Executive Member - Education Item 8 15 December 2005 Major Projects Status Report
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 E-mail: [email protected]
1. Summary
1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.
1.2 Appendix 3 shows those capital projects for which an allocation has been made in the Education Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.
2. Completed Schemes
2.1 Since the October 2005 meeting of the Executive Member - Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:
SCHOOL COMPLETION DATE
Alton Community School
- Building works September 2005
- Demolition and Landscaping November 2005
Brune Park Community November 2005
Chiltern Primary School November 2005
Neville Lovett Community School October 2005
Nightingale Primary - Building works November 2005
(MUGA to be undertaken Easter 2006)
Toynbee/Hayling/Noadswood October 2005.
3. Additional Works and Funding Added Post Contract
3.1 The following schemes have had further funding added to the contract for specific additional works.
3.2 Brookfield Community School
An additional £13,000 has been added to the major scheme on site at the above school from the Policy and Resources NDS Condition fund 2005/06. This will enable an inner courtyard to be raised to the same level as the surrounding buildings to comply with DDA regulations. Work was due to complete during late October 2005, however, due to the additional works, it is anticipated that work will now complete during December 2005.
3.3 South Baddesley CE (C) Primary School
Additional funding of £31,921, excluding fees, has been added to the major scheme currently underway at this school to provide a SEN room. Contributions have come from the school of £10,000, with £11,207 from the Education 2005/06 Capital Programme contingency and £10,714 from the Policy and Resources 2005/06 Capital Repairs budget.
3.4 Staunton Park Community School
Additional funding of £3,250 has been added by the school to the current major scheme at this school to provide a Healthy Living Centre. The additional funding has provided for sound system infrastructure and an induction loop.
4. Additional Works and Funding added at Pre Contract Stage
4.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.
4.2 Additional funding has come from various sources including increased Education Capital Programme allocations and inflation and tolerance adjustments; additional school funding for specific additional requested works and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.
5. Current Position
5.1 This section gives the summarised position of the major projects, which have already been approved by the Executive Members for Policy and Resources and Education. Those schemes with works on site are reported as being financially on target unless otherwise indicated elsewhere in this report.
5.2 Brune Park Community School
The major scheme at this school to provide a dance studio and dining hall was due for completion during October 2005, however, due to unforeseen works associated with asbestos removal and underground services, along with a slight programme delay by the main contractor, the work was completed during late November 2005.
5.3 Calmore Infant School
The major scheme at this school to provide an integrated yet independent Early Years Centre was due to complete during late October 2005. A Partial Possession of the building was given in early November 2005 and the accommodation was available for use by the school at that time. There are, however, a number of outstanding snagging items which still need to be addressed by the contractor and it is anticipated that a full Certificate of Practical Completion will be issued during December 2005.
Conclusion
The details of the major capital projects outlined in this report will provide greatly enhanced school accommodation and facilities.
Recommendations
1. That the position of the major projects being undertaken by the Director of Property, Business and Regulatory Services be noted.
2. That the additional funding added to the major capital projects at pre contract stage, previously approved by the Executive Members' Education and Policy and Resources at design project appraisal stage, be approved.
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS
Tender schedules
Project Appraisals
MAJOR PROJECT STATUS REPORT Appendix 1
School |
Current Status |
Start |
Complete |
Funding/ * Contract Sum £ |
Source of Funding £ |
Alton Community Infant School - three classroom, staff room and link corridor extension - demolition and external works |
Complete Complete |
Dec 04 Oct 05 |
Sep 05 Nov 05 |
* 859,888 |
Education Capital 04/05 779,888 P&R NDS Condition 04/05 50,000 P&R Capital Repairs 04/05 30,000 859,888 |
Blackfield Primary School - creation of 2.5fe Primary school by extending and remodelling existing Junior school |
On site |
Dec 05 |
Aug 06 |
* 1,498,208
|
Education Capital 05/06 1,185,345 Edu Early Years 05/06 34,483 Education contingency 46,552 School 231,828 1,498,208 |
Brookfield Community School, Sarisbury Green - internal refurbishment |
On site |
May 05 |
Dec 05 |
* 957,394 add 13,000 970,934 |
Education Capital 04/05 375,000 Contingency 54,133 NDS Modernisation 05/06 78,261 NDS Condition fund 04/05 450,000 NDS Condition fund 05/06 13,000 970,394 |
Broughton Primary School, Stockbridge -new kitchen |
Tender |
Jan 06 |
May 06 |
240,000 |
Education Capital 05/06 220,000 School 20,000 240,000 |
Brune Park Community School, Gosport - Extension to provide a new dance studio and dining hall |
Complete |
Jan 05 |
Nov 05 |
* 1,264,484 |
Education Capital 04/05 1,116,484 School - Devolved Capital 80,000 P&R NDS Condition 04/05 50,000 Underspend from previous phase of work 18,000 1,264,484 |
Calmore Infant School - internal alterations to form an integrated yet independent Early Years Centre |
Partial Possession Practical Completion |
May 05 |
Nov 05 Dec 05 |
* 473,552 |
Education Capital 04/05 377,000 School 96,552 473,552 |
Chiltern Primary School, Basingstoke - Worting School amalgamation |
Enabling works Complete |
Jul 04 Apr 05 |
Aug 04 Nov 05 |
* 123,475 * 1,377,678 1,501,153 |
Education Capital 04/05 1,463,153 SAI 04/05 22,000 P&R NDS Condition 04/05 6,000 School 10,000 1,501,153 |
Costello Technology College, Basingstoke - replacement maths / technology teaching block |
On site |
Nov 05 |
Feb 07 |
* 5,200,434 |
P&R Fire Re'statem't 05/06 4,870,434 Education Capital 05/06 250,000 P&R NDS Condition 05/06 80,000 5,200,434 |
Court Moor School, Fleet - refurbish and extend Youth Block |
Design |
Feb 06 |
Jun 06 |
242,000 |
Edu - Youth Service 05/06 138,000 Edu - Early Years 05/06 59,000 School - Connexions 25,000 P&R NDS Condition 05/06 20,000 242,000 |
Cove Junior School, Farnborough - three classroom extension, Music/Drama and kiln room |
On site |
Sep 05 |
Apr 06 |
* 804,202 |
Education Capital 05/06 717,000 School 54,202 P&R NDS Condition 05/06 33,000 804,202 |
The Crescent Primary School, Eastleigh - two classroom and library extension |
On site |
Jul 05 |
Mar 06 |
* 827,050 |
Education Capital 05/06 628,550 School 53,500 HC3S 20,000 P&R NDS Condition 05/06 125,000 827,050 |
Crestwood Community School, Eastleigh - Community Sports Hall, drama studio and Fitness Suite |
On site |
Oct 05 |
Jun 06 |
* 3,132,183 |
Capital Programme 05/06 3,132,183 |
Eggars School, Alton - IT block, Sports Hall and internal refurbishment |
On site |
Mar 05 |
Dec 05 |
* 2,508,232 |
Education Capital 03/04 1,020,000 NDS Modernisation 03/04 65,000 Treloar College Funding 288,000 School 271,232 Eggars Trust Fund 688,000 P&R NDS Fire Alarm 04/05 76,000 P&R Landlord contribution 70,000 P&R External Works 04/05 30,000 2,508,232 |
Grayshott CE (C) Primary - single storey extension and internal alterations |
On site |
Oct 05 |
May 06 |
* 525,000 |
Education Capital 05/06 365,000 School 160,000 525,000 |
The Henry Cort Community College, Fareham - extension to staff room, two new offices, internal remodelling and refurbishment |
On site |
Aug 05 |
Mar 06 |
* 395,948 |
Education Capital 05/06 97,948 School 262,000 P&R NDS Condition 05/06 15,000 P&R Capital Repairs 05/06 2,000 P&R L'lords M. Works 05/06 12,000 P&R Ext. Landscaping 05/06 7,000 395,948 |
Hollywater School, Bordon - new special school |
On site |
May 05 |
Dec 06 |
* 6,088,472 |
Edu Cap / TCF 05/06 4,887,472 P&R Capital Repairs 05/06 629,000 P&R Capital Receipt 572,000 6,088,472 |
John Hunt of Everest Community school, Basingstoke - New School and Youth facility |
Enabling Complete Main Contract |
Aug 05 Jan 06 |
Nov 05 Apr 07 |
* 1,106,416 20,506,256 21,612,672
|
Capital Receipts 13,257,896 Developer's Contribution 2,467,201 B&D Borough Council 2,110,595 County Council 3,776,980 21,612,672 |
Lakeside School, Chandlers Ford - refurb. boarding accommodation; demolish surplus boarding house; new teaching block and refurbish teaching accommodation |
Enabling Phase 1 Phase 2 |
Jul 04 Nov 04 Jul 05 |
Aug 04 Apr 05 May 06 |
* 196,000 * 568,000 * 1,301,254 * 2,065,254 |
Education Mod'tion 04/05 1,565,000 Education Capital 04/05 261,254 P&R NDS Condition 04/05 49,000 P&R Fire Precautions 04/05 190,000 2,065,254 |
Minstead Rural Study Centre, Lyndhurst - new residential building, extension to schoolhouse and removal of temps |
On site |
Dec 05 |
Jul 06 |
* 1,228,000 |
Education Capital 05/06 519,000 Temp Classroom Hire 05/06 28,000 New Opportunities Fund 487,000 Study Centre 100,000 New Forest District Council 26,000 P&R Landlords contribution 68,000 1,228,000 |
Mountbatten School and Language College - new Staff Room, Inclusion room and Multi-agency space |
On site |
Jul 05 |
Feb 06 |
* 449,000 |
Edu. Capital - SEED 05/06 117,000 School 332,000 449,000 |
Netley Marsh Infant - new classrooms and extended hall |
On site |
Aug 05 |
Feb 06 |
* 678,312 |
Education Capital 0506 595,381 School 62,931 P&R NDS Condition 05/06 20,000 678,312 |
Neville Lovett Community School, Fareham - new entrance foyer and reception; refurbishment of food tech area and hearing impaired unit. |
Complete |
Jan 05 |
Oct 05 |
* 597,642 |
SAI 04/05 274,700 NDS Modernisation 04/05 111,300 School 174,000 P&R NDS Condition 05/06 37,642 597,642 |
Newtown Soberton Infant School - new Hall and internal adaptations to create a Nursery Unit |
Tender Preparation |
Feb 06 |
Hall - Sep 06 Nursery - Oct 06 |
541,000 |
NDS Modernisation 05/06 438,000 School 103,000 541,000 |
Nightingale Primary School, Eastleigh - extension to provide permanent classroom accommodation - MUGA |
Complete |
Feb 05 Easter 06 |
Nov 05 Easter 06 |
* 1,196,477 |
NDS Modernisation 04/05 391,304 Contingency 55,173 Capital Receipt 646,552 School 103,448 1,196,477 |
Priestlands Secondary School, Lymington -music/drama facility and dining extension |
On site |
May 05 |
Dec 05 |
* 1,615,665 |
Education Capital 04/05 1,069,828 School 277,000 Specialist School Status 04/05 100,000 P&R NDS Condition 05/06 20,000 Transfer of Fees 148,837 1,615,665 |
Rachel Maddocks School, Waterlooville - extension, internal alterations, refurbishment and repair |
Tender |
Jan 05 |
Apr06 |
349,000 |
Education Capital 05/06 204,000 School 137,000 P&R Capital Repairs 05/06 8,000 349,000 |
Saint Lawrence CE (C) Primary - new hall, kitchen, link building and internal refurbishment |
On site |
Oct 05 |
Apr 06 |
* 599,485 |
Education Capital 05/06 599,485 |
South Baddesley CE (C) Primary - phase 1 - new classroom and staffroom - phase 2 - new hall and car park |
Complete On site |
May 05 Sep 05 |
Oct 05 Mar 06 |
* 424,722 * 484,872 add 31,921 941,515 |
Education Capital 04/05 391,828 Education contingency 11,207 School 125,653 NDS Condition 05/06 65,000 P&R Capital Repairs 05/06 87,827 P&R Capital 05/06 260,000 941,515 |
Staunton Park Community - Healthy Living Centre |
On site |
Jul 05 |
Feb 06 |
* 542,862 add 3,250 546,112 |
NDS Modernisation 04/05 70,862 School 53,250 Sport England 422,000 546,112 |
The Toynbee Community College, Chandlers Ford - new Multi-Purpose Suite |
On site |
Nov 05 |
May 06 |
* 508,620 |
School 265,517 P&R Capital 05/06 200,000 Eastleigh Borough Council 43,103 508,620 |
Waterside Primary School, Hythe - remodel and refurbish existing school; construct classroom block and early years unit |
On site |
Nov 05 |
Jul 06 |
* 1,913,815 |
Education Capital 05/06 1,539,462 School 125,000 P&R Capital Repairs 05/06 25,246 P&R NDS Condition 05/06 224,107 1,913,815 |
West Tytherley C of E Primary, Salisbury - classroom extension to replace temporary accommodation |
Design |
Apr 06 |
Nov 06 |
851,000 |
Education Capital 05/06 811,000 School 40,000 851,000 |
Whitchurch CE (C) Primary - two new classrooms, ICT Suite and corridor |
On site |
Jul 05 |
Feb 06 |
* 515,000 |
Education Capital 04/05 431,000 School 84,000 515,000 |
SPECIALIST SCHOOLS ACCOMMODATION PROGRAMME 2005/06 Appendix 2 | |||||
School |
Current Status |
Start |
Complete |
Funding / * Contract Sum |
Source of Funding £ |
Package 1 - - Toynbee School - The Hayling School - Noadswood School
- Aldworth Science College |
Complete Design |
Aug 05 Jan 06 |
Oct 05 Mar 06 |
* 311,369 |
NDS Modernisation 04/05 311,369 |
Appendix 3
Other Schemes in the Education Capital Programme
The following schemes are included in the Education 2005/06 Capital Programme and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member Education or Policy and Resources:
School Allocation
(excluding fees)
£'000
PRIMARY
North Basingstoke schools |
776 |
Whiteley / Western Wards |
1,240 |
2,016 |
SPECIAL
Sundridge School, Havant |
5,074 |
5,074 |
NDS MODERNISATION
Curdridge Primary |
618 |
Micheldever Primary |
1,240 |
Stanmore Primary |
217 |
The Bridge Centre |
830 |
2,905 | |
TOTAL |
9,995 |
I/PB&R/Committees/MajorMinorSelf-FundedApprovedbyExMem/MajorProjects