Summary

1.1

The following decision is sought:

1.2

That the Executive Member for Education advises the Executive Member for Policy and Resources that the project appraisal for the construction of a new stand-alone four-court sports hall at an estimated cost of up to £1,938,000, excluding fees, be approved.

2

Reason

2.1

Hardley School lacks sufficient and appropriate indoor sports facilities and this proposal will provide a purpose-built sports hall to enable the curriculum needs of the school to be met.

2.2

This decision supports Aim 1 and 5 of the Corporate Strategy by providing improved facilities which will benefit all users of the school.

3

Other options considered and rejected

3.1

The need of the school for the facilities in question has been identified as a priority and the works set out in the design project appraisal are considered to be the most appropriate and cost effective way of meeting that need.

4

Conflicts of interest declared by the decision-maker or other Executive Member consulted

4.1

None.

5

Dispensation granted by the Standards Committee

5.1

Not applicable.

6

Reason(s) for the matter being dealt with if urgent

6.1

Not applicable

Approved by:

..........................

Date of decision:

...................

Councillor D Kirk