Archived decisions
Funding form 5
Bids for funding from Hampshire County Council to support district LSP's
Name of LSP |
Basingstoke and Deane LSP | |
Contact Name |
Glyn Williams Head of Policy and Partnerships Basingstoke & Deane BC (01256 845794) | |
Amount Requested |
£11,000 | |
Summary of Bid (Details of proposed activity the money will be spent on) |
The funds are for the County Council's agreed contribution towards the cost of the LSP operating costs. | |
Timescale (anticipated period over which the money will be spent) |
The money will be spent over the current financial year - April 2005 to 31 March 2006 towards the operating costs of the LSP which includes the LSP Manager. | |
How does this bid support the targets within the Community Strategy? |
The LSP Manager ensures that the work of the LSP is co-ordinated and helps to ensure that the targets within the community strategy are delivered by partners. | |
Overall funding arrangements (please specify total cost of project and the amounts contributed from other partners) |
The total annual LSP costs are £85,000 of which the LSP operating costs are £45,000 and the Project costs are £40,000. The funding for the operating costs has been divided between partners as follows: BDBC - £22.5K HCC - £11K Housing Partnership Board - £2.3k Learning Consortium - £2.3k Community Safety Forum - £2.3k Health Partnership - £2.3k Local Business Partnership - £2.3k | |
Signed (by Chair of LSP or on behalf of) |
Glyn Williams |
Date |
Amount Agreed |
||
Signed (By HCC authority) |
Date | |
For further information or queries please contact:
Jo White Tel: 01962 845004 E-mail: [email protected]