Archived decisions
Hampshire County Council Basingstoke and Deane Highway and Transport Advisory Panel 9 November 2005 Passenger Transport Report Report of the Director of Environment |
Item 12 |
Contact: Andy Berncastle, ext 6389 email: [email protected]
1. Summary
1.1 This report details the position on local bus service support this year, describes the evolving Passenger Transport Strategy for the future and provides updates on the renewal of contracts for supported bus services and on Quality Bus Partnership (QBP) works.
2. Local Bus Service Support - Action in 2005/06
2.1 The County Council set its budget for the support of subsidised bus services for 2005/06 at the same level as 2004/05, adjusted for inflation. Regrettably, despite continued increases in funding in recent years, this budget remains under pressure due to sharp cost increases in the bus industry. The amount of funding available is not sufficient to meet the costs of all supported local bus services in the county. This means that financial support for some bus services or parts of services is being withdrawn.
2.2 In order to maximise value for money for the county's taxpayers, the routes which have been nominated for withdrawal are those which are used least or those which cost the most per passenger to support.
3. Passenger Transport Strategy
3.1 The Passenger Transport Strategy will form an integral part of the second Local Transport Plan (LTP), to be submitted to Government in March 2006. The proposed LTP needs to be realistic and so recognise that the car will be the dominant mode of travel for the foreseeable future and that modal shift will only come when congestion increases significantly. Long term proposals to increase bus and rail services as congestion creates a market for them are complemented in the meantime by improvements to the busiest bus routes, often in urban areas.
3.2 A balanced set of measures are proposed to improve transport and so enhance quality of life by:
(i) improving accessibility to services;
(ii) tackling congestion;
(iii) improving transport-related air quality; and
(iv) improving road safety.
Accessibility
3.3 The LTP is also realistic about accessibility. The Government has provided an accessibility auditing database, known as Accession. This aims to model theoretical journey times to key services by a combination of walking and public transport. However initial results must be viewed with caution due to problems with unreliable data and software faults. Some areas that are theoretically inaccessible by public transport may have limited problems due to high levels of car ownership. Equally, some areas may have worse accessibility than suggested by Accession, because of timetabling problems, cost, or lack of information.
3.4 The LTP approach takes a more holistic and realistic approach to accessibility than required by the Government. In particular, the LTP:
(i) considers accessibility to a wider range of services;
(ii) investigates actual rather than theoretical accessibility; and
(iii) considers non-transport measures to improve accessibility, such as bringing services to people.
3.5 The role of scheduled or demand-responsive bus services needs to be carefully judged as these can be very expensive to provide to remote locations or for infrequently used services such as hospital visits.
3.6 The Passenger Transport Strategy is therefore evolving as more information becomes available. It is intended that the results of pilot studies will be available to inform the development of the full LTP.
New Approach to Service Provision
3.7 To best match service provision to passenger needs, work is progressing with consultants on an access and demand model which enables the best mix of conventional, flexible and community-based transport to be delivered. The model is initially being developed as a pilot in the Basingstoke and Alton areas. The model will assist in answering some fundamental questions including:
(i) Are travel needs being met?
(ii) Is the current allocation of funds correct?
(iii) Does it provide best value for money?
3.8 The model will also enable the assessment of proposals aimed at modal shift and offer solutions to the accessibility problems identified by Accession. It will help optimise service provision and help offset rising cost pressures whilst providing a framework for strategic network development in the future.
4. Contracts for Supported Bus Services
4.1 New four-year contracts started on 31 July 2005 for most of the non-commercial bus services in Basingstoke and Deane. Support from the Borough Council, which exceeded the County Council's subsidy criteria, enabled the retention of the following rural services:
(i) 36 Baughurst/Stoney Heath-Basingstoke;
(ii) 54 Hannington-Basingstoke; and
(iii) 310 Steventon-Basingstoke.
5. Basingstoke Quality Bus Partnership: Route 3 - East Popley to South Ham
5.1 Under the umbrella QBP between Hampshire County Council, Basingstoke and Deane Borough Council and Stagecoach, a route-specific QBP is being developed for Route 3, which operates between East Popley, the town centre and South Ham. Improvements will include raised boarding kerbs, bus stop clearways, new high quality bus stop poles with integrated information displays and, where required, new bus shelters. Real-Time Passenger Information displays will be introduced at key stops. Low-floor accessible buses have recently been introduced to the route and strong patronage growth is anticipated. Works will commence in early 2006, at a cost of £200,000, funded from the capital programme.
6. Impact Assessments
6.1 This report provides a position statement only, therefore an impact assessment, in terms of the Race Relations (Amendment) Act, has not been undertaken.
Recommendation
That this report be noted
Section 100 D - Local Government Act 1972 - background papers | |
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report. | |
NB the list excludes: | |
1. |
Published works. |
2. |
Documents which disclose exempt or confidential information as defined in the Act. |
TITLE |
LOCATION |
Correspondence files and records of tenders and works. |
Environment Department Passenger Transport Group |
610/AB