Archived decisions
Hampshire County Council Executive Member - Education Item 23 March 2006 Micheldever CE Primary School, Micheldever
Report by the Director of Property, Business and Regulatory Services |
| How the conclusion in this report fits with the Corporate Strategy This scheme will impact on the delivery of all Corporate Aims, focusing most immediately on: Aim 5 - improving services: all users of the proposed new facilities will benefit from these proposals. |
Contact: Steve Clow Ext: 7858 e-mail: [email protected]
1 |
Summary |
1.1 |
Micheldever Church of England Primary School is a small rural village school, situated in the centre of Micheldever. There are currently 82 pupils (aged 4-11 years) on roll. The school is a Voluntary Controlled Primary School. |
1.2 |
The original school building is of traditional brick and flint Victorian construction. There are currently two temporary buildings (housing three classrooms), in poor condition, and the school has an undersized hall and other shortcomings when compared to current benchmark standards. |
1.3 |
It is now proposed to replace the temporary buildings with three purpose-built classrooms and a new hall. Unsightly kitchen and boiler room extensions will be demolished and replaced and a new library/resource and group room provided. |
1.4 |
The total estimated cost of the scheme is £1,815,000, excluding fees, and this investment will transform the quality of the buildings and facilities at this small village school. |
1.5 |
The Director of Property, Business and Regulatory Services has progressed the design of the proposed additional accommodation and the purpose of this report is to outline the design proposals and seek approval to the attached design project appraisal. |
2 |
Scope of the Works |
2.1 |
The proposed new accommodation will form a courtyard around two existing yew trees, with a new entrance hall and reception linking the new-build to the existing main school building. |
2.2 |
The accommodation will provide three new classrooms, a new hall, library/resource and group room. The existing school hall will be remodelled as the reception classroom, kitchen/servery and plant rooms. |
2.3 |
The scheme has been carefully designed to conserve and enhance the original school building (which is a Grade II Listed Building) and to site the new accommodation to provide a satisfactory relationship between old and new, whilst providing appropriate external spaces. |
2.4 |
The two existing yew trees will be protected before commencement of building works to ensure their continued health. |
3 |
Acquisition of Property Interests |
3.1 |
The development proposals envisage providing a permanent foul drainage connection to a nearby private sewerage treatment works owned by Winchester City Council. The pipe will cross third party land. Agreement, in principle, has been reached with the two landowners and detailed negotiations are in hand. If unsuccessful, drainage tanks will be installed within the existing school site. |
3.2 |
It is also proposed to create a small temporary playing field area for the duration of the works on adjoining third party land. Agreement, in principle, has been reached with the landowner and detailed negotiations are in hand. |
4 |
Funding and Timing |
4.1 |
The project will be funded as follows (all figures shown exclude fees): £ Capital Programme (NDS Modernisation) 05/06 (agreement sought to carry this forward into the 2006/07 Capital Programme) 1,241 Capital Programme (Primary Halls Block Vote) 362 School - devolved capital/fundraising 132 NDS Condition Funding 40 Policy and Resources Capital Repairs budget 40 1,815 |
Section 100 D - Local Government Act 1972 - background papers
The following documents disclose facts or matters on which this report, or an important part of it, is based and has been relied upon to a material extent in the preparation of this report.
NB the list excludes:
1 Published works
2 Documents which disclose exempt or confidential information as defined in the Act.
Title Location
Architect's plans PMIS file
Building Profile Reports TMH
Hampshire County Council
Building Design Project Appraisal |
Executive Member - Education
23 March 2006
Buildings, Land and Procurement Panel
4 April 2006
Executive Member - Policy and Resources
6 April 2006
Project: |
Micheldever CE Primary School, Micheldever | |
Hall and Classroom extension | ||
Commencement date: |
June 2006 | |
Completion date: |
October 2007 | |
Planned year of start in accordance with Capital Programme: |
2006/07 | |
Recommendation:
That the building design project appraisal for the Micheldever CE Primary School scheme be approved.
1 Finance
Capital Expenditure |
Current Estimate (at Nov 2004 prices) £'000 |
Capital Programme ( at Nov 2004 prices) £'000 |
Buildings |
1,815 |
1,603 |
Fees |
267 |
244 |
Land to be purchased |
_ |
_ |
Total |
*2,082 |
1,847 |
* The means by which the difference between the Current Estimate and the Capital Programme
allocation is to be met is shown in the table below.
Financial Provision for Total Scheme |
Buildings £'000 |
Fees £'000 |
Total cost £'000 |
1 From own Resources: |
|||
a) Capital Programme (NDS Modernisation) |
1,241 |
186 |
1,427 |
b) Capital Programme (Primary Halls Block Vote) |
362 |
58 |
420 |
c) School - devolved capital/fundraising |
132 |
13 |
145 |
d) Policy and Resources Capital Repairs budget |
40 |
5 |
45 |
e) NDS Condition Funding |
40 |
5 |
45 |
Total |
1,815 |
267 |
2,082 |
Building Cost - Net Cost (excluding abnormals) = £1,692 per m2
Due to the extensive nature of the alterations it is not appropriate to give a gross cost
Devolved Capital allocations £'000
2005/06 18
2006/07 22
2007/08 24
Total 64
Landlord funded work connected with this scheme
A P&R contribution of £40,000, excluding fees, is being made towards the cost of boiler replacement and drainage works.
Value of land already acquired for this project
The whole of this site is owned by Diocesan Trustees and not the County Council.
Revenue implications
(a) Employees £'000 |
(b) Other £'000 |
(a+b) *Net Current Expenditure £'000 |
(c) Capital Charges £'000 |
(a+b+c) Total Net Expenditure £'000 | |
Revenue Implications Additional+ /Reductions |
Nil |
4 |
4 |
112 |
116 |
Unit cost (£) (e.g. per place) |
- |
- |
- |
- |
- |
% variation to Committee's budget |
- |
- | |||
Number of additional Staff (fte) |
- |
- |
* The overall level of the revenue budget for funding schools will (from April 2006) be prescribed by central government, and capital projects have no bearing on the level of this budget. Therefore, this proposed project will have no bearing on the overall level of the Children's Services budget, extra costs and savings being met from the same overall schools' funding level.
Energy costs
The estimated annual energy consumption for the new accommodation will meet that required by current Building Regulations. It is anticipated that the increase in fuel cost for the school will be in the order of £2,484 per annum (£7.90 for each m² of new accommodation). The additional CO² consumption will be 21.8 tonnes per year
2 Details of site and existing infrastructure
Location/adjoining land and buildings
The school is located within the heart of the village and is surrounded by private housing.
Area including comparison with local/national standards
The total site area is 0.75 acres (0.304 hectares). The DfES guideline for a school of this size is 1.69 acres (0.685 hectares).
Access
The main vehicular and pedestrian accesses are from Church Street. It is proposed that the contractor will use the main vehicular access for the duration of the works.
Once within the school boundaries, pupils and staff will be clearly separated from construction traffic and activities. Deliveries and movement of plant will be restricted during the school day to ensure the safety of all those involved.
Existing buildings and temporary buildings
The main school building is of traditional brick and flint construction, dating from 1870. There are currently two temporary buildings on site which are in very poor condition and will be removed as part of the scheme. There are some semi-derelict brick sheds and outbuildings which will be demolished. Existing above-ground fuel tanks will be replaced with underground storage tanks.
Results of trial boreholes
The soils on this site comprise topsoil overlying gravely clay in turn overlying chalk.
Conventional trench fill foundations are considered appropriate, but will need to be much deeper than normal in some areas to allow for the effects of the adjacent trees.
Ground floor slabs will be suspended beam and block.
Mains services position
It is proposed to run a foul drain sewer via adjoining private land to a nearby existing sewage treatment plant owned by Winchester City Council. These negotiations are currently ongoing and if this option is not agreed, it will be necessary to install underground drainage tanks on the school site. Sufficient contingency has been included in the costs to cover either option at this stage.
A new electrical supply is required and gas supply will be from underground LPG tanks.
3 Scope of the Project
Type of project, layout and facilities provided
The proposed scheme will provide the following new accommodation:
· hall
· 3 classrooms
· storage areas
· staff and pupil wcs
· library/resource room
· group room
· kitchen, to include servery and wc
· plant room
· entrance hall - link to existing main building
The existing building will be adapted and refurbished to provide the following accommodation:
· reception classroom
· quiet room
· head teacher's office
· medical/interview room
· staff room/office
· staff/pupil wcs
· storage area
Places provided
90 replacement places.
4 The Proposed Building
Type of construction, finish and appearance
New-build construction will be of traditional masonry with red brick walls, pitched roofs will have plain clay tiles and other roofs over circulation areas will have a high-performance covering. Windows, doors and glazed screens will be of painted timber. All to complement the existing Grade II listed building.
Accessible facilities
The scheme has been designed with level/ramped access throughout.
One accessible wc will be provided as part of this scheme.
Heating and ventilation systems
Gas (LPG) fire condensing boilers serving under floor heating will heat the new and existing building.
Ventilation generally will be by natural means, with mechanical extract ventilation only where required.
Fire risk assessment
In consultation with the Hampshire Fire and Rescue Service, a fire risk assessment concludes that this is a low fire risk category building. Therefore a sprinkler system will not be installed.
Health and safety
A designer's risk assessment and a design health and safety plan, in accordance with Regulation 15 of the Construction Design and Management Regulations 1994, have been undertaken for the proposed scheme
5 External Works
Car parking
There will be no change to the existing parking arrangements.
Landscape proposals
It is proposed to reorganise the landscape layout by moving the existing adventure play area and reinstating the tarmac area on which the temporary buildings are currently located to create a suitable area of usable games and play space.
The internal courtyard area will be reorganised around the retained mature yew trees to create an outdoor teaching and story-telling space, whilst a dedicated early years area will be created at a lower level. The access will be widened and set at a gradient. The connections between spaces will be linked using pergola structures. There will also be a rationalisation of vehicular and pedestrian access to the front and side of the school.
Situation on site and environmental impact
This scheme incorporates the removal of some unsightly extensions made over the years to the rear of the building and also the temporary buildings located to the rear of the site, which have reached the end of their useful life. The scheme aims to conserve and enhance the original Victorian school building and the new accommodation has been designed to be sympathetic in manner.
The two yew trees will be protected throughout the works to ensure their safety and long-term future.
Evidence of bats has been found on site and a licence will be applied for and any necessary actions taken to ensure compliance with all statutory requirements. This has been built into the programme.
6 Planning
Planning approval was granted in February 2006.
7 Building management
Existing arrangements will apply to cleaning, catering, local management and maintenance arrangements.
8 Furniture and equipment
To be funded from the Children's Services Capital Programme Block Vote for Furniture and Equipment.
9 Professional resources
Architectural Services } Format Milton Architects
Quantity Surveying } Davis Langdon & Everest
Electrical and Mechanical Engineering } Giffords
Structural Engineering } R J Watkinson
10 Consultations
The following have been consulted during the development of the project: Headteacher and Governors of the school, Environment Department, Children's Services, Access Officer, local County Councillor.