Hampshire County Council Executive Member Education Item14 26 October 2005 Minor Projects - Progress Report
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
1. Summary
1.1 The purpose of this report is to provide an update of the progress made in implementing those schemes in the Education Capital Programme with a value of between £43,000 and £216,000 (exclusive of fees).
2. Current Position
2.1 The attached tables summarise the current position in relation to schemes funded by the Education 2004/05 and 2005/06 Capital Programme including Minor Works, Seed Challenge, William Price Trust, Schools Access Initiative (SAI), New Opportunities Fund (NOF) and Staff Workplaces budget. The tables provide details of the funding, a brief description of the works and a summary of the current position.
3. Education Minor Works 2005/06
3.1 Alderman Quilley School, Eastleigh
The residue of the NOF funding from the sports hall project (£18,000), together with School Devolved Capital of £15,000, Environment - Safe Routes to School 04/05 funding of £76,120 and a contribution of £40,000 from the P&R External Works Budget 05/06 will be used to undertake car park relocation works, new access roads, footpaths and cycleways.
Works are due to commence on site during September 2005, with completion anticipated in December 2005.
4. Schools Access Initiative (SAI) / Disability Discrimination Act (DDA) 2005/06
4.1 Fordingbridge Junior School
An allocation of £49,000 has been made in the Education Capital Programme SAI 2005/06 for works to upgrade and modify the accessible wc facilities.
Works are due to commence on site during September 2005 with completion anticipated during November 2005.
5. William Price Trust 2005/06
5.1 Heathfield Special School, Fareham
An allocation of £57,000 has been made in the Capital Programme 2005/06 which together with School devolved capital of £24,000 will be used to improve and extend the existing Early Years play area.
It is anticipated that works will commence on site during January 2006 with completion anticipated during March 2006.
6. Specialist School College Status Allocations 2004/05
6.1 Alderman Quilley Secondary School, Eastleigh
An allocation of £87,000 has been made in the Capital Programme 2005/06, which together with School devolved capital of £18,500 and NDS Modernisation funding of £43,500, will be used to provide new entrance doors and ramp, also internal refurbishment and electrical/mechanical works.
£5,000 of the funding is to be used for a small package of enabling works for the removal of asbestos ceilings. This work is due to commence in September.
It is anticipated that the main works will commence on site during October 2005, with completion during December 2005.
Recommendation
1. That the changes to the minor works programme be approved.
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information File, PBRS
Minor Works Capital Programme 2005/06 (* including carry forwards)
School |
Funding Position £ |
Summary of works |
Comments |
Alderman Quilley School, Eastleigh |
Residue of NOF sports hall Project 18,000 School Devolved Capital 15,000 Environment - Safe Routes to School 04/05 76,120 P&R External Works Budget 05/06 40,000 149,120 |
Relocation of school car park to new location behind Sports Hall with new access roads, footpaths and cycle ways. |
Works commenced on site in September 2005 with completion anticipated in December 2005. |
Bordon Junior School |
Capital Programme 05/06 50,103 School - Devolved Capital 66,000 P&R NDS Condition 05/06 25,000 141,103 |
Entrance lobby, canopy and internal alterations to admin office. |
Works are due to commence on site during October 2005 with an anticipated completion date of February 2006. |
Butts Primary School, Alton
|
Capital Programme 05/06 77,587 P&R Capital Repairs 20,000 School - Devolved Capital 67,242 164,829 |
Extend existing building to improve administrative accommodation and provide a multi purpose teaching room. |
Works are due to commence on site in October 2005 with completion anticipated in February 2006. |
Grange Junior School, Rowner, Gosport |
Capital Programme 05/06 20,000 School - Devolved Capital 58,621 78,621 |
ICT Suite and porch extension. |
This scheme is currently on hold pending Governors' meeting in September 2005. |
Hamble Primary School |
Capital Programme 05/06 100,000 School - Devolved Capital 55,000 155,000 |
Extension to classroom to create additional teaching space, cloak and alterations to lobby/entrance area. |
It is proposed to invite tenders during November2005 with works commencing on site in January 2006 and completion anticipated in June 2006. |
Havant SEN, Havant |
Capital Programme 04/05 129,000 |
Possible contribution to future major scheme. |
May form part of capital scheme. Project currently on hold. |
Hayling School, Hayling Island |
Capital Programme 04/05 151,200 |
Landscaping works to include resurfacing, seating, planting and student seating shelter. |
Works were completed on site during September 2005. |
Hounsdown Secondary School, Totton |
Environment - Safe Routes to School 04/05 41,379 Safe Routes to School 05/06 62,069 School Funding 59,483 NDS Condition Funding 20,000 P&R External Works 20,000 202,931 |
Improvements to the entrance to the School to include a new footpath/ |
Approved by the Environment Committee June 2005. Works commenced on site during August 2005 with completion anticipated in November 2005. |
West End Infant School, Aldershot |
Capital Programme 04/05 66,087 School - Devolved Capital 125,070 191,157 |
Internal alterations and entrance extension. |
Works were completed on site during September 2005. |
Staff Workplaces 2005/06 (*including carry forwards)
School |
Funding position £ |
Summary of Works |
Comments |
Burley Primary School |
Capital Programme 05/06 39,311 School - Devolved Capital 30,000 69,311 |
Small extension to provide additional office accommodation. |
Feasibility/design underway and programme being agreed. |
Connaught Secondary School, Aldershot |
Capital Programme 05/06 28,448 P&R Capital Repairs 1,552 P&R Maintenance 2,000 School - Devolved Capital 58975 90,975 |
Upgrade staff accommodation and male staff toilets. |
Work commenced on site during August 2005 with completion anticipated in October 2005. |
Itchen Abbas Primary School, Winchester |
Capital Programme 05/06 43,500 Education - School Security 17,400 School - Devolved Capital 73,275 134,175 |
Relocation of admin office and Headteacher's office to first floor to provide improved security and staff office facilities. |
Tenders were invited during October 2005. Works are due to commence on site in November 2005 with completion anticipated in March 2006. |
Warblington Secondary School |
Capital Programme 04/05 50,000 P&R NDS Condition 05/06 15,000 65,000 |
Staff and admin upgrade. |
Works were completed on site during October 2005. |
SEED Challenge 2004/05 and 2005/06 (*including carry forwards)
School |
Funding position £ |
Summary of Works |
Comments |
All Saints CE Junior School, Fleet |
SEED 04/05 35,888 School - Devolved Capital 94,333 130,221 |
To create a Continuous Professional Development Centre/workroom for all staff. In addition a group space for SEN will also be provided. |
Works were completed on site during October 2005. |
Denmead Junior School, Waterlooville |
SEED 04/05 57,536 School - Devolved Capital 91,164 148,700 |
New ICT room. |
Work commenced during May 2005 with completion anticipated in August 2005. |
Limington House School, Basingstoke |
SEED 04/05 37,033 School - Devolved Capital 51,399 88,432 |
Creation of tutorial areas for pupils in 14-19 age range who exhibit challenging behaviour plus a hygiene area to reflect the changing needs of the post 16 group. To include a new teaching area. |
Works were completed on site during September 2005. |
Marnel Junior School, Basingstoke |
SEED 04/05 11,638 School Devolved Capital 76,318 87,956 |
Alterations and refurbishment. |
Works commenced on site during August 2005 and anticipated completion is November 2005. |
Meadowlands Infant School |
SEED 04/05 36,439 School - Devolved Capital 50,685 87,124 |
A comprehensive and complete redesign and redevelopment of the front area of the school to provide a dedicated staff workspace with ICT facilities. |
Work completed August 2005. |
Merton Junior School, Basingstoke |
SEED 04/05 50,109 School - Devolved Capital 76,942 127,051 |
Improve reception area and its security. Reorganised office accommodation. To increase the size and facilities of the staff room. To create a group/tutorial space for children with SEN. |
The scheme was completed during September 2005. |
New Milton Infant School |
SEED 04/05 56,926 School - Devolved Capital 89,131 146,057 |
Provision of SEN space and additional staff room accommodation. Construction of a corridor to bypass the hall. Provision of an adequate library and PE storage to free up space in hall area. |
Works commenced on site during July 2005 with completion anticipated in October 2005. |
Riverside Community Special School, Waterlooville |
SEED 04/05 57,955 School - Devolved Capital 76,539 134,494 |
Teaching and learning resources/training area and multi-sensory room development. |
Works were completed on site during August 2005. |
St Thomas' Infant School |
SEED 04/05 50,018 School - Devolved Capital 86.000 136,018 |
To create a new administration office and staff work room. To create a new SEN room for group work. |
Works were completed on site during August 2005. |
Wallisdean Junior School, Fareham |
SEED 04/05 42,434 School - Devolved Capital 57,888 100,322 |
Build a new staff room freeing up space to be developed as an ICT suite/ meeting room. |
The main works were completed during August 2005. Some additional works to windows are expected to be complete during October 2005. |
Westfields Junior School, Yateley |
SEED 04/05 52,240 School - Devolved Capital 58,760 P&R Asbestos Removal 05/06 5,000 116,000 |
Alterations to toilets and alterations to provide food technology, ICT and space for SEN. |
Works were completed during September 2005. |
Westfields Junior School, Yateley |
This scheme is Phase 2 of the above item and is included within that funding |
Renewal of suspended ceilings and floors coverings, installation of new wet area units and redecoration. |
Works were completed during September 2005. |
Schools Access Initiative (SAI) / Disability Discrimination Act (DDA) 2005/06 (*including carry forwards)
School |
Funding Position £ |
Summary of Works |
Comments |
Abbottswood Junior School, Totton |
Capital Programme 04/05 60,058 Capital Programme 05/06 40,870 100,928 |
Hygiene room and WC modifications and level access. |
These works were completed on site during September 2005. |
Bohunt Community School |
Capital Programme 05/06 49,652 |
Improvements to provide accessibility |
Feasibility/design underway and programme being agreed. |
Fordingbridge Junior School |
Capital Programme 05/06 49,000 |
Disabled WC upgrade and access and modifications to existing WC's |
It is proposed to commence works on site during September 2005 with completion anticipated in November 2005. |
Frogmore Community School, Yateley |
Capital Programme 05/06 69,565 |
Toilet upgrade and physio rooms with ramp access. |
Scheme currently on hold pending further discussions with the School. |
Guillemont Junior School, Farnborough |
Capital Programme 05/06 56,304 |
Accessible WC and ramp access across site. |
Works were completed on site during September 2005. |
Horndean Junior School, Waterlooville |
Capital Programme 05/06 63,930 School - Devolved Capital 9,500 73,430 |
Accessible WC and alterations to girls WC and alterations to provide level access. |
Due to the high value of tenders returned, this scheme is being revised and will be re-tendered in the near future. |
Kings School, Winchester |
Capital Programme 05/06 52,174 |
Internal lift access. |
Following discussions with the School during September, the scheme is currently being redesigned. |
Ringwood Infant School, Ringwood |
Capital Programme 05/06 56,522 |
Internal access and modifications to WC's. |
It is proposed to invite tenders during October 2005 with works commencing on site in November 2005 and completion anticipated in March 2006. |
Siskin Junior School, Gosport |
Capital Programme 04/05 50,000 Capital Programme 05/06 25,478 School devolved capital 8.933 84,411 |
Accessible WC and adaptation to staff WC, Medical room and stores. |
This scheme was completed on site during September 2005. |
Uplands Primary School, Fareham |
Capital Programme 04/05 54,957 |
External access and internal platform lift. |
Phase1 of the works completed in September 2004. Phase 2 of the works include providing access around the site. Work commenced on site in May 2005 with completion anticipated in September 2005. |
Weyford Infant School |
Capital Programme 05/06 70,174 |
Ramps, accessible WC and platform lift. |
Works commenced on site in August 2005 with completion anticipated in October 2005. Ramps to form part of framework agreement - commence on site September, completion anticipated October 2005. |
Wildern Secondary School, Hedge End |
Capital Programme 05/06 58,522 |
Alarm system for HI, modifications to WC's and level access. |
Feasibility/design underway and programme being agreed. |
Wyvern Technology College, Fair Oak |
Capital Programme 05/06 108,696 |
Accessibility and internal modifications. |
Feasibility/design underway and programme being agreed. |
William Price Trust 2005/06 (*including carry forwards )
School |
Funding Position £ |
Summary of Works |
Comments |
Heathfield Special School. Fareham |
Capital Programme 05/06 57,400 School - Devolved Capital 24,000 |
Improvement and extension of existing Early Years playground. |
It is intended to tender this scheme during November 2005. Start on site is anticipated in January 2006, completion anticipated March 2006. |
Oak Meadow Early Years Centre, Fareham |
Capital Programme 05/06 * 127,826 |
Internal alterations to form additional meeting areas, creation of new external entrance, provide staff room, toilets, kitchen and storage areas. Also formation of car park with 17 spaces including some accessible spaces, new footpath, entrance and external storage shed. |
Due to higher-than-expected tenders, the scheme is now being carried out in two phases: the car park work commenced on site during August 2005, with completion anticipated in October. The internal alterations are due to commence on site during September 2005, with completion anticipated November. |
New Opportunities Fund (NOF) - 2005/06 (*including carry forwards)
School |
Funding Position £ |
Summary of Works |
Comments |
Bridgemary Community School, Gosport |
NOF 05/06 *156,000 School - Devolved Capital 30,000 186,000 |
Multi Use Games Area (MUGA) |
Works were completed on site during October 2005. |
Cowplain Secondary School, Waterlooville |
This scheme is now a Major Project and is reported elsewhere on the agenda. |
Multi Use Games Area (MUGA) |
This scheme is now a Major Project and is reported elsewhere on the agenda. |
Park Community School, Havant |
NOF 05/06 *156,000 School - Devolved Capital 30,000 186,000 |
Multi Use Games Area (MUGA) |
Works were completed on site during October 2005. |
Specialist School College Status Allocations 2004/05 (including carry forwards)
School |
Funding Position £ |
Summary of Works |
Comments |
Alderman Quilley Secondary School, Eastleigh |
Capital Programme 04/0587,000 School funding 18,500 NDS Modernisation 43,500 149,000 |
New doors/ramp. Internal refurbishment/decoration, electrical/mechanical works. Enabling package for asbestos removal (£5k) |
Due to be tendered during September 2005. Enabling works are due to start during September 2005, with the main package of work due to commence in October 2005, with completion anticipated December 2005. |
Amery Hill Secondary School, Alton |
Capital Programme 05/0687,000 School funding tbc |
Specialist school allocation (Music) |
Feasibility/design underway and programme being agreed. |
Bay House Secondary School, Gosport |
Capital Programme 05/0687,000 School funding tbc |
Specialist school allocation |
This work will form part of the major capital scheme being undertaken at the school. |
Crestwood College for Business and Enterprise, Eastleigh |
Capital Programme 05/06 105,000 School funding tbc |
Specialist school allocation |
Feasibility/design underway and programme being agreed. |
Eggars Community School, Alton |
Capital Programme 05/0687,000 School funding tbc |
Specialist school allocation |
Feasibility/design underway and programme being agreed. |
John Hanson School, Andover |
Capital Programme 05/0687,000 School funding tbc |
Specialist school allocation (Science) |
Feasibility/design underway and programme being agreed. |
The Petersfield School, Petersfield |
Capital Programme 05/0687,000 School funding tbc |
Specialist school allocation (Sports) |
Feasibility/design underway and programme being agreed. |
Priestlands Secondary School, Lymington |
Capital Programme 05/0687,000 School funding tbc |
Specialist school allocation (Arts) |
Feasibility/design underway and programme being agreed. |
Testwood Secondary School, Totton |
Capital Programme 05/0687,000 School funding tbc |
Specialist school allocation (Arts) |
Feasibility/design underway and programme being agreed. |
NDS Modernisation Programme 2005/6 - Schools Specialist Accommodation Programme
School |
Funding Position £ |
Summary of Works |
Comments |
Brune Park Secondary School, Gosport |
Capital Programme 05/06 43,103 School funding tbc |
1 No. Science lab refurbishment |
Feasibility/design underway and programme being agreed. |
Court Moor Secondary School, Fleet |
Capital Programme 04/05 87,000 Capital Programme 05/06 87,000 School Funding 52,900 226,900 |
4 No. Science Lab refurbishments |
Work commenced on site during March 2005 and completed during June 2005. |
Cowplain Secondary School |
Capital Programme 05/06 43,103 |
1 No. Science lab refurbishment |
Feasibility/design underway and programme being agreed. |
Frogmore Community School, Yateley |
Capital Programme 04/05 87,000 School - Devolved Capital 126,724 212,724 |
Food technology and textiles refurbishment |
Works commenced on site during June 2005 and were completed during August 2005. An additional £25,000 School devolved capital was added to the scheme for fit-out of textiles room. |
Hamble Community Sports College, Hamble |
Capital Programme 05/06 132,174 School funding 47,129 179,303 |
2 No. science lab refurbishments and new external fire escape stair |
This scheme was completed on site during October 2005. |
Noadswood Secondary, Dibden Purlieu |
Capital Programme 05/06 86,207 School Funding tbc |
2 No. Science lab refurbishment |
Feasibility/design underway and programme being agreed. |
Portchester Community School |
Capital Programme 05/06 86,207 School Funding tbc |
2 No. science lab refurbishment |
Feasibility/design underway and programme being agreed. |
Test Valley Secondary School |
Capital Programme 05/06 43,103 |
1 No. Science Lab Refurbishment |
Feasibility/design underway and programme being agreed. |