Archived decisions

Hampshire County Council

Executive Member - Education Item 8

15 December 2005

Major Projects Status Report

Report of the Director of Property, Business and Regulatory Services

 

How the conclusion in this report fits with the Corporate Strategy

This scheme will impact on the delivery of the following Corporate Aims

Aim 1 - maximising life opportunities - by providing new and/or improved teaching accommodation to be enjoyed by the schools.

Aim 5 - improving services - by providing good quality buildings that enable service delivery.

1. Summary

1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

1.2 Appendix 3 shows those capital projects for which an allocation has been made in the Education Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.

2. Completed Schemes

2.1 Since the October 2005 meeting of the Executive Member - Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:

    SCHOOL COMPLETION DATE

                      Alton Community School

                      - Building works September 2005

                      - Demolition and Landscaping November 2005

                      Brune Park Community November 2005

                      Chiltern Primary School November 2005

                      Neville Lovett Community School October 2005

                      Nightingale Primary - Building works November 2005

                      (MUGA to be undertaken Easter 2006)

                      Toynbee/Hayling/Noadswood October 2005.

3. Additional Works and Funding Added Post Contract

3.1 The following schemes have had further funding added to the contract for specific additional works.

3.2 Brookfield Community School

      An additional £13,000 has been added to the major scheme on site at the above school from the Policy and Resources NDS Condition fund 2005/06. This will enable an inner courtyard to be raised to the same level as the surrounding buildings to comply with DDA regulations. Work was due to complete during late October 2005, however, due to the additional works, it is anticipated that work will now complete during December 2005.

3.3 South Baddesley CE (C) Primary School

      Additional funding of £31,921, excluding fees, has been added to the major scheme currently underway at this school to provide a SEN room. Contributions have come from the school of £10,000, with £11,207 from the Education 2005/06 Capital Programme contingency and £10,714 from the Policy and Resources 2005/06 Capital Repairs budget.

3.4 Staunton Park Community School

      Additional funding of £3,250 has been added by the school to the current major scheme at this school to provide a Healthy Living Centre. The additional funding has provided for sound system infrastructure and an induction loop.

4. Additional Works and Funding added at Pre Contract Stage

4.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

4.2 Additional funding has come from various sources including increased Education Capital Programme allocations and inflation and tolerance adjustments; additional school funding for specific additional requested works and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.

5. Current Position

5.1 This section gives the summarised position of the major projects, which have already been approved by the Executive Members for Policy and Resources and Education. Those schemes with works on site are reported as being financially on target unless otherwise indicated elsewhere in this report.

5.2 Brune Park Community School

        The major scheme at this school to provide a dance studio and dining hall was due for completion during October 2005, however, due to unforeseen works associated with asbestos removal and underground services, along with a slight programme delay by the main contractor, the work was completed during late November 2005.

5.3 Calmore Infant School

      The major scheme at this school to provide an integrated yet independent Early Years Centre was due to complete during late October 2005. A Partial Possession of the building was given in early November 2005 and the accommodation was available for use by the school at that time. There are, however, a number of outstanding snagging items which still need to be addressed by the contractor and it is anticipated that a full Certificate of Practical Completion will be issued during December 2005.

Conclusion

    The details of the major capital projects outlined in this report will provide greatly enhanced school accommodation and facilities.

Recommendations

1. That the position of the major projects being undertaken by the Director of Property, Business and Regulatory Services be noted.

2. That the additional funding added to the major capital projects at pre contract stage, previously approved by the Executive Members' Education and Policy and Resources at design project appraisal stage, be approved.

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the act.

                    TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS

      Tender schedules

      Project Appraisals

MAJOR PROJECT STATUS REPORT Appendix 1

School

Current Status

Start

Complete

Funding/

* Contract Sum

£

Source of Funding

£

Alton Community Infant School

- three classroom, staff room and link corridor extension

- demolition and external works

Complete

Complete

Dec 04

Oct 05

Sep 05

Nov 05

* 859,888

Education Capital 04/05 779,888

P&R NDS Condition 04/05 50,000

P&R Capital Repairs 04/05 30,000

859,888

Blackfield Primary School

- creation of 2.5fe Primary school by extending and remodelling existing Junior school

On site

Dec 05

Aug 06

* 1,498,208

Education Capital 05/06 1,185,345

Edu Early Years 05/06 34,483

Education contingency 46,552

School 231,828

1,498,208

Brookfield Community School, Sarisbury Green

- internal refurbishment

On site

May 05

Dec 05

* 957,394

add 13,000

970,934

Education Capital 04/05 375,000

Contingency 54,133

NDS Modernisation 05/06 78,261

NDS Condition fund 04/05 450,000

NDS Condition fund 05/06 13,000

970,394

Broughton Primary School, Stockbridge

-new kitchen

Tender

Jan 06

May 06

240,000

Education Capital 05/06 220,000

School 20,000

240,000

Brune Park Community School, Gosport

- Extension to provide a new dance studio and dining hall

Complete

Jan 05

Nov 05

        * 1,264,484

Education Capital 04/05 1,116,484

School - Devolved Capital 80,000

P&R NDS Condition 04/05 50,000

Underspend from previous

phase of work 18,000

              1,264,484

Calmore Infant School

- internal alterations to form an integrated yet independent Early Years Centre

Partial Possession

Practical

Completion

May 05

Nov 05

Dec 05

* 473,552

Education Capital 04/05 377,000

School 96,552

473,552

Chiltern Primary School, Basingstoke

- Worting School amalgamation

Enabling works

Complete

Jul 04

Apr 05

Aug 04

Nov 05

* 123,475

        * 1,377,678

1,501,153

Education Capital 04/05 1,463,153

SAI 04/05 22,000

P&R NDS Condition 04/05 6,000

School 10,000

1,501,153

Costello Technology College, Basingstoke

- replacement maths / technology teaching block

On site

Nov 05

Feb 07

* 5,200,434

P&R Fire Re'statem't 05/06 4,870,434

Education Capital 05/06 250,000

P&R NDS Condition 05/06 80,000

5,200,434

Court Moor School, Fleet

- refurbish and extend Youth Block

Design

Feb 06

Jun 06

242,000

Edu - Youth Service 05/06 138,000

Edu - Early Years 05/06 59,000

School - Connexions 25,000

P&R NDS Condition 05/06 20,000

242,000

Cove Junior School, Farnborough

- three classroom extension, Music/Drama and kiln room

On site

Sep 05

Apr 06

* 804,202

Education Capital 05/06 717,000

School 54,202

P&R NDS Condition 05/06 33,000

804,202

The Crescent Primary School, Eastleigh

- two classroom and library extension

On site

Jul 05

Mar 06

* 827,050

Education Capital 05/06 628,550

School 53,500

HC3S 20,000

P&R NDS Condition 05/06 125,000

827,050

Crestwood Community School, Eastleigh

- Community Sports Hall, drama studio and Fitness Suite

On site

Oct 05

Jun 06

* 3,132,183

Capital Programme 05/06 3,132,183

Eggars School, Alton

- IT block, Sports Hall and internal refurbishment

On site

Mar 05

Dec 05

* 2,508,232

Education Capital 03/04 1,020,000

NDS Modernisation 03/04 65,000

Treloar College Funding 288,000

School 271,232

Eggars Trust Fund 688,000

P&R NDS Fire Alarm 04/05 76,000

P&R Landlord contribution 70,000

P&R External Works 04/05 30,000

2,508,232

Grayshott CE (C) Primary

- single storey extension and internal alterations

On site

Oct 05

May 06

* 525,000

Education Capital 05/06 365,000

School 160,000

525,000

The Henry Cort Community College, Fareham

- extension to staff room, two new offices, internal remodelling and refurbishment

On site

Aug 05

Mar 06

* 395,948

Education Capital 05/06 97,948

School 262,000

P&R NDS Condition 05/06 15,000

P&R Capital Repairs 05/06 2,000

P&R L'lords M. Works 05/06 12,000

P&R Ext. Landscaping 05/06 7,000

395,948

Hollywater School, Bordon

- new special school

On site

May 05

Dec 06

* 6,088,472

Edu Cap / TCF 05/06 4,887,472

P&R Capital Repairs 05/06 629,000

P&R Capital Receipt 572,000

6,088,472

John Hunt of Everest Community school, Basingstoke

- New School and Youth facility

Enabling

Complete

Main Contract

Aug 05

Jan 06

Nov 05

Apr 07

* 1,106,416

20,506,256

21,612,672

Capital Receipts 13,257,896

Developer's Contribution 2,467,201

B&D Borough Council 2,110,595

County Council 3,776,980

21,612,672

Lakeside School, Chandlers Ford

- refurb. boarding accommodation; demolish surplus boarding house; new teaching block and refurbish teaching accommodation

Enabling

Phase 1

Phase 2

Jul 04

Nov 04

Jul 05

Aug 04

Apr 05

May 06

* 196,000

* 568,000

* 1,301,254

* 2,065,254

Education Mod'tion 04/05 1,565,000

Education Capital 04/05 261,254

P&R NDS Condition 04/05 49,000

P&R Fire Precautions 04/05 190,000

2,065,254

Minstead Rural Study Centre, Lyndhurst

- new residential building, extension to schoolhouse and removal of temps

On site

Dec 05

Jul 06

* 1,228,000

Education Capital 05/06 519,000

Temp Classroom Hire 05/06 28,000

New Opportunities Fund 487,000

Study Centre 100,000

New Forest District Council 26,000

P&R Landlords contribution 68,000

1,228,000

Mountbatten School and Language College

- new Staff Room, Inclusion room and Multi-agency space

On site

Jul 05

Feb 06

* 449,000

Edu. Capital - SEED 05/06 117,000

School 332,000

449,000

Netley Marsh Infant

- new classrooms and extended hall

On site

Aug 05

Feb 06

* 678,312

Education Capital 0506 595,381

School 62,931

P&R NDS Condition 05/06 20,000

678,312

Neville Lovett Community School, Fareham

- new entrance foyer and reception; refurbishment of food tech area and hearing impaired unit.

Complete

Jan 05

Oct 05

* 597,642

SAI 04/05 274,700

NDS Modernisation 04/05 111,300

School 174,000

P&R NDS Condition 05/06 37,642

597,642

Newtown Soberton Infant School

- new Hall and internal adaptations to create a Nursery Unit

Tender Preparation

Feb 06

Hall -

Sep 06

Nursery -

Oct 06

541,000

NDS Modernisation 05/06 438,000

School 103,000

541,000

Nightingale Primary School, Eastleigh

- extension to provide permanent classroom accommodation

- MUGA

Complete

Feb 05

Easter 06

Nov 05

Easter 06

* 1,196,477

NDS Modernisation 04/05 391,304

Contingency 55,173

Capital Receipt 646,552

School 103,448

1,196,477

Priestlands Secondary School, Lymington

-music/drama facility and dining extension

On site

May 05

Dec 05

* 1,615,665

Education Capital 04/05 1,069,828

School 277,000

Specialist School Status 04/05 100,000

P&R NDS Condition 05/06 20,000

Transfer of Fees 148,837

1,615,665

Rachel Maddocks School, Waterlooville

- extension, internal alterations, refurbishment and repair

Tender

Jan 05

Apr06

349,000

Education Capital 05/06 204,000

School 137,000

P&R Capital Repairs 05/06 8,000

349,000

Saint Lawrence CE (C) Primary

- new hall, kitchen, link building and internal refurbishment

On site

Oct 05

Apr 06

* 599,485

Education Capital 05/06 599,485

South Baddesley CE (C) Primary

- phase 1 - new classroom and staffroom

- phase 2 - new hall and car park

Complete

On site

May 05

Sep 05

Oct 05

Mar 06

* 424,722

* 484,872

add 31,921

941,515

Education Capital 04/05 391,828

Education contingency 11,207

School 125,653

NDS Condition 05/06 65,000

P&R Capital Repairs 05/06 87,827

P&R Capital 05/06 260,000

        941,515

Staunton Park Community

- Healthy Living Centre

On site

Jul 05

Feb 06

* 542,862

add 3,250

546,112

NDS Modernisation 04/05 70,862

School 53,250

Sport England 422,000

546,112

The Toynbee Community College, Chandlers Ford

- new Multi-Purpose Suite

On site

Nov 05

May 06

* 508,620

School 265,517

P&R Capital 05/06 200,000

Eastleigh Borough Council 43,103

508,620

Waterside Primary School, Hythe

- remodel and refurbish existing school; construct classroom block and early years unit

On site

Nov 05

Jul 06

* 1,913,815

Education Capital 05/06 1,539,462

School 125,000

P&R Capital Repairs 05/06 25,246

P&R NDS Condition 05/06 224,107

1,913,815

West Tytherley C of E Primary, Salisbury

- classroom extension to replace temporary accommodation

Design

Apr 06

Nov 06

851,000

Education Capital 05/06 811,000

School 40,000

851,000

Whitchurch CE (C) Primary

- two new classrooms, ICT Suite and corridor

On site

Jul 05

Feb 06

* 515,000

Education Capital 04/05 431,000

School 84,000

515,000

SPECIALIST SCHOOLS ACCOMMODATION PROGRAMME 2005/06 Appendix 2

School

Current Status

Start

Complete

Funding / * Contract Sum

Source of Funding £

Package 1 -

    - Toynbee School

    - The Hayling School

    - Noadswood School

    - Aldworth Science College

Complete

Design

Aug 05

Jan 06

Oct 05

Mar 06

* 311,369

NDS Modernisation 04/05 311,369

          Appendix 3

Other Schemes in the Education Capital Programme

The following schemes are included in the Education 2005/06 Capital Programme and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member Education or Policy and Resources:

School Allocation

        (excluding fees)

          £'000

PRIMARY

North Basingstoke schools

776

Whiteley / Western Wards

1,240

 

2,016

SPECIAL

Sundridge School, Havant

5,074

 

5,074

NDS MODERNISATION

Curdridge Primary

618

Micheldever Primary

1,240

Stanmore Primary

217

The Bridge Centre

830

 

2,905

   

TOTAL

9,995

I/PB&R/Committees/MajorMinorSelf-FundedApprovedbyExMem/MajorProjects