1. Summary
1.1 On 8 September the River Hamble Harbour Board approved the proposals for Eastlands Boatyard and Universal Marina, subject to the views of the Management Committee. On 10 October 2005 the River Hamble Harbour Management Committee recommended approval of planning consents for Eastlands Boatyard, Universal Marina and Riverside Boatyard (Foulkes Boatyard). The proposal for Riverside Boatyard (Foulkes Boatyard) has not yet been before the River Hamble Harbour Board. Therefore this proposal is now submitted.
2. Corporate Strategy
2.1 These decisions support Aims 1 to 5 of the Corporate Strategy (Maximising Life Opportunities, Stewardship of the Environment, Achieving Economic Prosperity, Building Strong and Safe Communities, and Improving Services) by contributing to the statutory duties entailed in the management of the River Hamble.
3. Designated Sites and the Harbour Authority's Responsibilities
3.1 The River Hamble Harbour Authority is a Relevant Authority under The Conservation (Natural Habitats, & c) Regulations 1994, commonly known as the Habitats Regulations. As a Relevant Authority the Harbour Authority therefore has a duty to secure compliance with the requirements of the Habitats Directive and to ensure that in the exercise of any of its powers or functions it will have regard to both direct and indirect effects on the interest features of the European Marine Site.
3.2 The River Hamble is part of the Solent European Marine Site and is afforded protection due to its international nature conservation value. The majority of the Hamble estuary East and West banks fall within the Solent and Southampton Water Special Protection Area (SPA) and Ramsar site. The whole river is within the Solent Maritime Special Area of Conservation (SAC).
3.3 As a section 28G authority under the Wildlife and Countryside Act 1981 (as amended by the Countryside and Rights of Way Act 2000), The River Hamble Harbour Authority has a duty to take reasonable steps, consistent with the proper exercise of the authority's functions, to further the conservation and enhancement of the flora, fauna or geological or physiographical features by reason of which the site is of special scientific interest.
3.4 Consent may be granted by the River Hamble Harbour Board permitting harbour works in the navigation of the River Hamble to accord with Section 10 of the Southampton Harbour Act 1924 and Section 48 of the Southampton Harbour Act 1949, as amended by the River Hamble Harbour Revision Orders 1969 to 1989. Within the River Hamble Harbour Board's statutory duties lies the responsibility to ensure that all matters concerning navigational safety are addressed. This area of responsibility includes the proposed development for Riverside Boatyard which is set out in the attached appendix.
4. Impact Assessments
4.1 The installations of walk ashore berths, provision of full services and improved decking will produce improved opportunities for handicapped sailors at Riverside Boatyard.
Recommendation
Riverside Boatyard (Foulkes Boatyard)
Details of this proposal are attached in the appendix. The recommendation is:
That the River Hamble Harbour Board supports this revised proposal allowing Riverside Boatyard (Foulkes Boatyard) to proceed with the proposed plans to refurbish its boatyard as set out on Drawing Number M2802/014 Title: Foulkes Boatyard Pontoon Layout Existing/Revised Proposal; Scale 1:1000. Should conditional consent be granted, it is recommended to include as part of any consent the following conditions, that:
(i) copies of all other consents required for this project be produced to the Harbour Master before proceeding with the works;
(ii) the number of boats moored within the curtilage of Riverside Boatyard (Foulkes Boatyard) is not increased beyond the current allocation of vessels;
(iii) the developer produces to the Harbour Master, before proceeding with the works, a method statement to include:
(a) start and completion dates of the works;
(b) disposal plan for obsolete pontooning and floats;
(c) type of pile driving, percussion or vibro;
(d) proposed location of any displaced vessels during the works;
(e) all sinkers, ground chain, risers and mooring buoys made redundant by the modernisation are removed from the bed of the river and disposal plans are produced to the Harbour Master.;
(f) two fixed red vertical navigation lights to be established and maintained by the marina (Riverside Boatyard (Foulkes Boatyard)) on the furthest upstream and downstream outer pontoons; and
(g) any lighting established on the pontoon system must be off a type that does not interfere with safe navigation; and
(iv) the developer is to adhere to the approved method statement throughout the process. Major amendments will not be permitted and minor amendments must have the prior written approval of the Harbour Master.
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
None. |
623A/TC
APPENDIX
Riverside Boatyard (Foulkes Boatyard)
1. Riverside Boatyard (Foulkes Marina) has applied for conditional Harbour Authority consent to modernise the moorings which are located directly downstream of the M27 road bridge.
2. Conditional consent to construct new pontoons, repair existing pontoons and also remove existing pontoons was granted by the Executive Member for the Environment at a Decision Making Meeting on the 2 April 2003. There has been a considerable period between consent being granted and this new plan being put foreword for consent. This has arisen because of consultations with English Nature, The Environment Agency and Eastleigh Borough Council regarding the condition of the site and deciding on the best long term plans for the site.
3. Following consultations both with English Nature and Eastleigh Borough Council it was English Nature's opinion that:
"The proposal is not likely to have a significant effect on the interest features of the European sites and therefore does not require an appropriate assessment under the Conservation (Natural Habitats, & c.) Regulations 1994. The proposed development is unlikely to have a detrimental effect on the SSSI."
4. The revised application has the same footprint as the plan already given consent in April 2003, with alterations to allow safer access to the mooring during strong tidal flows. It will be noted that the proposed pontooning has been angled to allow better and safer access.
5. The benefits of the proposed scheme are:
a. all ground tackle is removed from the River apart from two mooring buoys.
b. safe navigation will be maintained past the moorings without drift at low tide.
c. safe access to the moorings will be provided.
d. no increase in boat numbers will be allowed.
e. there is no requirement for dredging.
f. Commences the first steps for the clean-up on this part of the River.
6. Full details of the proposed new development are set out in the plan titled Foulkes Boatyard Pontoon Layout Existing/Revised Proposal; Drg No. M2802/014, Scale 1:1000. Copies of the original plans will be on display at the meeting.
7. Harbour Master's Comments
7.1 The proposed plan is an opportunity to:
a. clean up this area of the River and withdraw the moorings into a tighter area.
b. reduce the danger of moorings drifting into the main channel.
c. remove most of the ground tackle from the river bed.
d. remove dilapidated, dangerous and unsightly pontoons from the River; also
e. the proposed development does not have any adverse effects on navigational safety and I believe it a benefit towards safer navigation.
7.2 It is worth noting that the marina owner has given very strong indications that once the revenue recovered from the proposed development allows, work will commence on the eastern bank clean-up. It should be noted that some material has been removed from that site over the last 18 months and the operator appears very keen to proceed further.
8. Conservation (Natural Habitats &c.) Regulations
8.1 The proposed works lie within a European Marine Site and a Site of Special Scientific Interest.
9. Harbour Works Regulations 1999
9.1 It is considered that this application constitutes a "Relevant Project". The Harbour Master should be informed of the proposed timing and method statement for the works. Mitigation would be discussed between the Environment Agency, English Nature and the Harbour Authority. Some of these moorings are trot type moorings, therefore it would also be an opportunity to reduce the ground tackle in the River and may therefore reduce disturbance to the species and features of the designated sites.