Corporate Procurement - Progress Report

Report by the Director of Property, Business and Regulatory Services

Contact: Neil Jones Ext: 6180 e-mail: [email protected]

1

Summary

   

1.1

The following decisions are sought:

 

That approval be given to:

 

(i) the progress being made to embedding procurement efficiencies in the 2005/06 budget;

    (ii) a further report being produced for the Buildings, Land and Procurement Panel on how procurement efficiencies could be realised in 2006/07 and 2007/08.

(iii) The Director of Property, Business and Regulatory Services being authorised to conclude new contract arrangements for the supply of electricity to a range of large sites commencing November 2005.

2

Reason(s)

2.1

To enable continuing progress to be made on corporate procurement initiatives across the County council and to meet the efficiency agenda created through Gershon.

2.2

This decision supports Aims 5 and 6 of the Corporate Strategy by promoting a strategic approach to procurement and developing procurement skills and capacity within the authority.

   

3

Other options considered and rejected

   

3.1

None

4

Conflicts of interest declared by the decision-maker or other Executive Member consulted

   

4.1

Not applicable

 

5

Dispensation granted by the Standards Committee

   

5.1

Not applicable

   

6

Reason(s) for the matter being dealt with if urgent

   

6.1

Not applicable