme 05/06 50,000

1 No. science lab refurbishment

Feasibility/design underway and programme being agreed.

Learning Skills Council 2004/05

School

Funding Position £

Summary of Works

Comments

Mill Chase Community School, Bordon

Learning Skills Council 52,000

NDS Modernisation 2004/05

Secondary Schools 14-19 Agenda 68,000

              120,000

Formation of a Catering/Training Kitchen

This scheme was successfully negotiated with Nolan Davis Contracting Limited. Work commenced on site on April 2005 and was completed during May 2005.