WORKS |
CONTRACTOR(S) |
VALUE |
SELECTION METHOD |
REASON FOR PROCUREMENT STRATEGY |
PROJECTS NOW ALLOCATED TO THE FRAMEWORK ARRANGEMENTS |
Havant ESC |
To be confirmed |
|
|
|
Havant EBD |
Balfour Beatty |
£4,770,000 |
Direct appointment through Major Framework call off arrangement |
· Good performance on the Enhance projects · Extensive experience of Education sector · Involvement of additional framework contractor in education projects · Good local knowledge following Malmesbury Lawn · Contractor to review scheme design prior to construction |
Whitely 1FE Primary School |
Brazier |
£3,500,000 |
Direct appointment through Major Framework call off arrangement |
· Good performance on the Enhance projects and NOF Sports Halls · Contractor to assist with development of common design approach for programme of new primary schools · Involved with developing common design approach to Enhance schemes |
PROJECTS CURRENTLY UNDER DESIGN DEVELOPMENT |
Education Capital |
|
|
|
|
Dowd's Farm - new 1FE primary |
HBG |
£3,000,000 |
Direct appointment through Major Framework call off arrangement |
· Good performance on the Enhance projects and number of education schemes · Contractor to assist with developing common design approach for large programme of new primary schools · Collaboration over key supply chains and procurement |
King's Copse - new 1FE primary |
HBG |
£3,000,000 |
Direct appointment through Major Framework call off arrangement · |
Pinewood Infant School - replacement 1FE infant school |
Brazier |
£3,000,000 |
Direct appointment through Major Framework call off arrangement |
· Good performance on the Enhance projects and NOF Sports Halls · Contractor to assist with development of common design approach for programme of new primary schools · Involved with developing common design approach to Enhance schemes |
Costello Technology College New Technology & Maths Block |
HBG Construction Ltd |
£5,500,000 |
Direct appointment through Major Framework call off arrangements |
· Contractor successfully completed similar scheme at Wildern School. · Programme, planning and execution of the advance works including piling and ground clearance. · Phasing and construction strategy for complex inner city project. · Early involvement of major contractor required due to scale and complexity of project. · Collaborate over procurement and selection of key supply chains |
Waterside Primary School New 1 FE Primary School (on existing Junior site) |
Mansell Construction Services Ltd |
£1,970,000 |
Direct appointment through Major Framework call off arrangements |
· Contractor has considerable experience of HCC Education schemes · Good performance on previous projects · Involvement of previous contractor team with established supply chains · Early contractor involvement required due to complexity of schemes and to engage in planning and programming of the works |
Holbury Primary School New 2 FE Primary School (on existing Junior site) |
Mansell Construction Services Ltd |
£1,800,000 · |
John Hunt of Everest |
Wates |
£22,000,000 |
Best Value selection based on submissions from four Framework Contractors |
· Major project requiring a collaborative partnership approach · Engage with contractor over planning, programming and scheme development |
Recreation and Heritage |
|
|
|
|
Winchester Cultural Centre |
Mansells |
£5,625, 000 |
Best value selection based on submissions from two framework contractors |
· Programming, planning and execution of the advance works including piling and ground clearance. · Phasing and construction strategy for complex inner city project. · Early involvement of major contractor required due to the scale and complexity of project · Collaborate over procurement and selection of key supply chains |
Other |
|
|
|
· |
Ashburton Court Redevelopment |
To be confirmed |
|
One of three contractors to be selected on basis of best value evaluation of submission |
· Early involvement of major contractor required due to scale and complexity of the scheme. · Phasing and construction strategy for complex inner city project. |
CONTRACTS AWARDED SINCE APRIL 2005 |
Minstead Rural Studies Centre |
Mowlem |
£1,155,000 |
Direct appointment through Major Framework call off arrangements |
· Pre contract contractor involvement required in terms of design development work , programming planning · Good local knowledge required for resolution of local supplier sources to meet sustainable construction brief |
Eastleigh Crestwood Community School Sports and Drama Development |
Brazier |
£3,051,951 |
Direct appointment through Major Framework call off arrangements |
· Similarity with NOF developments by same major contractor · Contractor able to provide resource to support design development · Utilise same construction and supply approach as used for the NOF sports halls · Key main contractor team who successfully undertook NOF developments · Early major contractor involvement |
Tatchbury Mount |
HBG |
£6,450,000 |
Continuation with same contractors following good performance on prior phase of the Enhance project |
· Continuity of team · Continuity of supply chains · Continuous improvement through further involvement · Secure resources to complete the instructions |
John Hunt of Everest - enabling works |
Wates |
£1,106,415 |
Continuity with arrangements for the construction of the replacement school |
· Contractor has been involved in design development of scheme · Continuity with main contract |
Lakeside School Extension and improvements - Phase 2 |
Wates |
£1,301,254 |
Continuity with earlier phases of work |
· Contractor has undertaken phase 1 of the works · Collaborate with the selected framework contractor over design and programming of the works · Early involvement of a contractor in resolving complex phasing issues and dealing with site health and safety issues |
East Hampshire Special School |
Mowlem |
£6,088,638 |
Best value selection based on submissions from two framework contractors |
· Early involvement of major contractor required due to scale and complexity of project. · Programming and advance works to be undertaken · Collaborative over procurement and selection of key supply chains |