Archived decisions

Hampshire County Council

Rushmoor Highway and Transport Advisory Panel

7 October 2005

Travel Plan Programmes

Report of the Director of Environment

Item 10

Contact: Jon Foley, ext 7559 email: [email protected]

1. Summary

1.1 This report provides a progress update on the workplace and school travel planning programmes in the Rushmoor area, together with information on a recently completed county-wide personalised travel planning project. It also includes an update on the Safer Routes to School programme for schemes within the Rushmoor area.

2. Workplace Travel Plan Programme

2.1 There are currently 15 organisations developing a travel plan, compared to nine reported to the last Panel meeting in March 2005.

2.2 The current status of travel plans in the Rushmoor area is shown in the table below. An indication of the number of employees covered by the plans has also been given. Individual organisations are not identified for reasons of confidentiality - for example some travel plans are related to planning applications or a change in location that is not yet public knowledge.

    Travel Plan Level

    Number of businesses

    Number of employees*

    0 - Has an interest in travel and transport issues but no plan being produced

    0

     

    1 - Framework travel plan produced (often planning related), inception meeting held or some measures have been implemented

    10

    2996

    2 - Draft travel plan produced and approved by HCC

    4

    1400

    3 - Full travel plan produced and approved by HCC. Measures being implemented and reviewed.

    1

    300

      * this is an approximation. Not all employee data is yet complete

2.3 The Travel Plan Adviser is currently working to update records by liaising more closely with District Council officers to provide a more complete picture of travel plan activity.

      Travel Plan Partnership Fund 2005/06

2.4 In June 2005 the Executive Member for Environment: South Hampshire and Resource Management approved a £36,900 capital and £9,280 revenue county-wide allocation to allow this fund to be run for a second year. This fund provides up to 50% match funding to support businesses in providing on-site facilities to support the development of their travel plan. This could include, for example, secure cycle parking, marking out of car share bays, provision of information displays and the production of bespoke travel information.

2.5 No businesses in the Rushmoor area submitted a bid for funding for this financial year.

3. School Travel Plan Programme

3.1 The School Travel Planning Team continue to work with schools to develop School Travel Plans. To date over 405 schools throughout Hampshire have developed or are in the process of developing plans compared with just over 330 as at March 2005.

3.2 The School Travel Planning Team has been funded since April 2004 through a central Government grant (£165,000 per annum). Originally this funding was due to come to an end in March 2006, however the County Council is pleased to report that the funding has now been extended to March 2008.

3.3 Schools with travel plans approved by the School Travel Planning Team are eligible for funding through the Safer Routes to School programme, as well as a one-off capital grant from the Department for Education and Skills (DfES). The latter is only available to state schools. In 2004 83 schools received a total of £532,309 from the DfES; in 2005 71 schools were put forward and received grants totalling £402,597 from the DfES.

3.4 The team works closely with Borough Council officers and is now engaged with 32 of the 41 schools in the Rushmoor area (39 maintained and two independent), compared with 31 schools as at March 2005. A summary of the current status of all School Travel Plans in the Rushmoor area is shown as a table below. More detail is shown in the appendix.

    Travel Plan Level

    Number of schools

    Level 0 - Interest shown

    9

    Level 1 - Initial work on travel plan started

    8

    Level 2 - Draft travel plan completed

    4

    Level 3 - Final travel plan submitted and approved

    11

    C- Contacted, awaiting response

    9

4. Safer Routes to School Programme

4.1 The Safer Routes to School programme links very closely with the development of the School Travel Plan programme. One of the objectives of a School Travel Plan is to encourage as many children as possible to be active and independent by walking, cycling or using public transport to get to and from school on a regular basis. This could be through a combination of physical and other measures. If physical works are identified within the approved School Travel Plan then the school can bid for funding from the Safer Routes to School programme.

4.2 On 21 January 2005 the former Executive Member for Environment agreed an indicative allocation of £1.5 million for a county-wide programme of Safer Routes to School schemes from the 2005/06 Capital Programme.

4.3 When a proposal for highway improvements is received from a school with a completed School Travel Plan, the feasibility is assessed to determine the scale, implications, costs and benefits. As more proposals come forward, this allows the priorities to be determined for inclusion in the programme. The current status of potential and actual schemes is shown in the appendix.

5. Personalised Travel Planning Programme

5.1 The County Council recently (March 2005) completed a large scale personalised travel planning project called `InfoMotion'. This direct marketing project (the largest of its kind in the UK), which included close partnership working with local bus operators, targeted some 115,000 households within walking distance of high quality bus services across Hampshire.

5.2 Personalised travel planning is a process whereby individuals (either householders, employees or visitors) are provided with tailored travel advice and information based on an understanding of their personal trip requirements. It can, as in the case of the InfoMotion project, also be complemented by the provision of incentives (eg trial season tickets) to introduce people to a new mode of travel that they may not have otherwise considered.

5.3 Of the 115,000 households contacted 38,000 responded. Of these 19% (7,720 households) were already regular uses of public transport (and so did not participate further), 48% (18,240 households) were infrequent users of public transport who were interested in participating and 33% (12,540 households) were not interested in participating. Through a process of one to one dialogue the `interested' group as subsequently provided with tailored information and incentives to encourage greater bus use.

5.4 Monitoring of local bus patronage and participants' travel behaviour was undertaken. Bus patronage in one area of the county increased by 6% (peaking at 11% during the marketing period) while in another area of the county the monitoring found that there had been a 21% increase in person trips by bus and a 9% reduction in person trips by car by those participating. The results from the travel behaviour element of the monitoring also showed that there had been a reduction, from 31% to 17%, in the proportion of people dissatisfied with local bus services.

5.5 The project therefore highlighted the effectiveness of personalised travel planning not only in changing travel behaviour but also influencing individual's perceptions of public transport. The County Council will now consider the future role of personalised travel planning within the delivery of its Local Transport Plan.

6. Impact Assessments

6.1 This report provides a position statement only, therefore an impact assessment in terms of the Race Relations (Amendment) Act has not been undertaken.

Recommendation

That Members note the progress made with the delivery of the workplace and School

Travel Plans and Safer Routes to School programmes in the Rushmoor area, together with the outcomes of the recent InfoMotion personalised travel planning project.

Section 100 D - Local Government Act 1972 - background papers

 

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

 

NB the list excludes:

 

1.

Published works.

 

2.

Documents which disclose exempt or confidential information as defined in the Act.

TITLE

LOCATION

None

 

552/JF

APPENDIX

Rushmoor Highway and Transport Advisory Panel

School Travel Plan levels as at August 2005

School Name

School Travel Plan Level

Date level achieved

SRTS scheme

SRTS Scheme year

SRTS Allocation £000's

Infant

         

Belle Vue Infant School, Aldershot

    1

    07/12/2004

     

Cove Infant School, Cove

    C

       

Farnborough Grange Nursery/Infant School and Early Years Centre, Farnborough

    1

    09/11/2004

    Entrance improvements

    2002/03

7

Manor Infant School, Cove

    3

    29/03/2004

    To be considered for funding in 2006/07

   

Marlborough Infant School, Aldershot

    0

    19/11/2004

     

North Farnborough Infant School, Farnborough

    2

    01/10/2004

     

Parsonage Farm Nursery and Infant School, Farnborough

    3

    01/09/2001

    Pedestrian crossing facilities and footway improvements

    2001/02

40

Pinewood Infant School, Farnborough

    3

    01/04/2004

    Pedestrian crossing facilities and footway improvements

    2001/02

40

South Farnborough Infant School, Farnborough

    3

    20/11/2003

    Traffic calming scheme on Queens Road - joint scheme including St Marks Primary and Linden Education Centre

    2004/05

200

Southwood Infant School, Cove

    0 (C)

    10/02/2005

     

St Michael's C E (Controlled) Infant School, Aldershot

    0

    07/12/2004

     

Talavera Infant School, Aldershot

    0

    18/11/2004

     

West End Infant School, Aldershot

    1 (0)

    14/11/2002

     
           

Junior

         

Beaumont Junior School, Aldershot

    C

       

Cove Junior School

    3

    01/10/2002

    Pedestrian improvements

    2003/04

16

Grange Community Junior School, Farnborough

    2

    23/11/2004

     

Guillemont Junior School, Farnborough

    3 (2)

    15/07/2004

    Cycle Shelters

    Pedestrian crossing facilities and footway improvements

    2004/05

    2001/02

5

40

Manor Junior School, Cove

    3

    29/03/2004

    See Manor Infant School

   

Newport Junior School, Aldershot

    1 (0)

    05/11/2004

     

South Farnborough Junior School, Farnborough

    0

    01/12/2004

     

St Michael's C E (Controlled) Junior School, Aldershot

    0

    18/11/2004

     

St Peter's C E (Aided) Junior School, Farnborough

    C

       

Talavera Junior School, Aldershot

    0

    01/12/2004

     
           

Primary

         

Cherrywood Community Primary School, Farnborough

    C

       

Fernhill Primary School, Farnborough

    C

 

    School Crossing Patrol works

    2004/05

tbc

Park Primary School, Aldershot

    2

    13/09/2004

     

St Bernadette Catholic Primary School, Cove

    1 (0)

    01/11/2004

     

St Joseph's Catholic Primary School, Aldershot

    3

    01/11/2003

    SRTS measures including improvements for pedestrians, signing and lining.

    2004/05

60

St Mark's C E (Aided) Primary School, Farnborough

    3

    01/03/2004

    See South Farnborough Infant School

   

School Name

School Travel Plan Level

Date level achieved

SRTS scheme

SRTS Scheme year

SRTS Allocation £000's

St Patrick's Catholic Voluntary Aided Primary School, Farnborough

    1

    13/11/2002

     

Tower Hill Community School, Cove

    2

    01/10/2004

     
           

Secondary

         

Cove School

    1

    18/11/2004

     

Fernhill School, Farnborough

    3

    01/09/2002

    Awaiting updated STP

   

Oak Farm Community School, Cove

    0

    06/12/2004

     

The Connaught School, Aldershot

    0

    01/11/2003

     

The Wavell School, Farnborough

    C

       
           

Special

         

Henry Tyndale School, Farnborough

    1

    12/11/2004

     

The Samuel Cody School, Farnborough

    C

       

The Linden Education Centre, Farnborough

    3

    30/03/2004

    See South Farnborough Infant School

   
           

Independent

         

Farnborough Hill, Farnborough

    C

       

Salesian College, Farnborough

    C

       

Key:

0 Interest shown 2 Draft travel plan completed

1 Initial work on travel plan started 3 Final travel plan submitted and approved

C Contacted, awaiting response

() School Travel Plan Level at time of last HTAP. No change to level if not shown.