Archived decisions
HAMPSHIRE COUNTY COUNCIL EXECUTIVE MEMBER - ENVIRONMENT: NORTH HAMPSHIRE AND SPATIAL STRATEGY |
ITEM 1 PROJECT APPRAISAL |
_____________________________________________
8 NOVEMBER 2005
_____________________________________________
____________________________________________________________________
PROJECT: |
TRUNK ROAD, FARNBOROUGH - FLOOD ALLEVIATION |
____________________________________________________________________
COMMENCEMENT DATE: |
DECEMBER 2005 |
COMPLETION DATE: |
JANUARY 2006 |
PLANNED YEAR OF START IN ACCORDANCE WITH CAPITAL PROGRAMME: 2005/06 |
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
1. |
FINANCE (Client Department, Director of Property, Business and Regulatory Services [Estates Practice] and County Treasurer) |
____________________________________________________________________
Current |
Capital | ||||
Estimate |
Programme | ||||
(at 2005 |
(at 2005 | ||||
prices) |
prices) | ||||
Capital Expenditure |
£'000 |
£'000 | |||
Land to be purchased |
Nil |
Nil | |||
Construction |
73 |
73 | |||
Fees |
6 |
6 | |||
79 |
79 | ||||
Less developers/ |
65 |
65 | |||
other contributions |
|||||
14 |
14 | ||||
Financial provision for total scheme |
Total Cost | ||||
1. |
From Committees own resources |
||||
(a) Capital programme (as above) |
14 | ||||
(b) Other |
|||||
14 | |||||
2. |
From other resources |
||||
(a) Developer Contributions |
50 | ||||
(b) Developer Contributions (Rushmoor) |
15 | ||||
(c) |
|||||
TOTAL |
79 | ||||
Value of land for this project in HCC ownership £ |
|||||
Variations from capital programme |
|||||
Revenue implications |
£'000 |
% variation | |||
to Committee's | |||||
budget | |||||
Net current expenditure |
1 |
0.001 | |||
Capital charges |
8 |
0.006 | |||
TOTAL net expenditure |
9 |
0.007 | |||
____________________________________________________________________
____________________________________________________________________
2. |
STATEMENT OF NEED/JUSTIFICATION FOR PROJECT (Client Department) |
____________________________________________________________________
2.1 |
This part of Trunk Road has a pedestrian/cycle underpass link between the existing pedestrian/cycle route on Summit Avenue and Fleet Road that passes under the mainline rail track. It has no access to motorised vehicles. |
Targets and Outcomes | |
2.2 2.3 2.4 |
The scheme aims to contribute to the County Council's Local Transport Plan objective to halt the decline of cycling numbers, and to encourage cycle usage and walking in the area, by locally providing an accessible and safe route all year round. Recent surveys have shown that 288 pedestrians/cyclists use the route per day, however for several weeks per year it becomes impassable due to flooded conditions. This causes a detour to be taken of approximately 1.5 miles, and so discourages walking and cycling at these times. The scheme will also address safety concerns by those exiting and entering Fleet Road by reducing the current speed limit from 40 miles per hour (mph) to 30 mph. |
____________________________________________________________________
3. |
ROAD IMPROVEMENT PROPOSAL (Client Department) |
____________________________________________________________________
National/County Network and Policies | |
3.1 |
This scheme improves conditions for pedestrian and cycle safety by better vehicle speed management and the addition of drainage improvements in the underpass. This will facilitate more journeys by foot or bicycle, thus supporting the policies of the LTP, which has been developed to meet national transportation needs. |
Details of Scheme and Design Standards | |
3.2 3.3 3.4 3.5 3.6 3.7 |
The scheme has been designed to meet the objectives of improving accessibility for pedestrians, cyclists and the mobility impaired. The scheme comprises raising the pedestrian/cycleway under the underpass by a height of 600 millimetres, whilst retaining the existing height at the edges to act as drainage ditches. From these, a replacement section of drainage pipe will run out under Fleet Road to improve water flows into the existing highway drainage network. This will remove the risk of flooding in the underpass and keep it open all year round for its users. Guard railing will be put in place to avoid user slippage into the drainage ditches by the routes users. In addition, lighting will be included in the underpass and the existing 30 mph speed limit will be extended along Fleet Road to aid the safety of pedestrians and cyclists when crossing at this point. A location plan is attached and a detailed drawing will be displayed at the meeting. The proposals meet current National and County standards for highway improvement schemes, and conform to the recommendations of the Safety Audit. |
Environmental Impact | |
3.8 |
The scheme will contribute to a safer and improved environment for cyclists, pedestrians and other vulnerable users. There are no adverse environmental impacts. |
Land Requirements | |
3.9 |
No land acquisition required. All works to be confined within existing public highway limits. |
Statutory Procedures | |
3.10 |
Traffic Regulation Orders are required to implement the change in the speed limit. These will be advertised by Rushmoor Borough Council. |
Public Consultation | |
3.11 3.12 |
No public consultation was carried out regarding the drainage works as there are no residential properties within close proximity to the scheme; there will also be no negative impacts on the local community. The need for an extension to the 30 mph speed zone has been identified during liaison between both Parsonage Farm and Guillemont Schools as the route is used by their pupils and parents. Railtrack has been consulted on the proposals and raises no objection. |
Local Member's View | |
3.13 |
The local Member, Councillor Leversha, supports the proposal. |
Impact Assessments | |
3.14 3.15 |
The scheme will improve the conditions for pedestrians and cyclists in the area by ensuring that their travel route remains open all year round. The route can also be used by disabled people with mobility wheelchairs. Assessment of the Race Relations (Amendment) Act has also been made in the development of this scheme but the proposal is not expected to compromise equalities in terms of race or gender. |
Maintenance Implications | |
3.16 |
The revenue implications of this proposal will be taken into account in the setting of the annual budget. |
Crime and Disorder Act 1998 | |
3.17 |
The provisions of this Act have no impact on this proposal. |
Sustainability | |
3.18 |
The scheme will improve the environment for walking and cycling. |
____________________________________________________________________
4. |
ROAD IMPROVEMENT - ALTERNATIVES CONSIDERED |
____________________________________________________________________
4.1 |
The option to do nothing was considered, however this was not perceived to be acceptable in terms of providing reasonable facilities for its users. |
___________________________________________________________________
Recommendation
That this Project Appraisal for the implementation of drainage improvements on the shared pedestrian and cycle path underpass between the A327 Summit Avenue and Fleet Road, Farnborough, and the extension of the existing 30 miles per hour limit on Fleet Road, at an estimated cost of £79,000 predominantly developer funded, be approved.
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
Trunk Road, Farnborough |
Environment Department Room 415 |
632Rpt/MG