Executive Member - Education Item Item 13

26 October 2005

Major Projects Status Report

Report of the Director of Property, Business and Regulatory Services

 

How the conclusion in this report fits with the Corporate Strategy

This scheme will impact on the delivery of the following Corporate Aims

Aim 1 - maximising life opportunities - by providing new and/or improved teaching accommodation to be enjoyed by the schools.

Aim 5 - improving services - by providing good quality buildings that enable service delivery.

1. Summary

1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

1.2 Appendix 3 shows those capital projects for which an allocation has been made in the Education Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.

2. Completed Schemes

2.1 Since the July 2005 meeting of the Executive Member - Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:

    SCHOOL COMPLETION DATE

                      Bursledon CE (C) Infant September 2005

                      Droxford Junior School August 2005

                      Hiltingbury Infant School July 2005

                      Kings' Secondary School September 2005

                      Lantern's Children's Centre September 2005

                      Mill Chase Community September 2005

                      Perins Community School September 2005

                      Portchester Community School July 2005

                      Robert Mays Secondary September 2005

                      Testwood School October 2005

                      Wherweel Primary School September 2005

3. Additional Works and Funding Added Post Contract

3.1 The following schemes have had further funding added to the contract for specific additional works.

3.2 The Neville Lovett Community School, Fareham

      Additional funding of £37,642, excluding fees, has been added to the major contract currently on site at this school. The funding has come from the Policy and Resources NDS Condition Fund 05/06 for the replacement of a failed screed floor, re-routing of an electrical cable and the provision and installation of fire curtains in ceiling voids. The scheme commenced on site during early January 2005 and was due to complete in early August, however, due to these additional works and poor contractor performance, the contract will now complete during late October 2005.

3.3 Wherwell Primary School, Andover

      The Executive Member may recall in the March and June 2005 Major Projects Status report details of the discovery of bat roosts at this school during the construction period which caused a delay in the works. The financial impact of this delay has now been resolved and proposals in the Capital Programme Issues report elsewhere on this agenda recommended that additional funding of £71,000, excluding fees, be made from the Education capital programme contingency to meet the additional costs associated with the discovery of bat roosts and the subsequent delay in the building works.

4. Additional Works and Funding added at Pre Contract Stage

4.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

4.2 Additional funding has come from various sources including increased Education Capital Programme allocations and inflation and tolerance adjustments; additional school funding for specific additional requested works and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.

5. Current Position

5.1 This section gives the summarised position of the major projects, which have already been approved by the Executive Members for Policy and Resources and Education. Those schemes with works on site are reported as being financially on target unless otherwise indicated elsewhere in this report.

5.2 Alton Community Infant School

      A scheme at the above school to provide a three classroom extension, staff room and link corridor commenced on site in December 2004 and was due for completion during September 2005. The new accommodation was scheduled for completion during September 2005 and the school will have use of the building, however, a delay in the overall works has resulted in the demolition and landscaping works to be completed during early November 2005.

5.3 Lantern's Children's Centre, Winchester

      A major project to provide a new Early Years Centre in Winchester commenced on site during July 2004. The work was due to complete during August 2005, however, due to unforeseen service relocation works at the main site entrance and the impact of poor performance by a key sub-contractor, the work was completed during September 2005.

5.4 Nightingale Primary School, Eastleigh

    A major project at this school to provide permanent teaching accommodation to replace temporary classrooms and to provide a Multi Use Games Area (MUGA) was due to complete during November 2005. The new teaching accommodation element of the scheme is progressing well and the new accommodation will be available, on schedule, in early November 2005.

    Due to the location of the temporary buildings on site and the earliest date for their removal is anticipated to be December 2005 following the decant of pupils to the new teaching accommodation, it is proposed to undertake the work to provide a MUGA during the Easter 2006 period. This course of action provides an opportunity to undertake these works at a time of year when the weather is more favourable and which is appropriate for the schools operations.

Conclusion

    The details of the major capital projects outlined in this report will provide greatly enhanced school accommodation and facilities.

Recommendations

1. That the position of the major projects being undertaken by the Director of Property, Business and Regulatory Services be noted.

2. That the additional funding added to the major capital projects at pre contract stage, previously approved by the Executive Members' Education and Policy and Resources at design project appraisal stage, be approved.

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the act.

                    TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS

      Tender schedules

      Project Appraisals

MAJOR PROJECT STATUS REPORT Appendix 1

School

Current Status

Start

Complete

Funding/

* Contract Sum

£

Source of Funding

£

 

Alton Community Infant School

- three classroom, staff room and link corridor extension

- demolition and external works

On site

Dec 04

Oct 05

Sep 05

Nov 05

* 859,888

Education Capital 04/05 779,888

P&R NDS Condition 04/05 50,000

P&R Capital Repairs 04/05 30,000

859,888

 

Blackfield Primary School

- creation of 2.5fe Primary school by extending and remodelling existing Junior school

Tender Analysis

Nov 05

Sep 06

1,250,000

Education Capital 05/06 1,185,000

School 65,000

1,250,000

 

Brookfield Community School, Sarisbury Green

- internal refurbishment

On site

May 05

Oct 05

* 957,394

Education Capital 04/05 375,000

Contingency 54,133

NDS Modernisation 05/06 78,261

NDS Condition fund 04/05 450,000

957,394

 

Brune Park Community School, Gosport

- Extension to provide a new dance studio and dining hall

On site

Jan 05

Oct 05

        * 1,264,484

Education Capital 04/05 1,116,484

School - Devolved Capital 80,000

P&R NDS Condition 04/05 50,000

Underspend from previous

phase of work 18,000

              1,264,484

 

Bursledon CE (C) Infant School

- three classroom and ancillary accommodation and removal of temporary buildings

Complete

Mar 05

Sep 05

* 788,173

Education Capital 04/05 742,107

School 46,066

788,173

 

Calmore Infant School

- internal alterations to form an integrated yet independent Early Years Centre

On site

May 05

Oct 05

* 473,552

Education Capital 04/05 377,000

School 96,552

473,552

 

Chiltern Primary School, Basingstoke

- Worting School amalgamation

Enabling works

On site

Jul 04

Apr 05

Aug 04

Nov 05

* 123,475

        * 1,377,678

1,501,153

Education Capital 04/05 1,463,153

SAI 04/05 22,000

P&R NDS Condition 04/05 6,000

School 10,000

1,501,153

 

Costello Technology College, Basingstoke

- replacement maths / technology teaching block

Contract Formation

Nov 05

Feb 07

4,910,000

P&R Fire Re'statem't 05/06 4,580,000

Education Capital 05/06 250,000

P&R NDS Condition 05/06 80,000

4,910,000

 

Cove Junior School, Farnborough

- three classroom extension, Music/Drama and kiln room

On site

Sep 05

Apr 06

* 804,202

Education Capital 05/06 717,000

School 54,202

P&R NDS Condition 05/06 33,000

804,202

 

The Crescent Primary School, Eastleigh

- two classroom and library extension

On site

Jul 05

Mar 06

* 827,050

Education Capital 05/06 628,550

School 53,500

HC3S 20,000

P&R NDS Condition 05/06 125,000

827,050

 

Crestwood Community School, Eastleigh

- Community Sports Hall, drama studio and Fitness Suite

On site

Oct 05

Jun 06

* 3,132,183

Capital Programme 05/06 3,132,183

 

Droxford Junior School

- demolish kitchen, convert hall to classroom and construct new hall, kitchen and playground

Complete

Feb 05

Aug 05

* 714,034

Education Capital 04/05 673,718

School 40,316

714,034

 

Eggars School, Alton

- IT block, Sports Hall and internal refurbishment

On site

Mar 05

Dec 05

* 2,508,232

Education Capital 03/04 1,020,000

NDS Modernisation 03/04 65,000

Treloar College Funding 288,000

School 271,232

Eggars Trust Fund 688,000

P&R NDS Fire Alarm 04/05 76,000

P&R Landlord contribution 70,000

P&R External Works 04/05 30,000

2,508,232

 

Grayshott CE (C) Primary

- single storey extension and internal alterations

On site

Oct 05

May 06

* 525,000

Education Capital 05/06 365,000

School 160,000

525,000

 

The Henry Cort Community College, Fareham

- extension to staff room, two new offices, internal remodelling and refurbishment

On site

Aug 05

Mar 06

* 395,948

Education Capital 05/06 97,948

School 262,000

P&R NDS Condition 05/06 15,000

P&R Capital Repairs 05/06 2,000

P&R L'lords M. Works 05/06 12,000

P&R Ext. Landscaping 05/06 7,000

395,948

 

Hiltingbury Infant School, Chandlers Ford

- two classroom extension and remove temps

Complete

Oct 04

Jul 05

* 689,201

NDS Modernisation 03/04 332,596

P&R NDS Condition 03/04 316,605

School 40,000

689,201

 

Hollywater School, Bordon

- new special school

On site

May 05

Dec 06

* 6,088,472

Edu Cap / TCF 05/06 4,887,472

P&R Capital Repairs 05/06 629,000

P&R Capital Receipt 572,000

6,088,472

 

John Hunt of Everest Community school, Basingstoke

- New School and Youth facility

Enabling

On site

Main Contract

Aug 05

Nov 05

Nov 05

Apr 07

* 1,106,416

20,506,256

21,612,672

Capital Receipts 13,257,896

Developer's Contribution 2,467,201

B&D Borough Council 2,110,595

County Council 3,776,980

21,612,672

 

Kings' Secondary School, Winchester

twelve classroom teaching block

Complete

Nov 04

Sep 05

* 1,433,569

School 1,433,569

 

Lakeside School, Chandlers Ford

- refurb. boarding accommodation; demolish surplus boarding house; new teaching block and refurbish teaching accommodation

Enabling

Phase 1

Phase 2

Jul 04

Nov 04

Jul 05

Aug 04

Apr 05

May 06

* 196,000

* 568,000

* 1,301,254

* 2,065,254

Education Mod'tion 04/05 1,565,000

Education Capital 04/05 261,254

P&R NDS Condition 04/05 49,000

P&R Fire Precautions 04/05 190,000

2,065,254

 

Lanterns Children's Centre

- new Early Years Centre

Complete

Jul 04

Sep 05

* 2,329,951

Education Capital 03/04 616,000

Temp C'room Hire 04/05 147,000

Capital receipts 1,441,951

Friends of Medecroft 65,000

Medecroft - Devolved capital 60,000

2,329,951

 

Minstead Rural Study Centre, Lyndhurst

- new residential building, extension to schoolhouse and removal of temps

Contract Formation

Nov 05

Jul 06

        1,180,618

Education Capital 05/06 422,414

New Opportunities Fund 515,652

Study Centre 146,552

New Forest District Council 26,000

P&R Landlords contribution 70,000

1,180,618

 

Mountbatten School and Language College

- new Staff Room, Inclusion room and Multi-agency space

On site

Jul 05

Feb 06

* 449,000

Edu. Capital - SEED 05/06 117,000

School 332,000

449,000

 

Netley Marsh Infant

- new classrooms and extended hall

On site

Aug 05

Feb 06

* 678,312

Education Capital 0506 595,381

School 62,931

P&R NDS Condition 05/06 20,000

678,312

 

Neville Lovett Community School, Fareham

- new entrance foyer and reception; refurbishment of food tech area and hearing impaired unit.

On site

Jan 05

Oct 05

* 560,000

add 37,642

597,642

SAI 04/05 274,700

NDS Modernisation 04/05 111,300

School 174,000

P&R NDS Condition 05/06 37,642

597,642

 

Newtown Soberton Infant School

- new Hall and internal adaptations to create a Nursery Unit

Tender Preparation

Nov 05

Hall-Sep 06

Nursery-

Oct 06

541,000

NDS Modernisation 05/06 438,000

School 103,000

541,000

 

Nightingale Primary School, Eastleigh

- extension to provide permanent classroom accommodation

- MUGA

On site

Feb 05

Easter 06

Nov 05

Easter 06

* 1,196,477

NDS Modernisation 04/05 391,304

Contingency 55,173

Capital Receipt 646,552

School 103,448

1,196,477

 

Perins Community School, Alresford

- dance studio, fitness suite and PE classroom

Complete

Jan 05

Sep 05

* 1,762,319

Education Capital 04/05 828,024

Transfer of Fees 126,795

Specialist College Status 86,000

School 371,500

P&R Capital Repairs 04/05 300,000

P&R L'lords M/Works 04/05 25,000

P&R NDS Condition 04/05 25,000

1,762,319

 

Portchester Community School

- reorganise reception and administration; internal alterations and access improvements

Complete

Jul 04

Jul 05

* 792,936

Education SAI 04/05 413,683

Nursery School Community 18,493

HC3S 34,500

School 195,474

P&R NDS Condition 04/05 108,286

P&R M'ment Partnership 04/05 7,500

P&R Fire Precautions 04/05 15,000

792,936

         

Priestlands Secondary School, Lymington

-music/drama facility and dining extension

On site

May 05

Dec 05

* 1,615,665

Education Capital 04/05 1,069,828

School 277,000

Specialist School Status 04/05 100,000

P&R NDS Condition 05/06 20,000

Transfer of Fees 148,837

1,615,665

 

Rachel Maddocks School, Waterlooville

- extension, internal alterations, refurbishment and repair

Tender Preparation

Nov 05

Mar 06

310,000

Education Capital 05/06 165,000

School 137,000

P&R Capital Repairs 05/06 8,000

310,000

 

Saint Lawrence CE (C) Primary

- new hall, kitchen, link building and internal refurbishment

On site

Oct 05

Apr 06

* 599,485

Education Capital 05/06 599,485

 

South Baddesley CE (C) Primary

- phase 1 - new classroom and staffroom

- phase 2 - new hall and car park

On site

On site

May 05

Sep 05

Oct 05

Mar 06

* 424,722

* 484,872

909,594

Education Capital 04/05 391,828

School 115,653

NDS Condition 05/06 65,000

P&R Capital Repairs 05/06 77,113

P&R Capital 05/06 260,000

        909,594

 

Staunton Park Community

- Healthy Living Centre

On site

Jul 05

Jan 06

* 542,862

NDS Modernisation 04/05 70,862

School 50,000

Sport England 422,000

542,862

 

Testwood School, Totton

- Synthetic Turf Pitch

Complete

Jun 05

Oct 05

* 473,856

Football Foundation Grant 429,356

School 44,500

473,856

 

The Toynbee Community College, Chandlers Ford

- new Multi-Purpose Suite

Contract Formation

Nov 05

May 06

* 508,620

School 265,517

P&R Capital 05/06 200,000

Eastleigh Borough Council 43,103

508,620

 

Waterside Primary School, Hythe

- remodel and refurbish existing school; construct classroom block and early years unit

Tender Preparation

Dec 05

Aug 06

1,935,000

Education Capital 05/06 1,408,000

School 125,000

P&R Capital Repairs 05/06 178,000

P&R NDS Condition 05/06 224,000

1,935,000

 

Wherwell Primary School, Andover

- extensions and internal alterations

Complete

Aug 04

Apr 05

Feb 05

Sep 05

* 538,513

NDS Modernisation 04/05 441,959

Staff Workplaces 04/05 34,783

Temp classroom hire 04/05 9,300

School 52,471

538,513

 

Whitchurch CE (C) Primary

- two new classrooms, ICT Suite and corridor

On site

Jul 05

Feb 06

* 515,000

Education Capital 04/05 431,000

School 84,000

515,000

 

SPECIALIST SCHOOLS ACCOMMODATION PROGRAMME 2005/06 Appendix 2

School

Current Status

Start

Complete

Funding / * Contract Sum

Source of Funding £

Robert Mays Secondary School

- refurbishment of science laboratories and preparation rooms

Complete

May 05

Sep 05

* 373,000

NDS Modernisation 05/06 132,000

Specialist School funds 04/05 87,000

School 154,000

373,000

Mill Chase Community School

- refurbish science laboratories and food technology rooms; refurbishment to form Learning Support Unit

Complete

Jun 05

Sep 05

* 425,332

NDS Modernisation 05/06 317,573

SAI 04/05 107,759

425,332

Package 1 -

    - Toynbee School

    - The Hayling School

    - Noadswood School

    - Aldworth Science College

Complete

Design

Aug 05

Jan 06

Oct 05

Mar 06

* 311,369

NDS Modernisation 04/05 311,369

          Appendix 3

Other Schemes in the Education Capital Programme

The following schemes are included in the Education 2005/06 Capital Programme and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member Education or Policy and Resources:

School Allocation

        (excluding fees)

          £'000

PRIMARY

North Basingstoke schools

776

Whiteley / Western Wards

1,240

 

2,016

SPECIAL

Sundridge School, Havant

5,074

 

5,074

NDS MODERNISATION

Broughton Primary

228

Curdridge Primary

618

Micheldever Primary

1,240

Stanmore Primary

217

The Bridge Centre

830

 

3,133

   

TOTAL

10,223