Hampshire County Council Amended Decision Sheet Executive Member for Policy and Resources Item 2G 4 November 2005 Revenue and Capital Repairs 2005/06 - six-monthly review Report by the Director of Property, Business and Regulatory Services |
Contact: Karen Murray Ext: 7876 email: [email protected]
1 |
Summary |
| |
|
1.1 |
The following decisions are sought: |
| |
|
| |
That approval be given to the following additions to the NDS/Capital Repairs programme: Up to £100,000 Ticehurst OPH - replacement of oil fired boilers Marlfield OPH - replacement of oil fired boiler and oil tank Rookwood Phase II - window replacement, roofing and security improvements Stubbington Study Centre fire precaution improvements £100,000-£200,000 Addenbrooke OPH, Gosport - installation of new fire alarm and emergency lighting Thurlston House OPH, Fleet - installation of new fire alarm and emergency lighting Stocklands OPH, Calmore - installation of new fire alarm and emergency lighting Vigo Infant and School Schools - SCOLA 1 cladding (increase NDS allocation) Winchester Cultural Centre - contribution to infrastructure works Wavell School - fire alarm replacement scheme (increase NDS allocation) Yateley School - fire alarm replacement scheme (NDS) Over £200,000 Term engineering contract support - defer funding previously allocated in 2005/06 for boiler replacement schemes at Barncroft Infant, Barncroft Junior, Oak Meadow Primary and Stockbridge Primary to 2006/07 NDS programme to enable £395,000 to be allocated to term engineering contract support (NDS). Icknield Special School - recladding works - increase allocation to £310,000 (NDS) Property Information System - Phase 1 implementation |
| |
|
2 |
Reason(s) |
2.1 |
To enable the necessary funding allocations in 2005/6 and ensure the Built Estate is maintained to a high standard. |
2.2 |
This decision supports Aim 1 of the Corporate Strategy - maximising life opportunities - by providing a high-quality, safe and well-maintained estate for the community to enjoy and Aim 5 - improving services - by providing quality buildings that enable improved service delivery. |
| |
|
3 |
Other options considered and rejected |
| |
|
3.1 |
None. |
| |
|
4 |
Conflicts of interest declared by the decision-maker or other Executive Member consulted |
| |
|
4.1 |
Not applicable |
| |
|
5 |
Dispensation granted by the Standards Committee |
| |
|
5.1 |
Not applicable |
| |
|
6 |
Reason(s) for the matter being dealt with if urgent |
| |
|
6.1 |
Not applicable |
Approved by: |
.......................... |
Date of decision: |
......................... |
| |
Councillor T K Thornber |
|
|