Archived decisions
Appendix 5
1 Treasury Management Strategy 2006/07
1.1 The Authority has to approve an annual Treasury Management Strategy. The strategy covers capital finance and debt, interest rates and borrowing strategy and the investment of surplus funds.
2 Capital finance and debt
2.1 Total capital expenditure in 2006/07 is estimated to be £5.6m which it is planned to finance through a combination of revenue contributions, borrowing, capital grant, capital receipts and capital reserve.
2.2 Since the Authority was established, 13 long-term fixed-rate loans totalling £5.1m have to date been taken from the Public Works Loan Board (PWLB).
3 Interest rates and borrowing strategy
3.1 The Authority borrows for two main reasons:
· To finance capital expenditure
· To meet short-term cash requirements, for example on days when salaries are paid
3.2 The Authority borrows from two main sources:
· The PWLB to finance capital expenditure, normally long-term at fixed rates
· The County Council at variable rates based on local authority seven day notice rates. This can be used to meet short-term cash requirements, or to finance capital expenditure when circumstances are appropriate
3.3 Although the recent trend has been down, economic forecasters are expecting long-term interest rates to rise over the next two years, although the pace of such a rise is likely to be very slow. Base rates and other short-term rates are expected to peak at no higher than 5%.
3.4 Until now the Authority's borrowing strategy has been based on that of the County Council. For a number of years the County Council has borrowed long-term in small amounts, maintaining as far as possible the balance between long-term fixed rate debt, which provides budget stability and protection against rising interest rates, and short-term temporary debt, which enables advantage to be taken off falling rates. It is suggested that this strategy should be retained by the Authority.
4 Investment of surplus funds
4.1 In line with the budget proposals the Authority will aim to have re- accumulated balances of £2m by 31 March 2007. However, during the year cashflow requirements will mean that there is no scope for any direct long-term investment on the money markets. Therefore, the Authority will invest all its surplus funds with the County Council, earning interest based on the local authority seven-day notice rate.
Appendix 6
1 Level of Reserves 2006/07
1.1 The Local Government Act 2003 requires that the Treasurer assess the financial risks faced by the Authority and makes recommendations based on this as to the appropriate levels of resources required to be held against these risks.
1.2 In considering financial risks, a distinction must be made between:
· A provision, which is made for a known and quantified expectation of costs. It is usual, for example, to hold some provision in the Authority's accounts in respect of specific known claims against the Authority, which are not covered by insurance.
· On the other hand, reserves are set up against the possibilities of future costs that are not yet expected nor quantified, eg the likelihood that there will be more uninsured claims in future.
2. Level of reserves required
2.1 The approach taken in this paper is to assess the risks of increased expenditure that the Authority faces during any given year. Some adjustment is then appropriate given that:
· there is a much smaller chance that all identified risks will occur in the same year; and,
· the use of reserves is not the only means of meeting such pressures. Savings/transfers from underspent budgets are preferable (and the Authority has a good recent record in achieving these), and the Authority does have some temporary borrowing powers which could be used if necessary, together with other assistance available through the flexible use of capital funding.
2.2 The main factors used to evaluate the primary financial risks facing the Authority, together with the suggested amounts required to cover them, are summarised in Sections 3-9.
3. Pensions fluctuations
3.1 In previous years the reserves needed to cover potential pensions fluctuations have been set at £650,000 to allow for the lump sum impacts of firefighters retiring (as they have the discretion to retire at variable times in many cases), and £250,000 to allow for volatility in transfer values paid and received. The new financial framework for pensions, which comes into force from 1 April 2006, should eliminate most of these risks. However, it is considered prudent to leave this factor at its historic level for the moment as employee movements before 1 April will still be the responsibility of Fire Authorities and also to check how the new arrangements work in practice, and then review as part of the 200/08 budget process.
4 Inflation risk: Pay
4.1 There may be a need during the year to meet the costs of a pay award not known at the time of setting the budget. The application of formula approaches could minimise this effect, but some impact is likely with firefighters' pay awards taking effect from July, ie with a substantial first year impact but with a good chance that the figure will not be known in February when the budget is set. Non-uniformed staff pay is more likely to be known in advance, given an effective date of awards of 1 April - though, there have been occasions in recent years when the pay award has not been agreed until much later than this.
4.2 Here it is felt that a reserve equivalent to an additional 1.5% of firefighters' pay is sufficient, ie £300,000. Any unknown factors in non-uniformed pay can be dealt with by way of a provision as part of the budget setting process if necessary. This is not an issue for 2006/07 as the level of non-uniformed pay award is already known (2.95%).
5 Uninsured risks
5.1 Although the Authority has insurance in place, there remain risks. There was a period when the Authority effectively became uninsured from April 1997 to June 2001 due to its primary insurer going into liquidation. There are also some uninsured risks, e.g. for employment practice issues; and, if there are higher than budgeted levels of insurance claims, then there will be higher excess costs to pay. This is one of the harder areas to assess, but based on the historic number of uninsured risks tending to come forward and the continuing trend towards more litigation, £600,000 is recommended.
6 Extremes of weather
6.1 Unusually hot dry summers, wet winters and storms can all lead to additional operational costs, primarily associated with increased activity by retained firefighters. This is recognised under current arrangements through a protocol which builds in a budget variation for increases in the number of incidents. Historically, the highest variation was 16.5% in 2001/02, but this was exceptional, the second-largest variation in a year being 6%, and an anticipated variation of up to 10% is considered sufficient. This would equate to £220,000.
7. Other inflation
7.1 There is some risk attached to non-pay inflation levels: for example, insurance and fuel costs. To allow for a possible 10% increase in these heads over and above the budgeted level of inflation would require £90,000.
8. Regionalisation
8.1 The increasing impact of the regional agenda leads to additional uncertainties. It is hoped that this will be sufficiently covered by the specific revenue budget provision of £150,000 made in 2005/06 and largely due to be carried forward into 2006/07, and built into the base budget thereafter. This will, however, be an area to keep under review
9 Capital Programme issues
9.1 Another significant development over the past two years has been the firming up of a more ambitious approach to capital spending with a move away from leasing vehicles and the initiation of Headquarters developments. This has led to the agreement of a Capital Programme which should balance if sufficient capital receipts can be generated. There is, however, a risk that this will not be achievable. If so, this could be dealt with in terms of pure financial risk by re-timing projects, but if members wish to guard against the service impact of any such re-timings, it would make sense to take some account of Capital Programme risk in deciding on the level of reserves. It is difficult to rationalise a formula-based approach to this, but with most years likely to feature a major scheme worth around £2m separate from the comparatively routine vehicle replacement programme, a "safety net" equivalent to 25% of this - ie £500,000 - might sensibly be built into the overall assessment. This, too, may require review in 2007/08, by when the full extent of capital commitments and offsetting capital receipts should have been considerably clarified.
10. Conclusion: level of reserves
10.1 Bringing all these factors together leads to a `maximum exposure' of £2.6m as set out in Table 1. However, as mentioned above, other funding sources may be available, and it is not likely that all these problems will occur in the same year. That is illustrated historically by the fact that the Authority's outturn position has very rarely resulted in an overspend, and recent years have produced underspends. In theory it would probably be reasonable to discount the level of reserves required by 50% for the improbability of simultaneous recurrence of problems. However, it is considered sensible to take a more cautious position so a reduction of only 25% is proposed at this stage: this can be revisited if the Authority's budget performance continues to be healthy. This would suggest that an appropriate level of reserve is £1,960,000. Given the imprecise nature of the assessment, it is reasonable to round this up to £2m. Naturally, the level can be kept under review in light of both experience and variations in factors such as uninsurable risks and inflation rates.
10.2 This results in reserves at just over 3% of annual spend, which appears to be a somewhat lower proportion than for most other fire and rescue authorities.
10.3 This is a relevant background factor, though not a determinant of good practice as it may be for example that less strict control of budgets is in place in such authorities, and Hampshire should also gain through the `economy of scale' in spreading risks across a larger spending base than most.
10.4 Table 1: Summary of Factors
Factor |
Assessed impact £000 |
Pensions: payments |
650 |
Pensions: transfers |
250 |
Inflation: pay |
300 |
Uninsured risks |
600 |
Extremes of weather |
220 |
Inflation: other |
90 |
Capital factors |
500 |
2,610 | |
x 75% |
1,960 |
Nearest £100,000 |
2,000 |
10.5 Accordingly, the budget for 2006/07 has been set on the basis of continuing to provide for a £2m level of reserves, but members may wish to note that next year's review is likely - in the absence of any new factors emerging - to reduce the recommended level somewhat .
Appendix 7
Consultation meetings held 16 January 2006
Summary of the main issues raised
Meeting with trades unions representatives (1130hrs - 1215hrs)
Present:
Cllr Cartwright - Chairman of Hampshire Fire and Rescue Authority
Cllr Smith - Vice Chairman of Hampshire Fire and Rescue Authority
Cllr Price - Spokesperson for Liberal Democrat Group
Cllr Horne - Spokesperson for Labour Group
Rikki Noble - Chairman, Retained Firefighters Union (RFU)
Andy Needham - Secretary, Retained Firefighters Union (RFU)
Brian Neat - Fire Officers' Association (FOA)
Sue Brumitt - UNISON
John Bonney - Chief Officer
Dave Curry - Deputy Chief Officer
Paul Carey-Kent - Deputy Treasurer
David Howells - Director of Corporate Services
A short presentation was given by Paul Carey-Kent and David Howells which was based on the report on the Draft Budget 2006/07 that was due to be presented to the Finance and General Purposes Committee on 20 January 2006. Questions were taken during and after the presentation.
Overall, there was general satisfaction with the proposals. The following issues/comments were made:
Repair and maintenance of buildings: Whilst there was appreciation of the one-off investment of capital funding for improvements to retained fire stations made in response to comments raised last year, concern was again expressed about the deterioration in the condition of buildings. RFU representatives suggested that there was a need to continue this investment. Members and officers agreed to consider this and report the concern to the Finance and General Purposes Committee.
Budget for job evaluation: Questions were asked about whether sufficient provision has been made for any outcomes of the job evaluation review - particularly in anticipation of any appeals or equal pay claims. It was explained that the pay budget had taken into account the likely costs of the review, but that no specific provision had been made to cover the cost of any appeal or other knock-on related costs and that, if these occurred, costs would probably be met from general reserves in the first year.
Cost of the co-responder scheme: RFU representatives asked how the costs of this partnership initiative with the Hampshire Ambulance Service were budgeted for. It was explained that the pay costs were absorbed within the overall budget for retained pay. While the number of incidents are such that they are within the fluctuating range of the total number of emergency incidents, these are being carefully monitored so that the full cost to HFRA can be identified. It was also mentioned that there was the prospect of some `pump-priming' financial support from the Hampshire Local Strategic Partnership bid to the ODPM.
Meeting with representatives from the business, residents and taxpayers communities (1230hrs - 1345hrs)
Present:
Cllr Cartwright - Chairman of Hampshire Fire and Rescue Authority
Cllr Smith - Vice Chairman of Hampshire Fire and Rescue Authority
Cllr Price - Spokesperson for Liberal Democrat Group
Cllr Horne - Spokesperson for Labour Group
Colin Richards (Vice Chair) - Hampshire Federation of Residents Associations
(Note: Representing Ted O'Toole - Chairman)
Terry Tingey (Vice Chair) - Fleet and Church Crookham
Derek Green - Warblington & Denvilles
Tony Higham - Emsworth
David Jones - Emsworth
William Prince - Langstone Village
Malcolm C Robinson - Warblington & Denvilles (Apologies from Keith Chessell)
David Webb - West Bedhampton
John Bonney - Chief Officer
Paul Carey-Kent - Deputy Treasurer
David Howells - Director of Corporate Services
A short presentation was given by Paul Carey-Kent and David Howells which was based on the report on the Draft Budget 2006/07 that was due to be presented to the Finance and General Purposes Committee on 20 January 2006. Questions were taken during and after the presentation.
Representatives for the various communities appeared to be generally satisfied with the proposals for the budget which, if approved, would result in a Council Tax increase in the range 2.7% to 3%. Several representatives mentioned the need to keep the increase to no more than the increase in pension costs (2.7%).
Costs of regional collaboration: Representatives were informed about the cost and funding arrangements of the new Regional Control Centre. It was explained that the ODPM had given assurances that fire and rescue authorities should not pay more than they do now towards the cost of mobilising resources to emergency incidents.
Civil protection: Representatives sought assurances about the Authority's ability to respond to major civil incidents (prompted by concerns over the recent fire and the oil storage depot at Hemel Hempstead). The opportunity was taken to report on HFRA's specialist team and equipment and the excellent collaboration that takes place between fire and rescue services to deal with such major instances.
Further discussions that took place after the presentation covering a wide range of issues. The questions and comments were not all specifically concerned with the budget proposals. The opportunity was also taken to mention some of the main IRMP proposals and to clarify any misunderstandings about them.