23 March 2006

Major Projects Status Report

Report of the Director of Property, Business and Regulatory Services

 

How the conclusion in this report fits with the Corporate Strategy

This scheme will impact on the delivery of the following Corporate Aims

Aim 1 - maximising life opportunities - by providing new and/or improved teaching accommodation to be enjoyed by the schools.

Aim 5 - improving services - by providing good quality buildings that enable service delivery.

1. Summary

1.1 This report seeks approval to the addition of funding to major capital projects, at pre contract stage, following the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

1.2 Appendix 2 shows those capital projects for which an allocation has been made in the Education Capital Programme and where the Director of Property, Business and Regulatory Services is either, or will shortly be, progressing feasibility work for these projects.

2. Completed Schemes

2.1 Since the January 2006 meeting of the Executive Member for Education, schemes at the following schools have been completed and the new accommodation handed over to the Children's Services Department. These schemes remain financially on target:

      SCHOOL COMPLETION DATE

      Staunton Park Community March 2006

      Whitchurch CE Primary School February 2006

3. Additional Works and Funding Added Post Contract

3.1 The following schemes have had further funding added to the contract for specific additional works.

3.2 Cove Junior School

    The scheme at the above school for a three classroom and music/drama extension commenced on site during October 2005. An additional £10,000 from the Policy and Resources 2005/06 NDS Condition budget has been added to this contract to convert the existing oil fired boilers to gas.

3.3 Grayshott CE (C) Primary School

      A major scheme currently on site at this school to construct a single storey extension and undertake internal alterations is progressing well on site, with completion due in May 2006. The school has recently added £32,728 to undertake the refurbishment of an existing toilet block, which will be incorporated into the current contract and will have no effect on the programme

3.4 John Hunt of Everest Community

      The major scheme to provide a new school and Youth Facility commenced on site in January 2006 and works are progressing well. Additional school funding of £27,385 has been added, at the request of the school, for revisions to the first floor corridor above the gymnasium, retention of a first floor arts/textiles terrace and retention of fire rated internal screens.

3.5 Netley Marsh Infant School

      A scheme for a new classroom, extended classroom and extended hall commenced on site during August 2005. Additional funding of £20,000 has recently been added to this contract from the Policy and Resources 2005/06 NDS Condition fund for a number of building maintenance items associated with the existing building.

3.6 St Lawrence CE (C) Primary School

      A scheme currently on site at the above school to provide a new hall, kitchen, link building and internal refurbishment is progressing well on site and is due for completion during April 2006. The school has recently added £43,500 from its Devolved Capital allocations for kitchen and hall equipment, furniture, works to fit out a Resource / Teaching area and partitioning of the existing Caretaker's Room.

3.7 South Baddesley Primary School

    The major scheme at this school to provide a new classroom and staff room (phase one) and a new hall and car park (phase two) is progressing well and is due for completion during March 2006. The school has recently added £23,188 to this contract for the provision of a new play court.

3.8 Whitchurch Primary School

      At the January 2005 meeting it was reported that the above school had made a contribution of £8,522 towards replacement coping stones for the major scheme currently on site. Since that time, the cost of these works has been finalised and subsequently reduced to £7,000. The Director of Property, Business and Regulatory Services has now made a contribution for the £7,000 from the Policy and Resources NDS Condition fund 2005/06 and the school have been reimbursed their original contribution.

      The school has since contributed £22,967 towards this contract for the provision of a new ramp to an existing playground.

4. Additional Works and Funding added at Pre Contract Stage

4.1 Appendix 1 and 2 provides detailed information for all current capital projects at their varying stages. Included are those at pre contract stage, where additional funding has been added since the approval of the design project appraisal by the Executive Members' Education and Policy and Resources.

4.2 Additional funding has come from various sources including increased Education Capital Programme allocations and inflation and tolerance adjustments; additional school funding for specific additional requested works and Policy and Resources budgets for additional Landlord maintenance items which can easily be included within the overall scheme.

4.3 Newtown Soberton Infant School

A design project appraisal for a scheme at this Infant School to provide a new hall and internal adaptations for a Nursery Unit was approved at the July 2005 meeting of the Executive Member for Policy and Resources.

Additional funding of £5,990 from the Education Capital Programme 2005 F&E budget has been added at pre-contract stage for additional furniture requirements.

5. Current Position

5.1 This section gives the summarised position of the major projects, which have already been approved by the Executive Members for Policy and Resources and Education. Those schemes with works on site are reported as being financially on target unless otherwise indicated elsewhere in this report.

5.2 Crescent Primary School

    A major scheme at this school to construct a two classroom and library extension was agreed at the February 2005 meeting of the Executive Member for Policy and Resources. Work was programmed to complete during March 2006, however, due to the late delivery of glulam beams the work will now complete during April 2006.

5.3 Mountbatten School and Language College

      A scheme to provide a new staff room, inclusion room and multi-agency space was approved a the April 2005 meeting of the Executive Member for Policy and Resources. Work was programmed to complete during February 2006, however, the contractor is currently reporting a delay to the contract which will result in a April 2006 completion. The current extension of time claim from the contractor is being investigated to ascertain the reason's for the delay to the agreed programme.

5.4 Netley Marsh Infant School

      As detailed above (in 3.5) this major scheme commenced on site during August 2005 and was due for completion during February 2006. Due to the late delivery of steel work it is now anticipated that work will complete during late March 2006, one month later than previously reported.

6. Pinewood Infant School, Farnborough

6.1 The Cabinet agreed on 13 December 2004 that Pinewood Infant School, which was largely destroyed by fire in March 2003, should be rebuilt as a one-form entry infant school (90 places) with language impairment resource provision. The project is included in the Children's Services Capital Programme 2006/07 at an estimated cost of £3.815m including furniture and equipment. £2.6m of the estimated cost is to be met from the County Council's Insurance Fund. The remaining £1.215m is to be met from the capital receipt due to Children's Services in 2006/07 from the sale of the site of the former Mayfield Infant School, Farnborough.

6.2 The planning application was submitted in January 2006 and the project appraisal will be submitted for approval during June 2006. It is proposed to commence construction of the new school at the end of July 2006.

6.3 Following the fire in March 2003, five temporary buildings, including administration, community spaces and classrooms, have been provided on the site. To enable the construction of the replacement school it is necessary to install a further double temporary classroom during the spring half term week, to allow the existing pre-school to decant from the remaining permanent building prior to the start of construction. The cost of the additional double classroom and associated enabling works is currently being confirmed but is estimated to be a maximum of £75k.

Conclusion

      The details of the major capital projects outlined in this report will provide greatly enhanced school accommodation and facilities.

Recommendations

1. That the position of the major projects being undertaken by the Director of Property, Business and Regulatory Services be approved.

2. That the additional funding added to the major capital project at Newtown Soberton Infant School, at pre contract stage, previously approved by the Executive Members' Education and Policy and Resources at design project appraisal stage, be approved.

3. That the proposal to install an additional double temporary classroom and undertake associated enabling works at Pinewood Infant School, Farnborough, to a maximum cost of £75k, prior to approval of the project appraisal, be approved.

Section 100 D - Local Government Act 1972 - background papers

The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.

NB the list excludes:

      1. Published works.

      2. Documents which disclose exempt or confidential information as defined in the act.

                    TITLE FILE

      Architect's plans Property Management Contract Reconciliation Statements Information Files, PBRS

      Tender schedules

Project Appraisal

I/PB&R/Committees/MajorMinorSelf-Funded?2006/March/MajorProjectsStatusReport

MAJOR PROJECT STATUS REPORT Appendix 1

School

Current Status

Start

Complete

Funding/

* Contract Sum

£

Source of Funding

£

Blackfield Primary School

- creation of 2.5fe Primary school by extending and remodelling existing Junior school

On site

Dec 05

Aug 06

* 1,498,208

Education Capital 05/06 1,185,345

Edu Early Years 05/06 34,483

Education contingency 46,552

School 231,828

1,498,208

Bridgemary Community School, Gosport

- new Exercise Space

Design

Jul 06

Dec 06

294,000

School 294,000

Broughton Primary School, Stockbridge

- new kitchen

On site

Mar 06

July 06

* 199,635

Education Capital 05/06 179,635

School 20,000

199,635

Costello Technology College, Basingstoke

- replacement maths / technology teaching block

On site

Nov 05

Feb 07

* 5,200,434

P&R Fire Re'statem't 05/06 4,870,434

Education Capital 05/06 250,000

P&R NDS Condition 05/06 80,000

5,200,434

Court Moor School, Fleet

- refurbish and extend Youth Block

Tender analysis

Apr 06

Jul 06

242,000

Edu - Youth Service 05/06 138,000

Edu - Early Years 05/06 59,000

School - Connexions 25,000

P&R NDS Condition 05/06 20,000

242,000

Cove Junior School, Farnborough

- three classroom extension, Music/Drama and kiln room

On site

Oct 05

May 06

* 804,202

add 10,000

814,202

Education Capital 05/06 717,000

School 54,202

P&R NDS Condition 05/06 43,000

814,202

The Crescent Primary School, Eastleigh

- two classroom and library extension

On site

Jul 05

Apr 06

* 827,050

Education Capital 05/06 628,550

School 53,500

HC3S 20,000

P&R NDS Condition 05/06 125,000

827,050

Crestwood Community School, Eastleigh

- Community Sports Hall, drama studio and Fitness Suite

On site

Oct 05

Jun 06

* 3,132,183

Capital Programme 05/06 3,132,183

Grayshott CE (C) Primary

- single storey extension and internal alterations

On site

Oct 05

May 06

* 525,000

add 32,728

557,728

Education Capital 05/06 365,000

School 192,728

557,728

Havant BESD School

- new BESD Secondary School

Design

Jun 06

Jul 07

4,910,000

Education Capital 05/06 712,000

TCF 3,056,000

Rachel Madocks receipt 671,000

Future land sales 471,000

4,910,000

The Henry Cort Community College, Fareham

- extension to staff room, two new offices, internal remodelling and refurbishment

On site

Aug 05

Mar 06

* 417,886

Education Capital 05/06 97,948

School 283,938

P&R NDS Condition 05/06 15,000

P&R Capital Repairs 05/06 2,000

P&R L'lords M. Works 05/06 12,000

P&R Ext. Landscaping 05/06 7,000

417,886

Hollywater School, Bordon

- new special school

On site

May 05

Dec 06

* 6,088,472

Edu Cap / TCF 05/06 4,887,472

P&R Capital Repairs 05/06 629,000

P&R Capital Receipt 572,000

6,088,472

John Hunt of Everest Community School, Basingstoke

- New School and Youth facility

Enabling -

Complete

On site

Aug 05

Jan 06

Nov 05

Apr 07

* 1,106,416

* 21,532,336

add 27,385

22,666,137

Capital Receipts 13,543,659

Developer's Contribution 2,383,824

B&D Borough Council 2,008,615

County Council 4,702,654

School 27,385

22,666,137

Lakeside School, Chandlers Ford

- refurb. boarding accommodation; demolish surplus boarding house; new teaching block and refurbish teaching accommodation

Complete

Complete

Phase 2

Jul 04

Nov 04

Jul 05

Aug 04

Apr 05

May 06

* 196,000

* 568,000

* 1,301,254

* 2,065,254

Education Mod'tion 04/05 1,565,000

Education Capital 04/05 261,254

P&R NDS Condition 04/05 49,000

P&R Fire Precautions 04/05 190,000

2,065,254

Minstead Rural Study Centre, Lyndhurst

- new residential building, extension to schoolhouse and removal of temps

On site

Dec 05

Jul 06

* 1,228,000

Education Capital 05/06 519,000

Temp Classroom Hire 05/06 28,000

New Opportunities Fund 487,000

Study Centre 100,000

New Forest District Council 26,000

P&R Landlords contribution 68,000

1,228,000

Mountbatten School and Language College

- new Staff Room, Inclusion room and Multi-agency space

On site

Jul 05

Apr 06

* 449,000

Edu. Capital - SEED 05/06 117,000

School 332,000

449,000

Netley Marsh Infant

- new classrooms and extended hall

On site

Aug 05

Mar 06

* 678,312

add 20,000

698,312

Education Capital 0506 595,381

School 62,931

P&R NDS Condition 05/06 40,000

698,312

Newtown Soberton Infant School

- new Hall and internal adaptations to create a Nursery Unit

On site

Mar 06

Hall -

Sep 06

Nursery -

Oct 06

* 546,990

NDS Modernisation 05/06 438,000

School 103,000

Education FF&E 05/06 5,990

546,990

Nightingale Primary School, Eastleigh

- extension to provide permanent classroom accommodation

- MUGA

Complete

Feb 05

Easter 06

Nov 05

Easter 06

* 1,201,663

NDS Modernisation 04/05 391,304

Contingency 55,173

Capital Receipt 646,552

School 108,634

1,201,663

Oak Lodge School, Dibden Purlieu

- drama room and music practice room

Design

Apr 06

Sep 06

241,000

School 241,000

Rachel Maddocks School, Waterlooville

- extension, internal alterations, refurbishment and repair

On site

Feb 05

Jun 06

* 346,963

Education Capital 05/06 204,000

School 136,259

P&R Capital Repairs 05/06 6,704

346,963

Rowner Youth Services, Gosport

- new Youth Facility

Tender analysis

Apr 06

Oct 06

346,027

Education Capital 06/07 88,027

P&R Capital Prog. 06/07 129,000

SRB 129,000

346,027

Saint Lawrence CE (C) Primary

- new hall, kitchen, link building and internal refurbishment

On site

Oct 05

Apr 06

* 599,485

add 43,500

642,985

Education Capital 05/06 599,485

School 43,500

642,985

South Baddesley CE (C) Primary

- phase 1 - new classroom and staffroom

- phase 2 - new hall and car park

Complete

On site

May 05

Sep 05

Oct 05

Mar 06

* 424,722

* 516,793

add 23,188

964,703

Education Capital 04/05 391,828

Education contingency 11,207

School 148,841

NDS Condition 05/06 65,000

P&R Capital Repairs 05/06 87,827

P&R Capital 05/06 260,000

        964,703

Staunton Park Community

- Healthy Living Centre

Complete

Jul 05

Mar 06

* 546,812

NDS Modernisation 04/05 70,862

School 53,950

Sport England 422,000

546,812

The Toynbee Community College, Chandlers Ford

- new Multi-Purpose Suite

On site

Nov 05

May 06

* 508,620

School 265,517

P&R Capital 05/06 200,000

Eastleigh Borough Council 43,103

508,620

Trosnant Infant and Junior Schools, Leigh Park

- Trospac full day-care provision

Negotiation

Apr 06

Aug 06

585,000

Education Capital 05/06 237,000

Sure Start (Children's Centre) 87,000

DfES general Sure Start 261,000

585,000

Waterside Primary School, Hythe

- remodel and refurbish existing school; construct classroom block and early years unit

On site

Nov 05

Jul 06

* 1,913,815

Education Capital 05/06 1,539,462

School 125,000

P&R Capital Repairs 05/06 25,246

P&R NDS Condition 05/06 224,107

1,913,815

West Tytherley C of E Primary, Salisbury

- classroom extension to replace temporary accommodation

Tender Analysis

Apr 06

Nov 06

906,473

Education Capital 05/06 866,473

School 40,000

906,473

Whitchurch CE (C) Primary

- two new classrooms, ICT Suite and corridor

Complete

Jul 05

Feb 06

* 515,000

add 29,967

544,967

Education Capital 04/05 431,000

School 106,967

P&R NDS Condition 05/06 7,000

544,967

Wildern School, Hedge End

- new Learning Centre

Tender Analysis

May 06

Dec 06

702,000

School 463,000

P&R Capital Repairs 06/07 50,000

Remainder tbc

702,000

Woolton Hill Junior School

- extension to library and hall store

Design

Jul 06

Nov 06

231,000

Education Capital 05/06 43,000

School 119,000

P&R Capital Repairs 06/07 69,000

231,000

          Appendix 2

Other Schemes in the Education Capital Programme

The following schemes are included in the Education 2005/ 06 and 2006/07 Capital Programmes and the Director of Property, Business and Regulatory Services is either currently, or shortly will be, progressing feasibility work for these. Where appropriate eg: - due to specific spend profiles or in order to meet an agreed programme of works, planning applications may be submitted for these schemes, prior to appraisals being presented to the Executive Member Education or Policy and Resources:

School Allocation

        (excluding fees)

          £'000

PRIMARY

Dowd's Farm Primary

3,695

Freegrounds Infant

517

New Whiteley Primary

1,240

King's Copse Primary

3,579

Pinewood Infant

3,182

Shamblehurst Primary

517

SECONDARY

Wildern School

216

SPECIAL

Baycroft School

261

Henry Tyndale School

486

Sundridge School

4,823

EDUCATION OTHER THAN AT SCHOOLS

Basingstoke School Plus

2,391

Woodlands Education Centre

3,967

NDS MODERNISATION

Burghclere Primary

443

Curdridge Primary 05/06

618

Greatham Primary

652

Hardley School

1,721

Micheldever Primary 05/06

1,240

Stanmore Primary 05/06

217

The Bridge Centre 05/06

830

TOTAL

30,595