BUSINESS PLAN / TIMELINE

DATE : 14/11/05

SERVICE NAME : HAMPSHIRE FAMILY

MENTORING

Circulation :- Steve Love

Janet Féat

Graham Wright

Nick Ralph

Michelle Lee-Izu

Activity

Time Frame

Lead

Comments

Advert for CSM

8th August

MLI

Recruitment drive not successful. Re-advertised October 2005.

Shortlist for CSM

30th August

NR, JF, MLI

Shortlisted 4 candidates 18th October 2005.

Reviewing / Planning meeting

30th August

SL

Meeting went ahead.

Interview of CSM

12th September

MLI

Took place on the 31st October 2005 recruited Felicity Keeping.

Offer letter to CSM

CRB Check

Letter of appointment

6th November 2005

ASAP

ASAP

MLI

MLI

MLI

Letter sent subject to CRB and references.

To be sent week beginning 14/11/05.

Send as soon as CRB and references received.

Completion of draft service specification.

30th August

MLI

Circulated: being negotiated with Hampshire Contract Section and PDCSR

Activity

Time frame

Lead

Comments

Completion of timeline.

30th August

MLI

Circulate to full Partnership group. Amended 15/11/05.

Sign off all above.

End Sept 2005

Full

Partnership

Timeline and budgets to be re-agreed 15/11/05.

Partnership contract to be agreed ASAP.

Collation of all relevant data in preparation of CSM induction.

November 2005

MLI

All partners to assist in drawing up an induction programme.

Develop a communication strategy.

November 2005

MLI

To include :-

a) questions and answer sheet

b) information sharing protocol

c) agreed media briefing.

Informal networking with Churches and relevant related groups with PDSR

On going

NR

 

Commence initial awareness raising to attract mentors.

November 2005

NR

MLI

 

Activity

Time frame

Lead

Comments

Advertisement/recruitment of volunteers

Commence Jan 06 on going

CSM

 

Development of training materials

Jan / Feb 06

CSM

Liaison with Russell Martin and others.

Drawing up policies and procedures

Commence beginning Jan 06

CSM

Key policies and procedure to be in place by end Feb 06

1st training event

End of February beginning of March 06

CSM

 

3 volunteers to be recruited and trained and introduced to families.

April 06

CSM

 

3 further volunteers recruited and trained and introduced to families

May 06

CSM

6 volunteers in total

4 further volunteers recruited, trained and introduced to families

June 06

CSM

10 volunteers and 10 families by end of August 06.

Activity

Time frame

Lead

Comments

Management / Steering group established.

April 06

All partners

To include all key partners to identify other key players, draw up terms of reference.

Support Church groups to apply for funding for 1st Co-ordinator.

April 06

CSM

 

Business Plan for 06/07

March 06

CSM

To be agreed by partners.

Initial six month Review

May 06

Key partners.

 

Recruitment of mentors and matching to families.

November 06

CSM

Recruit a further 10 volunteers making 20 in total.

Evaluation of service to date.

August 06

CSM

Short report on quantitative and qualitative evidence.

Decision on continuation of service development and roll out.

September 06

All funding partners