Archived decisions

Appendix 1a-c

   

Appendix 1 (a)

Education Service (Schools Block)

   
       

Revised Budget 2005/06

   
       

Calculation of the Cash Limit for the Revised Budget 2005/06

   
       

The following table shows the progression from the original budget for 2005/06 to the

 

cash limit for the revised budget 2005/06. Both are at estimated outturn prices

 

2005/06.

   
       
   

£'000

£'000

Original budget 2005/06 at outturn prices

 

640,218

Transfers to/from other services

 

-

Inter-block movement (reassessment)

 

412

       

=

Adjusted original budget

 

640,630

       

Inflation

   

Provision increased since the original budget for

   

-

business rates

 

236

       

Other variations

   

-

County Council contribution towards standards fund

   
 

schemes brought forward

 

1,690

-

teachers' sickness and maternity cover - 2004/05 over

   
 

spend brought forward

 

-247

-

variation in expenditure financed by government grants:

   
 

o teachers' pay thresholds

1,585

 
 

o standards fund

3,565

 
 

o schools standards grant

40

 
 

o early years

863

 
 

o school meals grant

1,350

 
 

o transitional support grant

3,455

 
 

o school milk grant

-3

 
     

10,855

-

inter-block movement (reassessment)

 

-

-

inter-committee adjustment

 

-

       
     

653,164

 

Projected excess expenditure

   
       

=

Cash limit for the revised budget 2005/06

 

653,164

       
       
       
       
       
   

Appendix 1 (b)

Education Service (LEA Block)

   
       

Revised Budget 2005/06

   
       

Calculation of the Cash Limit for the Revised Budget 2005/06

   
       

The following table shows the progression from the original budget for 2005/06 to the

 

cash limit for the revised budget 2005/06. Both are at estimated outturn prices

 

2005/06.

   
       
   

£'000

£'000

Original budget 2004/05 at outturn prices

 

62,948

Transfers to/from other services

 

1,179

Inter-block movement (reassessment)

 

-412

Youth Service initiatives

 

288

Procurement savings

 

-135

Pay awards 2004/05

 

42

=

Adjusted original budget

 

63,910

       

Inflation

   

Provision deleted since the original budget for

   

-

business rates

 

-

       

Other variations

   

-

County Council contribution towards standards fund

   
 

schemes brought forward

 

-

-

variation in expenditure financed by government grants:

   
 

o standards fund

182

 
     

182

 

modernisation, efficiency and restructuring

 

327

-

inter-block movement (reassessment)

 

-

-

carry forward of 2004/05 under spending

 

402

       
     

64,821

 

Projected excess expenditure

   
       

=

Cash limit for the revised budget 2005/06

 

64,821

       
       
       
       
   

Appendix 1 (c)

Children's Social Care services

   
       

Revised Budget 2005/06

   
       

Calculation of the Cash Limit for the Revised Budget 2005/06

   
       

The following table shows the progression from the original budget for 2005/06 to the

 

cash limit for the revised budget 2005/06. Both are at estimated outturn prices

 

2005/06.

   
       
   

£'000

£'000

       

Original budget 2005/06 at outturn prices

 

51,312

Procurement savings

   
 

Agency

-42

 
 

Other

-46

 
     

-88

=

Adjusted original budget

 

51,224

       

Other variations

   
 

Redistribution of Gershon targets within Social Services Department

 

361

 

Share of centrally held contingency against 2004/05 overspend

 

308

 

Variations in expenditure financed by government grants:

   
 

CAMHS grant movement

357

 
 

Carers grant movement

2

 
     

377

       
 

Projected excess expenditure

 

52,270

       

=

Cash limit for the revised budget 2005/06

 

52,270

       
       
 

Check total

 

717985