Executive Member - Education Item 19 January 2006 Major Projects Status Report
Report of the Director of Property, Business and Regulatory Services |
Contact: Steve Clow Ext: 7858 E-mail: [email protected]
1. Summary
1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.
1.2 Appendix 3 shows those capital projects for which an allocation has been made in the Education Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.
2. Completed Schemes
2.1 Since the December 2005 meeting of the Executive Member for Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:
SCHOOL COMPLETION DATE
Brookfield Community School December 2005
Calmore Infant School
- Partial Possession November 2005
- Practical Completion December 2005
Eggars School December 2005
Priestlands School December 2005.
3. Additional Works and Funding Added Post Contract
3.1 The following schemes have had further funding added to the contract for specific additional works.
3.2 Eggars School, Alton
The scheme at the above school to provide a new IT classroom block, new sports hall and undertake internal refurbishment commenced on site during March 2005 and was successfully completed during December 2005. The school recently made an additional contribution of £9,841, for the purchase and installation of additional IT equipment and external furniture.
3.3 The Henry Cort Community College, Fareham
A major scheme at the above school to provide a new staff room, library and offices along with internal remodelling and refurbishment commenced on site during August 2005. Work is progressing well, with an anticipated completion during March 2006. The school have recently added £21,938 for additional requested items including; roof lights, a sliding partition wall and extract ventilation fans, along with a contribution towards the cost of steelwork and curtain walling.
3.4 Priestlands School
A scheme for a new music/drama facility and extension to the dining facilities at this school commenced during May 2005 and was successfully completed during December 2005. Prior to completion the Executive Member for Education approved to an additional £20,604, excluding fees from the Education furniture and equipment budget 05/06. This funding enabled loose equipment associated with lighting and a curtain track system and tower for access to a lighting rig.
3.5 Whitchurch CE Primary School
A scheme to construct two new classrooms and ICT suite commenced on site during July 2005. The school have recently added £8,522 to the project to replace coping stones and work is progressing well on site with an anticipated completion during February 2006.
4. Additional Works and Funding added at Pre Contract Stage
4.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.
4.2 Additional funding has come from various sources including increased Education Capital Programme allocations and inflation and tolerance adjustments; additional school funding for specific additional requested works and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.
5. Curdridge Primary School
5.1 A major scheme in the 2005/06 Capital Programme is proposed at Curdridge Primary school to provide a two classroom extension, allowing for the removal of temporary classrooms. Detailed design work is currently being progressed for these proposals and it is intended to take a design project appraisal to the March 2006 meeting of the Executive Member for Education and the April 2006 meeting of the Executive Member for Policy and Resources.
5.2 At the November 2005 meeting of the Executive Member for Policy and Resources approval was given to procure this scheme on a develop and construct basis, on a two stage tender process, through competitive tender to a short list of three preferred contractors. The scheme will be fully developed and finally priced by the successful first stage tenderer.
5.3 Prior to seeking agreement to the design project appraisal, approval is sought to commence a first stage tender and progress the second stage tender. A contract will not be formed until full approval of the design project appraisal in April 2006. This will enable the current construction programme, intended to commence on site during May 2006 and complete during December 2006 and will comply with a current, approved, planning application to site temporary buildings on nearby Parish Council land, which has a time restriction to mid 2007.
5.4 It should be noted that in January 2006 a survey of the existing school building will be undertaken to ascertain the presence of bat roosts. If existing roosts are detected in this initial survey then an emergence survey will be required during May / June 2006 and an application to DEFRA will be required prior to any construction works. This will obviously impact on the desired programme of works, however, in order that momentum is maintained on this project, approval to the above preferred procurement method, prior to the approval of the design project appraisal, is required.
Conclusion
The details of the major capital projects outlined in this report will provide greatly enhanced school accommodation and facilities.
Recommendations
1. That the position of the major projects being undertaken by the Director of Property, Business and Regulatory Services be noted.
2. That the additional funding added to the major capital projects at pre contract stage, previously approved by the Executive Members' Education and Policy and Resources at design project appraisal stage, be approved.
3. That the Executive Member for Education approves the progression of the Curdridge Primary School scheme, with a two stage procurement method, prior to approval of the design project appraisal.
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1. Published works.
2. Documents which disclose exempt or confidential information as defined in the act.
TITLE FILE
Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS
Tender schedules
Project Appraisals
MAJOR PROJECT STATUS REPORT Appendix 1
School |
Current Status |
Start |
Complete |
Funding/ * Contract Sum £ |
Source of Funding £ |
Blackfield Primary School - creation of 2.5fe Primary school by extending and remodelling existing Junior school |
On site |
Dec 05 |
Aug 06 |
* 1,498,208
|
Education Capital 05/06 1,185,345 Edu Early Years 05/06 34,483 Education contingency 46,552 School 231,828 1,498,208 |
Bridgemary Community School, Gosport - new Exercise Space |
Design |
Jul 06 |
Dec 06 |
294,000 |
School 294,000 |
Brookfield Community School, Sarisbury Green - internal refurbishment |
Complete |
May 05 |
Dec 05 |
* 970,934 |
Education Capital 04/05 375,000 Contingency 54,133 NDS Modernisation 05/06 78,261 NDS Condition fund 04/05 450,000 NDS Condition fund 05/06 13,000 970,394 |
Broughton Primary School, Stockbridge - new kitchen |
Tender Analysis |
Jan 06 |
May 06 |
240,000 |
Education Capital 05/06 220,000 School 20,000 240,000 |
Calmore Infant School - internal alterations to form an integrated yet independent Early Years Centre |
Partial Possession Complete |
May 05 |
Nov 05 Dec 05 |
* 473,552 |
Education Capital 04/05 377,000 School 96,552 473,552 |
Costello Technology College, Basingstoke - replacement maths / technology teaching block |
On site |
Nov 05 |
Feb 07 |
* 5,200,434 |
P&R Fire Re'statem't 05/06 4,870,434 Education Capital 05/06 250,000 P&R NDS Condition 05/06 80,000 5,200,434 |
Court Moor School, Fleet - refurbish and extend Youth Block |
Tender preparation |
Mar 06 |
Jun 06 |
242,000 |
Edu - Youth Service 05/06 138,000 Edu - Early Years 05/06 59,000 School - Connexions 25,000 P&R NDS Condition 05/06 20,000 242,000 |
Cove Junior School, Farnborough - three classroom extension, Music/Drama and kiln room |
On site |
Oct 05 |
May 06 |
* 804,202 |
Education Capital 05/06 717,000 School 54,202 P&R NDS Condition 05/06 33,000 804,202 |
The Crescent Primary School, Eastleigh - two classroom and library extension |
On site |
Jul 05 |
Mar 06 |
* 827,050 |
Education Capital 05/06 628,550 School 53,500 HC3S 20,000 P&R NDS Condition 05/06 125,000 827,050 |
Crestwood Community School, Eastleigh - Community Sports Hall, drama studio and Fitness Suite |
On site |
Oct 05 |
Jun 06 |
* 3,132,183 |
Capital Programme 05/06 3,132,183 |
Eggars School, Alton - IT block, Sports Hall and internal refurbishment |
Complete |
Mar 05 |
Dec 05 |
* 2,508,232 add 9,841 2,518,073 |
Education Capital 03/04 1,020,000 NDS Modernisation 03/04 65,000 Treloar College Funding 288,000 School 281,073 Eggars Trust Fund 688,000 P&R NDS Fire Alarm 04/05 76,000 P&R Landlord contribution 70,000 P&R External Works 04/05 30,000 2,518,073 |
Grayshott CE (C) Primary - single storey extension and internal alterations |
On site |
Oct 05 |
May 06 |
* 525,000 |
Education Capital 05/06 365,000 School 160,000 525,000 |
The Henry Cort Community College, Fareham - extension to staff room, two new offices, internal remodelling and refurbishment |
On site |
Aug 05 |
Mar 06 |
* 395,948 add 21,938 417,886 |
Education Capital 05/06 97,948 School 283,938 P&R NDS Condition 05/06 15,000 P&R Capital Repairs 05/06 2,000 P&R L'lords M. Works 05/06 12,000 P&R Ext. Landscaping 05/06 7,000 417,886 |
Hollywater School, Bordon - new special school |
On site |
May 05 |
Dec 06 |
* 6,088,472 |
Edu Cap / TCF 05/06 4,887,472 P&R Capital Repairs 05/06 629,000 P&R Capital Receipt 572,000 6,088,472 |
John Hunt of Everest Community School, Basingstoke - New School and Youth facility |
Enabling - Complete On site |
Aug 05 Jan 06 |
Nov 05 Apr 07 |
* 1,106,416 * 21,532,336 22,638,752
|
Capital Receipts 13,543,659 Developer's Contribution 2,383,824 B&D Borough Council 2,008,615 County Council 4,702,654 22,638,752 |
Lakeside School, Chandlers Ford - refurb. boarding accommodation; demolish surplus boarding house; new teaching block and refurbish teaching accommodation |
Complete Complete Phase 2 |
Jul 04 Nov 04 Jul 05 |
Aug 04 Apr 05 May 06 |
* 196,000 * 568,000 * 1,301,254 * 2,065,254 |
Education Mod'tion 04/05 1,565,000 Education Capital 04/05 261,254 P&R NDS Condition 04/05 49,000 P&R Fire Precautions 04/05 190,000 2,065,254 |
Minstead Rural Study Centre, Lyndhurst - new residential building, extension to schoolhouse and removal of temps |
On site |
Dec 05 |
Jul 06 |
* 1,228,000 |
Education Capital 05/06 519,000 Temp Classroom Hire 05/06 28,000 New Opportunities Fund 487,000 Study Centre 100,000 New Forest District Council 26,000 P&R Landlords contribution 68,000 1,228,000 |
Mountbatten School and Language College - new Staff Room, Inclusion room and Multi-agency space |
On site |
Jul 05 |
Feb 06 |
* 449,000 |
Edu. Capital - SEED 05/06 117,000 School 332,000 449,000 |
Netley Marsh Infant - new classrooms and extended hall |
On site |
Aug 05 |
Feb 06 |
* 678,312 |
Education Capital 0506 595,381 School 62,931 P&R NDS Condition 05/06 20,000 678,312 |
Newtown Soberton Infant School - new Hall and internal adaptations to create a Nursery Unit |
Tender Preparation |
Feb 06 |
Hall - Sep 06 Nursery - Oct 06 |
541,000 |
NDS Modernisation 05/06 438,000 School 103,000 541,000 |
Nightingale Primary School, Eastleigh - extension to provide permanent classroom accommodation - MUGA |
Complete |
Feb 05 Easter 06 |
Nov 05 Easter 06 |
* 1,201,645 |
NDS Modernisation 04/05 391,304 Contingency 55,173 Capital Receipt 646,552 School 108,634 1,201,645 |
Priestlands Secondary School, Lymington -music/drama facility and dining extension |
Complete |
May 05 |
Dec 05 |
* 1,615,665 add 20,604 1,636,269 |
Education Capital 04/05 1,069,828 Education F&E 05/06 20,604 School 277,000 Specialist School Status 04/05 100,000 P&R NDS Condition 05/06 20,000 Transfer of Fees 148,837 1,636,269 |
Rachel Maddocks School, Waterlooville - extension, internal alterations, refurbishment and repair |
Tender Analysis |
Feb 05 |
Jun 06 |
349,000 |
Education Capital 05/06 204,000 School 137,000 P&R Capital Repairs 05/06 8,000 349,000 |
Saint Lawrence CE (C) Primary - new hall, kitchen, link building and internal refurbishment |
On site |
Oct 05 |
Apr 06 |
* 599,485 |
Education Capital 05/06 599,485 |
South Baddesley CE (C) Primary - phase 1 - new classroom and staffroom - phase 2 - new hall and car park |
Complete On site |
May 05 Sep 05 |
Oct 05 Mar 06 |
* 424,722 * 516,793
|
Education Capital 04/05 391,828 Education contingency 11,207 School 125,653 NDS Condition 05/06 65,000 P&R Capital Repairs 05/06 87,827 P&R Capital 05/06 260,000 941,515 |
Staunton Park Community - Healthy Living Centre |
On site |
Jul 05 |
Feb 06 |
* 546,112 |
NDS Modernisation 04/05 70,862 School 53,250 Sport England 422,000 546,112 |
The Toynbee Community College, Chandlers Ford - new Multi-Purpose Suite |
On site |
Nov 05 |
May 06 |
* 508,620 |
School 265,517 P&R Capital 05/06 200,000 Eastleigh Borough Council 43,103 508,620 |
Trosnant Infant and Junior Schools, Leigh Park - Trospac full day-care provision |
Negotiation |
Jan 06 |
May 06 |
585,000 |
Education Capital 05/06 237,000 Sure Start (Children's Centre) 87,000 DfES general Sure Start 261,000 585,000 |
Waterside Primary School, Hythe - remodel and refurbish existing school; construct classroom block and early years unit |
On site |
Nov 05 |
Jul 06 |
* 1,913,815 |
Education Capital 05/06 1,539,462 School 125,000 P&R Capital Repairs 05/06 25,246 P&R NDS Condition 05/06 224,107 1,913,815 |
West Tytherley C of E Primary, Salisbury - classroom extension to replace temporary accommodation |
Design |
Apr 06 |
Nov 06 |
851,000 |
Education Capital 05/06 811,000 School 40,000 851,000 |
Whitchurch CE (C) Primary - two new classrooms, ICT Suite and corridor |
On site |
Jul 05 |
Feb 06 |
* 515,000 add 8,522 523,522 |
Education Capital 04/05 431,000 School 92,522 523,522 |
SPECIALIST SCHOOLS ACCOMMODATION PROGRAMME 2005/06 Appendix 2 | |||||
School |
Current Status |
Start |
Complete |
Funding / * Contract Sum |
Source of Funding £ |
Package - Toynbee School - The Hayling School - Noadswood School
- Aldworth Science College |
Complete Contract Lead-in |
Aug 05 Jan 06 |
Oct 05 Mar 06 |
* 311,369 |
NDS Modernisation 05/06 311,369 |
Appendix 3
Other Schemes in the Education Capital Programme
The following schemes are included in the Education 2005/06 Capital Programme and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member Education or Policy and Resources:
School Allocation
(excluding fees)
£'000
PRIMARY
North Basingstoke Schools |
776 |
NDS MODERNISATION
Curdridge Primary |
618 |
Micheldever Primary |
1,240 |
Stanmore Primary |
217 |
The Bridge Centre |
830 |
2,905 | |
TOTAL |
3,681 |