19 January 2006

Major Projects Status Report

Report of the Director of Property, Business and Regulatory Services

How the conclusion in this report fits with the Corporate Strategy

This scheme will impact on the delivery of the following Corporate Aims

Aim 1 - maximising life opportunities - by providing new and/or improved teaching accommodation to be enjoyed by the schools.

Aim 5 - improving services - by providing good quality buildings that enable service delivery.

    1. Summary

    1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

    1.2 Appendix 3 shows those capital projects for which an allocation has been made in the Education Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.

    2. Completed Schemes

    2.1 Since the December 2005 meeting of the Executive Member for Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:

      SCHOOL COMPLETION DATE

                      Brookfield Community School December 2005

                      Calmore Infant School

      - Partial Possession November 2005

      - Practical Completion December 2005

      Eggars School December 2005

      Priestlands School December 2005.

    3. Additional Works and Funding Added Post Contract

    3.1 The following schemes have had further funding added to the contract for specific additional works.

    3.2 Eggars School, Alton

      The scheme at the above school to provide a new IT classroom block, new sports hall and undertake internal refurbishment commenced on site during March 2005 and was successfully completed during December 2005. The school recently made an additional contribution of £9,841, for the purchase and installation of additional IT equipment and external furniture.

    3.3 The Henry Cort Community College, Fareham

        A major scheme at the above school to provide a new staff room, library and offices along with internal remodelling and refurbishment commenced on site during August 2005. Work is progressing well, with an anticipated completion during March 2006. The school have recently added £21,938 for additional requested items including; roof lights, a sliding partition wall and extract ventilation fans, along with a contribution towards the cost of steelwork and curtain walling.

    3.4 Priestlands School

      A scheme for a new music/drama facility and extension to the dining facilities at this school commenced during May 2005 and was successfully completed during December 2005. Prior to completion the Executive Member for Education approved to an additional £20,604, excluding fees from the Education furniture and equipment budget 05/06. This funding enabled loose equipment associated with lighting and a curtain track system and tower for access to a lighting rig.

    3.5 Whitchurch CE Primary School

        A scheme to construct two new classrooms and ICT suite commenced on site during July 2005. The school have recently added £8,522 to the project to replace coping stones and work is progressing well on site with an anticipated completion during February 2006.

    4. Additional Works and Funding added at Pre Contract Stage

    4.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

    4.2 Additional funding has come from various sources including increased Education Capital Programme allocations and inflation and tolerance adjustments; additional school funding for specific additional requested works and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.

    5. Curdridge Primary School

    5.1 A major scheme in the 2005/06 Capital Programme is proposed at Curdridge Primary school to provide a two classroom extension, allowing for the removal of temporary classrooms. Detailed design work is currently being progressed for these proposals and it is intended to take a design project appraisal to the March 2006 meeting of the Executive Member for Education and the April 2006 meeting of the Executive Member for Policy and Resources.

5.2 At the November 2005 meeting of the Executive Member for Policy and Resources approval was given to procure this scheme on a develop and construct basis, on a two stage tender process, through competitive tender to a short list of three preferred contractors. The scheme will be fully developed and finally priced by the successful first stage tenderer.

5.3 Prior to seeking agreement to the design project appraisal, approval is sought to commence a first stage tender and progress the second stage tender. A contract will not be formed until full approval of the design project appraisal in April 2006. This will enable the current construction programme, intended to commence on site during May 2006 and complete during December 2006 and will comply with a current, approved, planning application to site temporary buildings on nearby Parish Council land, which has a time restriction to mid 2007.

    5.4 It should be noted that in January 2006 a survey of the existing school building will be undertaken to ascertain the presence of bat roosts. If existing roosts are detected in this initial survey then an emergence survey will be required during May / June 2006 and an application to DEFRA will be required prior to any construction works. This will obviously impact on the desired programme of works, however, in order that momentum is maintained on this project, approval to the above preferred procurement method, prior to the approval of the design project appraisal, is required.

    Conclusion

      The details of the major capital projects outlined in this report will provide greatly enhanced school accommodation and facilities.

    Recommendations

    1. That the position of the major projects being undertaken by the Director of Property, Business and Regulatory Services be noted.

    2. That the additional funding added to the major capital projects at pre contract stage, previously approved by the Executive Members' Education and Policy and Resources at design project appraisal stage, be approved.

    3. That the Executive Member for Education approves the progression of the Curdridge Primary School scheme, with a two stage procurement method, prior to approval of the design project appraisal.

    Section 100 D - Local Government Act 1972 - background papers

    The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

    NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the act.

                    TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS

      Tender schedules

      Project Appraisals

    MAJOR PROJECT STATUS REPORT Appendix 1

School

Current Status

Start

Complete

Funding/

* Contract Sum

£

Source of Funding

£

Blackfield Primary School

- creation of 2.5fe Primary school by extending and remodelling existing Junior school

On site

Dec 05

Aug 06

* 1,498,208

Education Capital 05/06 1,185,345

Edu Early Years 05/06 34,483

Education contingency 46,552

School 231,828

1,498,208

Bridgemary Community School, Gosport

- new Exercise Space

Design

Jul 06

Dec 06

294,000

School 294,000

Brookfield Community School, Sarisbury Green

- internal refurbishment

Complete

May 05

Dec 05

* 970,934

Education Capital 04/05 375,000

Contingency 54,133

NDS Modernisation 05/06 78,261

NDS Condition fund 04/05 450,000

NDS Condition fund 05/06 13,000

970,394

Broughton Primary School, Stockbridge

- new kitchen

Tender Analysis

Jan 06

May 06

240,000

Education Capital 05/06 220,000

School 20,000

240,000

Calmore Infant School

- internal alterations to form an integrated yet independent Early Years Centre

Partial Possession

Complete

May 05

Nov 05

Dec 05

* 473,552

Education Capital 04/05 377,000

School 96,552

473,552

Costello Technology College, Basingstoke

- replacement maths / technology teaching block

On site

Nov 05

Feb 07

* 5,200,434

P&R Fire Re'statem't 05/06 4,870,434

Education Capital 05/06 250,000

P&R NDS Condition 05/06 80,000

5,200,434

Court Moor School, Fleet

- refurbish and extend Youth Block

Tender preparation

Mar 06

Jun 06

242,000

Edu - Youth Service 05/06 138,000

Edu - Early Years 05/06 59,000

School - Connexions 25,000

P&R NDS Condition 05/06 20,000

242,000

Cove Junior School, Farnborough

- three classroom extension, Music/Drama and kiln room

On site

Oct 05

May 06

* 804,202

Education Capital 05/06 717,000

School 54,202

P&R NDS Condition 05/06 33,000

804,202

The Crescent Primary School, Eastleigh

- two classroom and library extension

On site

Jul 05

Mar 06

* 827,050

Education Capital 05/06 628,550

School 53,500

HC3S 20,000

P&R NDS Condition 05/06 125,000

827,050

Crestwood Community School, Eastleigh

- Community Sports Hall, drama studio and Fitness Suite

On site

Oct 05

Jun 06

* 3,132,183

Capital Programme 05/06 3,132,183

Eggars School, Alton

- IT block, Sports Hall and internal refurbishment

Complete

Mar 05

Dec 05

* 2,508,232

add 9,841

2,518,073

Education Capital 03/04 1,020,000

NDS Modernisation 03/04 65,000

Treloar College Funding 288,000

School 281,073

Eggars Trust Fund 688,000

P&R NDS Fire Alarm 04/05 76,000

P&R Landlord contribution 70,000

P&R External Works 04/05 30,000

2,518,073

Grayshott CE (C) Primary

- single storey extension and internal alterations

On site

Oct 05

May 06

* 525,000

Education Capital 05/06 365,000

School 160,000

525,000

The Henry Cort Community College, Fareham

- extension to staff room, two new offices, internal remodelling and refurbishment

On site

Aug 05

Mar 06

* 395,948

add 21,938

417,886

Education Capital 05/06 97,948

School 283,938

P&R NDS Condition 05/06 15,000

P&R Capital Repairs 05/06 2,000

P&R L'lords M. Works 05/06 12,000

P&R Ext. Landscaping 05/06 7,000

417,886

Hollywater School, Bordon

- new special school

On site

May 05

Dec 06

* 6,088,472

Edu Cap / TCF 05/06 4,887,472

P&R Capital Repairs 05/06 629,000

P&R Capital Receipt 572,000

6,088,472

John Hunt of Everest Community School, Basingstoke

- New School and Youth facility

Enabling -

Complete

On site

Aug 05

Jan 06

Nov 05

Apr 07

* 1,106,416

* 21,532,336

22,638,752

Capital Receipts 13,543,659

Developer's Contribution 2,383,824

B&D Borough Council 2,008,615

County Council 4,702,654

22,638,752

Lakeside School, Chandlers Ford

- refurb. boarding accommodation; demolish surplus boarding house; new teaching block and refurbish teaching accommodation

Complete

Complete

Phase 2

Jul 04

Nov 04

Jul 05

Aug 04

Apr 05

May 06

* 196,000

* 568,000

* 1,301,254

* 2,065,254

Education Mod'tion 04/05 1,565,000

Education Capital 04/05 261,254

P&R NDS Condition 04/05 49,000

P&R Fire Precautions 04/05 190,000

2,065,254

Minstead Rural Study Centre, Lyndhurst

- new residential building, extension to schoolhouse and removal of temps

On site

Dec 05

Jul 06

* 1,228,000

Education Capital 05/06 519,000

Temp Classroom Hire 05/06 28,000

New Opportunities Fund 487,000

Study Centre 100,000

New Forest District Council 26,000

P&R Landlords contribution 68,000

1,228,000

Mountbatten School and Language College

- new Staff Room, Inclusion room and Multi-agency space

On site

Jul 05

Feb 06

* 449,000

Edu. Capital - SEED 05/06 117,000

School 332,000

449,000

Netley Marsh Infant

- new classrooms and extended hall

On site

Aug 05

Feb 06

* 678,312

Education Capital 0506 595,381

School 62,931

P&R NDS Condition 05/06 20,000

678,312

Newtown Soberton Infant School

- new Hall and internal adaptations to create a Nursery Unit

Tender Preparation

Feb 06

Hall -

Sep 06

Nursery -

Oct 06

541,000

NDS Modernisation 05/06 438,000

School 103,000

541,000

Nightingale Primary School, Eastleigh

- extension to provide permanent classroom accommodation

- MUGA

Complete

Feb 05

Easter 06

Nov 05

Easter 06

* 1,201,645

NDS Modernisation 04/05 391,304

Contingency 55,173

Capital Receipt 646,552

School 108,634

1,201,645

Priestlands Secondary School, Lymington

-music/drama facility and dining extension

Complete

May 05

Dec 05

* 1,615,665

add 20,604

1,636,269

Education Capital 04/05 1,069,828

Education F&E 05/06 20,604

School 277,000

Specialist School Status 04/05 100,000

P&R NDS Condition 05/06 20,000

Transfer of Fees 148,837

1,636,269

Rachel Maddocks School, Waterlooville

- extension, internal alterations, refurbishment and repair

Tender Analysis

Feb 05

Jun 06

349,000

Education Capital 05/06 204,000

School 137,000

P&R Capital Repairs 05/06 8,000

349,000

Saint Lawrence CE (C) Primary

- new hall, kitchen, link building and internal refurbishment

On site

Oct 05

Apr 06

* 599,485

Education Capital 05/06 599,485

South Baddesley CE (C) Primary

- phase 1 - new classroom and staffroom

- phase 2 - new hall and car park

Complete

On site

May 05

Sep 05

Oct 05

Mar 06

* 424,722

* 516,793

Education Capital 04/05 391,828

Education contingency 11,207

School 125,653

NDS Condition 05/06 65,000

P&R Capital Repairs 05/06 87,827

P&R Capital 05/06 260,000

        941,515

Staunton Park Community

- Healthy Living Centre

On site

Jul 05

Feb 06

* 546,112

NDS Modernisation 04/05 70,862

School 53,250

Sport England 422,000

546,112

The Toynbee Community College, Chandlers Ford

- new Multi-Purpose Suite

On site

Nov 05

May 06

* 508,620

School 265,517

P&R Capital 05/06 200,000

Eastleigh Borough Council 43,103

508,620

Trosnant Infant and Junior Schools, Leigh Park

- Trospac full day-care provision

Negotiation

Jan 06

May 06

585,000

Education Capital 05/06 237,000

Sure Start (Children's Centre) 87,000

DfES general Sure Start 261,000

585,000

Waterside Primary School, Hythe

- remodel and refurbish existing school; construct classroom block and early years unit

On site

Nov 05

Jul 06

* 1,913,815

Education Capital 05/06 1,539,462

School 125,000

P&R Capital Repairs 05/06 25,246

P&R NDS Condition 05/06 224,107

1,913,815

West Tytherley C of E Primary, Salisbury

- classroom extension to replace temporary accommodation

Design

Apr 06

Nov 06

851,000

Education Capital 05/06 811,000

School 40,000

851,000

Whitchurch CE (C) Primary

- two new classrooms, ICT Suite and corridor

On site

Jul 05

Feb 06

* 515,000

add 8,522

523,522

Education Capital 04/05 431,000

School 92,522

523,522

SPECIALIST SCHOOLS ACCOMMODATION PROGRAMME 2005/06 Appendix 2

School

Current Status

Start

Complete

Funding / * Contract Sum

Source of Funding £

Package

    - Toynbee School

    - The Hayling School

    - Noadswood School

    - Aldworth Science College

Complete

Contract Lead-in

Aug 05

Jan 06

Oct 05

Mar 06

* 311,369

NDS Modernisation 05/06 311,369

          Appendix 3

    Other Schemes in the Education Capital Programme

    The following schemes are included in the Education 2005/06 Capital Programme and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member Education or Policy and Resources:

    School Allocation

        (excluding fees)

            £'000

    PRIMARY

North Basingstoke Schools

776

   

    NDS MODERNISATION

Curdridge Primary

618

Micheldever Primary

1,240

Stanmore Primary

217

The Bridge Centre

830

2,905

TOTAL

3,681

    I/PB&R/Committees/MajorMinorSelf-FundedApprovedbyExMem/MajorProjects