EXECUTIVE MEMBER FOR ENVIRONMENT : NORTH HAMPSHIRE
AND SPATIAL STRATEGY DECISION DAY
TUESDAY 26 JULY 2005 AT 9.00 AM
CHUTE ROOM, ELIZABETH II COURT, THE CASTLE, WINCHESTER
AGENDA
A. KEY DECISIONS
None
B. NON-KEY DECISIONS
1. PROJECT APPRAISAL : BASINGSTOKE ROUTE 3 QUALITY BUS PARTNERSHIP - INFRASTRUCTURE AND INFORMATION IMPROVEMENTS (Report herewith)
To consider the report of the Director of Environment and appended project appraisal for infrastructure and information improvements along service 3 in the Basingstoke area, to improve stop access and waiting facilities and install real-time passenger information at key stops as part of the Basingstoke Quality Bus Partnership, at an estimated cost of £200,000.
2. PROJECT APPRAISAL : ALDERSHOT TO YATELEY ROUTE 3 QUALITY BUS PARTNERSHIP - INFRASTRUCTURE AND INFORMATION IMPROVEMENTS (Report herewith)
To consider the report of the Director of Environment and appended project appraisal for infrastructure improvements to enhance Aldershot - Yateley Route 3 under the umbrella Blackwater Valley Quality Bus Partnership with Surrey County Council, Bracknell Forest Borough Council, Wokingham District Council and Stagecoach, at an estimated cost of £200,000.
3. PROJECT APPRAISAL : FARNBOROUGH ROUTE 6 QUALITY BUS PARTNERSHIP - INFRASTRUCTURE AND INFORMATION IMPROVEMENTS PHASE 2 (Report herewith)
To consider the report of the Director of Environment and appended project appraisal on the second stage of bus infrastructure improvements along Service 6 in the Farnborough area, including the provision of new bus shelters, the installation of real-time passenger information at key stops and two electronic information kiosks, at an estimated cost of £100,000.
4. PROJECT APPRAISAL : A343 NEWBURY ROAD, ANDOVER (Report herewith)
To consider the report of the Director of Environment and appended project appraisal for the installation of a puffin crossing, the construction of new footway links and the relocation of bus lay-bys/stops on the A343 Newbury Road, close to Enham Arch Andover to be externally funded at an estimated cost of £155,000.
5. SOUTH EAST DORSET SUB-REGIONAL STRATEGY
(Report herewith)
To consider the report of the Director of Environment which examines the content and implications for long term planning and transportation in Hampshire of the emergent Spatial Strategy for the South East Dorset Sub-Region.