Hampshire County Council Executive Member - Education Item 19 January 2006 Minor Projects - Progress Report
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
1. Summary
1.1 The purpose of this report is to provide an update of the progress made in implementing those schemes in the Education Capital Programme with a value of between £43,000 and £216,000 (exclusive of fees).
2. Current Position
2.1 The attached tables summarise the current position in relation to schemes funded by the Education 2004/05 and 2005/06 Capital Programme including Minor Works, Seed Challenge, William Price Trust, Schools Access Initiative (SAI), New Opportunities Fund (NOF) and Staff Workplaces budget. The tables provide details of the funding, a brief description of the works and a summary of the current position.
3. Minor Works Capital Programme 2005/06
3.1 Chase Children's Centre, Bordon
An allocation of £43,104, excluding fees, has been made in the Capital Programme 2005/06 to provide an extension to the existing office accommodation and a ramped access to the Centre.
This scheme will be negotiated with a preferred contractor with a view to commencing works on site during February 2006.
4. Staff Workplace 2004/05
4.1 Burley Primary School, Ringwood
An allocation of £39,311, excluding fees, has been made in the Capital Programme 2005/06 for a small extension to provide additional office accommodation. The school is making a contribution of £30,000, excluding fees, to the cost. It is proposed to tender these works during February 2006 with an anticipated start on site during February 2006 and completion during July 2006.
5. Schools Access Initiative (SAI) / Disability Discrimination Act (DDA) 2005/06
5.1 Bohunt Community School, Liphook
Funding of £57,800, excluding fees, has been made available in the 2005/06 Capital Programme for acoustics improvements and formation of a quiet room. It is proposed to tender the works during January 2006 and to carry out the works during April 2006.
Recommendation
1. That the changes to the minor works programme be approved.
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information File, PBRS
Minor Works Capital Programme 2005/06 (* including carry forwards)
School |
Funding Position £ |
Summary of works |
Comments |
Alderman Quilley School, Eastleigh |
Residue of NOF sports hall Project 18,000 School Devolved Capital 15,000 Environment - Safe Routes to School 04/05 76,120 Education Capital Programme 05/06 20,000 P&R External Works Budget 05/06 20,000 149,120 |
Relocation of school car park to new location behind Sports Hall with new access roads, footpaths and cycle ways. |
The Scheme was approved by Executive Member Environment on 14 September 2004. Works commenced on site during September 2005, with completion anticipated in January 2006. |
Bordon Junior School |
Capital Programme 05/06 50,103 School - Devolved Capital 66,000 P&R NDS Condition 05/06 25,000 141,103 |
Entrance lobby, canopy and internal alterations to admin office. |
Capital Programme funding has been increased by £7,000 and school funding by £6,000. The scheme is currently on site with completed anticipated during April 2006. |
Butts Primary School, Alton
|
Capital Programme 05/06 77,586 P&R Capital Repairs 20,000 School - Devolved Capital 45,049 162,635 |
Extend existing building to improve administrative accommodation and provide a multi purpose teaching room. |
Works commenced on site during September 2005 and it is anticipated they will complete during February 2006. |
Chase Children's Centre, Bordon |
Capital Programme 05/06 43,104 43,104 4 |
Extension to office accommodation and provision of ramped access to the Centre. |
It is proposed to negotiate this scheme with a preferred contractor. Anticipated start on site date is February 2006. |
Hamble Primary School |
Capital Programme 05/06 100,000 School - Devolved Capital 55,000 155,000 |
Extension to classroom to create additional teaching space, cloak and alterations to lobby/entrance area. |
It is proposed to invite tenders during January 2006 with works commencing on site in April 2006 and completion anticipated in August 2006. |
Littlefold Family Centre, Waterlooville |
Sure Start Children's Centre 174,000 DfES General Sure Start Grant 26,000 200,000 |
Conversion from existing Family Centre to Children's Centre |
This scheme is being developed by Stephens Cox Associates and a programme is currently being agreed with a view to tenders being sought in the New Year. |
Sway Primary School, Sway |
Education Capital Programme (Security Budget) 05/06 25,000 School - Devolved Capital 70,000 Workforce Reform Budget 50,000 145,000 |
Extension to provide staff room, plus entrance alterations. |
Feasibility/design underway and programme being agreed. |
Staff Workplaces 2005/06 (*including carry forwards)
School |
Funding position £ |
Summary of Works |
Comments |
Burley Primary School |
Capital Programme 05/06 39,311 School - Devolved Capital 30,000 69,311 |
Small extension to provide additional office accommodation. |
Tenders are due to be sought during February 2006 with an anticipated start on site date during April 2006 and completion during July 2006. |
Castle Hill Junior School, Basingstoke |
Capital Programme 05/06 35,000 School - Devolved Capital 35,000 70,000 |
Extension to staff room to provide additional space for staff. |
Feasibility/design underway and programme being agreed. |
Itchen Abbas Primary School, Winchester |
Capital Programme 05/06 43,500 Education - School Security 17,400 School - Devolved Capital 73,275 134,175 |
Relocation of admin office and Headteacher's office to first floor to provide improved security and staff office facilities. |
Works commenced on site during November 2005 and completion is anticipated during March 2006. |
SEED Challenge 2005/06 (*including carry forwards)
School |
Funding position £ |
Summary of Works |
Comments |
Marnel Junior School, Basingstoke |
SEED 04/05 11,638 School Devolved Capital 76,318 87,956 |
Alterations and refurbishment. |
Works commenced on site during August 2005 and anticipated completion is February 2006. |
Schools Access Initiative (SAI) / Disability Discrimination Act (DDA) 2005/06 (*including carry forwards)
School |
Funding Position £ |
Summary of Works |
Comments |
Bohunt Community School |
Capital Programme 05/06 57,800 |
Improvements to provide accessibility |
Tenders will be invited during January 06, with start on site and completion anticipated during April 2006. |
Fordingbridge Junior School |
Capital Programme 05/06 49,000 |
Disabled WC upgrade and access and modifications to existing WC's |
This scheme was completed during December 2005. |
Frogmore Community School, Yateley |
Capital Programme 05/06 69,565 |
Toilet upgrade and physio rooms with ramp access. |
Scheme currently on hold pending further discussions with the School. |
Horndean Junior School, Waterlooville |
Capital Programme 05/06 63,930 School - Devolved Capital 9,500 73,430 |
Accessible WC and alterations to girls WC and alterations to provide level access. |
Due to the high value of tenders returned, this scheme has been revised and tenders are currently being sought. |
Kings School, Winchester |
Capital Programme 05/06 52,174 |
Internal lift access. |
Following discussions with the School during September, the scheme is currently being redesigned. |
Ringwood Infant School, Ringwood |
Capital Programme 05/06 78,250 School - Devolved Capital 39,750 118,000 |
Internal access and modifications to WCs. |
Work is due to start on site in January 2006 with completion anticipated during April 2006. |
Weyford Infant School |
Capital Programme 05/06 70,174 |
Ramps, accessible WC and platform lift. |
The accessible wc/platform lift works were completed during September 2005. Ramps to form part of framework agreement - a programme is currently being agreed. |
Wildern Secondary School, Hedge End |
Capital Programme 05/06 58,522 |
Alarm system for HI, modifications to WC's and level access. |
Feasibility/design underway and programme being agreed. |
Wyvern Technology College, Fair Oak |
Capital Programme 05/06 108,696 |
Accessibility and internal modifications. |
Feasibility/design underway and programme being agreed. It is anticipated that the project will go out to tender in March 2006 and start on site in July 2006. It is anticipated that the school will make a contribution towards the works. |
William Price Trust 2005/06 (*including carry forwards )
School |
Funding Position £ |
Summary of Works |
Comments |
Heathfield Special School. Fareham |
Capital Programme 05/06 57,400 School - Devolved Capital 24,000 81,400 |
Improvement and extension of existing Early Years playground. |
It is intended to tender this scheme during February 2006. Start on site is anticipated in April 2006, completion anticipated July 2006. |
Oak Meadow Early Years Centre, Fareham |
Capital Programme 05/06 * Phase I 83,000 Phase II 44,826 127,826 |
Internal alterations to form additional meeting areas, creation of new external entrance, provide staff room, toilets, kitchen and storage areas. Also formation of car park with 17 spaces including some accessible spaces, new footpath, entrance and external storage shed. |
Due to higher-than-expected tenders, the scheme is now being carried out in two phases: Phase I completed in November 2005. Phase II (internal alterations) is due to commence during February 2006. |
Specialist School College Status Allocations 2005/06
School |
Funding Position £ |
Summary of Works |
Comments |
Alderman Quilley Secondary School, Eastleigh |
Specialist School Funding 05/06 87,000 P&R Capital Repairs 05/06 20,000 School funding 18,200 NDS Condition Fund 05/06 15,000 43,500 140,200 |
New doors/ramp. Internal refurbishment/decoration, electrical/mechanical works. Enabling package for asbestos removal (£5k) |
Enabling works to remove asbestos have been completed. The main package of work is due to commence in February 2006, with completion anticipated April 2006. |
Crestwood College for Business and Enterprise, Eastleigh |
Capital Programme 05/06 105,000 School funding tbc |
Specialist school allocation |
Feasibility/design underway and programme being agreed. |
Staunton Park Community School, Havant |
Capital Programme 05/06 87,000 |
Specialist school allocation (Sport) |
New allocation - 2005/06 Capital Programme |
Testbourne Community School, Whitchurch |
Capital Programme 05/06 87,000 |
Specialist school allocation (Arts) |
New allocation - 2005/06 Capital Programme |
Warblington School, Havant |
Capital Programme 05/06 87,000 |
Specialist school allocation (Science) |
New allocation - 2005/06 Capital Programme |
Winton School, Andover |
Capital Programme 05/06 87,000 |
Specialist school allocation (Technology) |
New allocation - 2005/06 Capital Programme |
NDS Modernisation Programme 2005/6 - Schools Specialist Accommodation Programme
School |
Funding Position £ |
Summary of Works |
Comments |
Brune Park Community College, Gosport and Noadswood School |
NDS Modernisation 05/06 130,435 School - Brune Park 25,936 School - Noadswood 37,053 193,424 |
1 No. Science lab refurbishment at Brune Park and 2 No. Science lab refurbishment at Noadswood. |
Work is due to commence on site during February 2006 and be completed during April 2006. |
Cowplain Community School, Waterlooville |
Capital Programme 05/06 43,478 School funding - Cowplain 30,979 74,457 |
1 No. Science lab refurbishment at Cowplain. |
Work is due to commence on site during February 2006 and be completed during March 2006. |
Fordingbridge Infant School |
Capital Programme 05/06 60,000 60,000 |
Replacement windows and doors |
It is proposed that this work will be tendered during April 2006 with a view to commencing on site during July 06 and completion September 06. |
Hythe Primary School |
Capital Programme 05/06 60,000 60,000 |
Replacement windows and doors |
It is proposed that this work will be tendered during April 2006 with a view to commencing on site during July 06 and completion September 06. |
Test Valley School, Stockbridge |
Capital Programme 05/06 43,103 |
1 No. Science lab refurbishment at Test Valley |
It is proposed that this work be undertaken during the summer 2006. A more detailed programme of work is to be agreed with the school. |