Hampshire County Council Havant Highway and Transport Advisory Panel 2 November 2005 Traffic Management Programme 2005/06 Report of the Head of Technical Services, Havant Borough Council |
Item 11 |
Contact: Alastair Norton, tel 023 9244 6510
email: [email protected]
1. Summary
1.1 This report covers the main programmes of traffic management work completed and ongoing in the borough during 2005/06 under the following headings:
(i) Traffic Regulation Orders and Road Safety Schemes;
(ii) Decriminalised Car Parking Enforcement;
(iii) Cycleways; and
(iv) Liveability Schemes.
2. Traffic Regulation Orders and Road Safety Schemes
2.1 The Borough Council receives numerous requests from the public for traffic management measures and priority is given to those where road safety is an issue. Schemes also transpire as a result of monthly Casualty Reduction Partnership meetings that take place with the County Council's Safety Engineering Group and the Police to discuss matters relating to the fatal and life threatening accidents that occur on the borough's roads.
2.2 The list of schemes included in the 2005/06 capital programme is attached as Appendix 1.
3. Decriminalised Car Parking Enforcement
3.1 Decriminalised car parking enforcement was successfully introduced on 4 April 2005. The scheme has so far been working satisfactorily and within budget expectations.
3.2 The improved enforcement has resulted in representations, particularly from Emsworth residents and traders, to extend the 30 minute limited on-street waiting in central Emsworth and to introduce a residents' parking scheme. Surveys have been undertaken with traders and shoppers in order to form a view as to the most appropriate course of action. Discussions are now taking place with ward Councillors in order to assess the results of the consultation and agree what action should be taken.
3.3 It should be noted that the Borough and County Councils are members of the National Parking Adjudication Service (NPAS) Joint Committee. This is the national body, based in Manchester, established under the relevant legislation to provide an independent adjudication service for drivers or vehicle owners wishing to appeal against a penalty charge notice. The county representative, Councillor Phrynette Dickens, is the Assistant Chairman of the NPAS Joint Committee.
3.4 Regulations are expected to be made during the next few months which will enable authorities already operating DPE to introduce camera enforcement of bus lanes under the Transport Act 2000. These will be superseded in due course by regulations under the Traffic Management Act when the provisions for civil enforcement outside London come into effect, although this is not expected to be until at least 2007. They will include not only parking and bus lane enforcement, but also some other moving traffic offences such as banned turns, no entry and yellow box markings.
4. Cycleways
4.1 Information as to the progress being made with the various cycleway schemes is set out in Appendix 2.
5. Liveability Schemes
5.1 The Borough Council is a pilot authority for the transformation of services in connection with public open spaces and has been awarded £3.3 million to be spent on capital schemes that enhance selected public spaces.
5.2 Possible schemes have been discussed at the Borough Council's six Community Boards and proposals have been submitted to the Council's Liveability Project Board. This Board has now agreed which schemes should be carried out. Many of these will involve improvements to the highway and be subject to a Section 278 Agreement.
5.3 The highway related schemes are as follows:
(i) London Road Precinct, Waterlooville
This scheme includes improvements to paving and the provision of street furniture, lighting, trees and gateway features to the northern section of the existing London Road Precinct.
(ii) Leigh Park Parking Pilot
Schemes piloting different solutions to the residential parking problems are to be carried out at Kingsworthy Road, Iping Avenue and Overton Crescent.
(iii) West Street, Havant
This scheme includes the provision of seating, lighting and stone paving in the section of West Street outside St Faith's Church.
(iv) Eastoke Corner, Hayling Island
This scheme includes the provision of a pedestrian plaza and viewing platform linking shop frontages to the seafront, with revisions to the highway and parking spaces.
(v) Langstone
This scheme includes an extension of the bridge lighting, an improved pedestrian refuge at Langstone, a small car park, tree planting and a gateway sculpture at north Hayling.
(vi) Emsworth
This scheme includes improvements to the A259 subway (lighting, mirrors, anti-slip surfaces, handrails and artwork) improved crossing refuges north and south of the A259/North Street roundabout, and replacement railings.
(vii) Milton Road, Cowplain
This scheme includes improved parking, new trees and street furniture, a mini roundabout, road narrowing, rumble strips and new surfacing on the section of Milton Road between the Eagle Avenue and Lovedean Lane junctions.
5.4 The Liveability funding conditions require schemes to be substantially completed by 31 March 2006. It is expected that most of them will be completed in accord with this condition but some work will inevitably carry over into the 2006/07 financial year.
6. Impact Assessments
6.1 This report provides a position statement only, therefore an impact assessment in terms of the Race Relations (Amendment) Act has not been undertaken.
Recommendation
That this report be noted.
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
None |
9311/AN
APPENDIX 1
HAVANT TRAFFIC MANAGEMENT PROGRAMME 2005/06
LOCATION |
ACTION BY |
TYPE |
PROGRESS |
TRAFFIC REGULATION ORDERS |
|||
COWPLAIN, Lovedean Lane |
HBC |
Restriction of waiting |
Advertised 20/7/04 - 17/8/04. Car park now constructed. Waiting restrictions painted 7/6/05 |
EMSWORTH, Town Centre |
HBC |
Restriction of waiting & loading |
Advertised 25/2/05 - 29/3/05. Objections reported to Executive |
HAVANT, Blenheim Gardens |
HBC |
Restriction of waiting |
Held in abeyance |
LEIGH PARK, Barncroft Way |
HBC |
No waiting/no stopping |
Works to be ordered |
HAVANT, North Way |
HBC |
Restriction of waiting |
Consensus unable to be obtained from the residents. Scheme held in abeyance. |
HAVANT, Elm Park Road |
HBC |
Restriction of waiting |
Advertised 18/7/05 - 15/8/05. Objections being analysed. |
PURBROOK, Alsford Road, Aldermoor Road East and Kentidge Road |
HBC |
Restriction of waiting |
Scheme advertised. Objections to HBC Executive on 23/3/05. Waiting restrictions painted 31/5/05. |
HAVANT, Southmoor Lane |
HBC |
Restriction of waiting & height restriction |
Advertised 1/8/05 - 30/8/05. Objections being analysed. |
HAVANT, Swanmore Road |
HBC |
Restriction of waiting |
Scheme being prepared. |
WATERLOOVILLE, (rear of Wellington Way) |
HBC |
Loading bay |
Scheme to be prepared |
HAVANT, Oaklands Road & Pine Grove |
HBC |
Restriction of waiting |
Scheme to be prepared. |
HAVANT, Park Lane |
HBC |
Restriction of waiting |
Scheme prepared. To be advertised for public comment. |
WATERLOOVILLE TOWN CENTRE REVIEW |
HBC |
Restriction of waiting |
Representations received - to be discussed with the ward Members |
WATERLOOVILLE, Stakes Hill Road |
HBC |
Restriction of waiting |
Scheme prepared. To be advertised. |
INVOLVEMENT IN CROSS-CUTTING SCHEMES |
|||
WATERLOOVILLE, Town Centre Bus Priority Scheme |
HCC/HBC |
Signing and Traffic Regulation Order preparation |
Scheme preparation commenced. |
DECRIMINALISED PARKING |
HBC |
Traffic Regulation Order borough-wide |
Consolidation Order in operation |
HAVANT BUS STATION (Market Parade) |
HBC |
Restriction of waiting, loading and speed limit |
TRO came into operation on 31/7/05. The buses are now temporarily relocated in Market Parade & North Street. |
LIVEABILITY |
HBC |
Borough boundary and district signs |
Signs designed - exhibition commenced 12/9/05. |
ROAD SAFETY ENGINEERING SCHEMES |
|||
EMSWORTH, New Brighton Road (phase 2) |
HBC |
Improvement to road signs |
Additional signage to be erected following a recent PIA. |
EXTERNALLY FUNDED SCHEMES |
|||
WATERLOOVILLE, Aston Road |
HBC |
Road closure |
Advertised 30/9/04 - 27/10/04. Objections analysed. Report went to HBC Executive on 23/3/05. Discussions in progress with the developer to bring the scheme into operation. |
HAVANT, Nest Business Park, Martin Road |
HBC |
Weight Restriction Order |
Design required |
HAVANT, Community Hospital, Lavant Drive & Leigh Road. |
HBC |
Road closure & waiting restrictions |
Advertised 16/12/04 - 10/1/05. Objections analysed. Report went to HBC Executive on 23/3/05. Waiting restriction approved & became operational on 23/3/05. Closure deferred pending receipt of planning application for hospital site. |
HAVANT, (Hargreaves Site) Selbourne Road & Brockhampton Lane |
HBC |
Road closure & waiting restrictions |
Scheme now prepared. To be advertised for public comment. |
HAVANT, Bulbeck Road |
HBC |
Extension to one-way system |
Advertised 1/8/05 - 30/8/05. Scheme to be implemented shortly. |
TEMPORARY TRAFFIC REGULATION ORDERS - since 1 April 2005, 22 temporary road closures have been processed; 16 by Notice and 6 by Order.
APPENDIX 2
HAVANT CYCLEWAYS
LOCATION |
PROGRESS |
Hayling Billy Trail (Havant Railway Station) |
Works to continue the trail from the centre of South West Trains car park to the station forecourt, including cycle storage and motor cycle storage, work commenced in October. |
Hayling Billy Trail (Langstone) |
No progress as funding has not been agreed. |
A259 (Emsworth, Havant Road) |
Feasibility study is being carried out by the County Council to assess the possible completion of the cycleway to Emsworth town centre. |
Southleigh Road |
Works to the section from Rowan Road to Emsworth Road have been completed. The section between Eastleigh Road and Rowan Road is currently being designed. |
Southleigh Road to Bellevue Lane |
As part of the school travel plan a feasibility study is being carried out. |
Horndean Road to Emsworth Primary School |
As part of the school travel plan a feasibility study is being carried out. |
Harts Farm Way |
Ground survey to be carried out in November 2005. |