Hampshire County Council Executive Member Education Item15 26 October 2005 Self-funded and Partially Self-funded schemes Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 E-mail: [email protected]
1. Introduction
1.1 Self-funded and partially self-funded schemes are developed as a result of a request from the School Governors to provide additional accommodation or facilities, which can be funded from their budget. The Director of Property, Business and Regulatory Services in each case develops designs and specifications to current County Council standards in accordance with the requirements of the Building Regulations and the space guidelines of the DfES notwithstanding the fact that these schemes are not always about satisfying basic need. It should be noted that contracts will not be let without confirmation that funding is available and the County Treasurer and County Education Officer will be consulted regarding the schools having sufficient funding to carry out the works outlined in this project.
2. The Schemes
2.1 The schemes have been developed in consultation with the Headteacher and Governors of the schools. The attached table summarises the current position in relation to each of these schemes, gives details of the funding, and a brief description of the scheme. Each of the schemes in this report is valued between £43,000 and £216,000 (exclusive of fees).
Recommendation
1. That the changes to the self funded report be approved.
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report and attached appraisal.
NB the list excludes:
1. Published works
2. Documents which disclose exempt or confidential information as defined in the Act.
TITLE FILE
Contract Reconciliation Statements Self-funded
Confirmation of School funding forms Schemes - TMH.
Architects Plans
Planning Statements
School |
Funding Position £ |
Summary of Works |
Comments |
Bishopswood Infant School, Tadley |
School - Devolved Capital 120,000 |
Music Room extension |
Work is due to commence on site during October 2005 and be completed during January 2006. |
The Butts Primary School, Alton |
School - Devolved Capital 67,000 |
Multi Purpose Room extension |
Work commenced on site during September 2005 and is due for completion during December 2005. |
Cliddesden Primary School, Basingstoke |
School - Devolved Capital 57,600 School Security budget 5,000 62,600 |
Administration / Staff room extension |
It is anticipated that work will commence on site during January 2006 and be completed during May 2006. |
Eling Infant School, Totton |
School - Devolved Capital 24,409 School - LMS 6,091 Education - School Security 05/06 21,500 52,000 |
Access improvements and alterations to reception |
Work commenced on site during October 2005 and is due for completion during November 2005. |
Fort Hill Community School, Basingstoke |
School - Devolved Capital 125,585 |
Design Technology classroom refurbishment |
Work commenced on site during August and was completed during October 2005. |
Four Marks CE Primary School |
School - Devolved Capital 68,803 |
Formation of Netball Courts and Path |
This scheme is currently out to tender and it is anticipated that work will commence on site during November 2005 and be completed during December 2005. |
Fryern Infant & Junior Schools, Chandlers Ford |
Infant School - Devolved Capital 9,440 Junior School - Devolved Capital 4,900 Safer Routes to Schools 05/06 44,643 P&R Management Partnership 05/06 5,000 63,983 |
Works to front entrance, car park and pedestrian flow |
Work commenced and completed during September 2005. |
School |
Funding Position £ |
Summary of Works |
Comments |
The Hayling School |
School 70,000 |
Internal alterations and refurbishment to ICT classrooms and Library |
Work commenced on site during July 2005 and was completed during September 2005. |
Henry Beaufort School, Winchester |
School - Devolved Capital 9,700 School - LMS 8,000 Playgroup contribution 16,000 P&R External Works 05/06 17,000 50,750 |
Nursery outdoor play area and social area |
Work commenced during October 2005 and is due for completion during November 2005. |
Icknield School, Andover |
School - Devolved Capital 47,393 School - PTA 34,000 School - Unofficial funds 66,041 147,434 |
Extensions to offices, staff room and entrance. |
It is proposed that this work will be combined with a package of SCOLA recladding to make one large scheme. Tenders have recently been invited and it is anticipated that work will commence on site during November 2005 and be completed during April 2006. |
Knightwood Primary School, Chandlers Ford |
School - Devolved Capital 91,000 School - LMS 3,000 School - Unofficial Funds 6,000 100,000 |
Alterations to lobby and office and extension to form store and staff work room |
This scheme is currently out to tender and it is anticipated that work will commence on site during November 2005 and be completed during February 2006. |
Leesland CE (C) Junior School, Gosport |
School - Devolved Capital 50,000 |
Toilet refurbishment |
Work is due to commence on site during January 2006 and be completed during March 2006. |
Osbourne School, Winchester |
School 45,000 |
Internal adaptations to provide one `calming room' and provision of external play area. |
Work commenced on site during July 2005 and was completed during September 2005. |
School |
Funding Position £ |
Summary of Works |
Comments |
Sheet Primary School, Petersfield |
School - Devolved Capital 84,500 |
Ground floor extension and internal alterations |
Work commenced on site during August and was completed during October 2005. |
Siskin Junior School, Gosport |
School - Devolved Capital 22,000 Gosport Borough Council 125,000 P&R External Works 05/06 15,000 162,000 |
Multi Use Games Area (MUGA) and playground improvement works |
Work commenced on site during August 2005 and is due for completion during November 2005. |
Talavera Junior School, Aldershot |
School - Devolved Capital 112,082 |
Extension to administration area |
Works were completed as part of the major re-cladding scheme at the school. |
Testwood School, Totton |
School 75,000 |
Changing Room refurbishment |
Work will commence on site during November 2005 and be completed during January 2006. |
Tweseldown Infant School, Fleet |
School - Devolved Capital 86,664 |
Internal alterations and refurbishment |
Work commenced on site during September 2005 and is due for completion during December 2005. |
Twyford Primary School |
School - Devolved Capital 35,000 P&R NDS Condition 05/06 25,000 60,000 |
Refurbishment of classrooms, toilets and cloakrooms and hall floor repairs. |
Work commenced during July 2005 and was completed during October 2005. |
The Wavell School, Farnborough |
School - Devolved Capital 63,000 |
Refurbishment of Art Classrooms |
Tenders have been returned and subject to confirmation of additional funding to meet the tender price, it is anticipated that work will commence on site October 2005 and be completed during December 2005. |
School |
Funding Position £ |
Summary of Works |
Comments |
Wildground Junior School, Dibden Purlieu |
School -Devolved Capital 51,000 School - LMS 15,000 66,000 |
New ICT Suite |
Work commenced on site during October 2005 and is due for completion during November 2005. |